PP.62 A manufacturer of solid state drives (SSDs) has projected the next six months of demand to be as shown the table below:

Supply/Demand Info Beginning Jan Feb Mar Apr May Jun
Forecast (demand) 48,000 52,000 60,000 54,000 58,000 64,000
Regular production
Overtime production
Subcontract production
Ending inventory 6,000
Hired employees
Fired employees
Total employees 200

Cost variables as as follows:

Cost Variables
Labor cost/hour $14
Overtime cost/unit $32
Subcontracting cost/unit $29
Holding cost/unit/month $8
Hiring cost/employee $2,500
Firing cost/employee $4,200

Here is some additional relevant (capacity) information:

Capacity Information
Total labor hours/SSD 2
Regular production units/employee/month 200
Max regular production/month 56,000
Max overtime production/month 4,000
Max subcontractor production/month 5,000

Given the above information (and don't overlook beginning number of employees and inventory levels in the first table), create a level production plan with only the use of regular production and no inventory left over at the end of the six-month period.

What is the regular production cost (over the six months from January through June) for a level production plan? (Display your answer to the nearest whole number.)

What is the total overtime production cost for this production plan? (Display your answer to the nearest whole number.)

What is the total subcontract cost for this production plan? (Display your answer to the nearest whole number.)

What is the total holding cost for this production plan? (Display your answer to the nearest whole number.)

What is the total hire cost for this production plan? (Display your answer to the nearest whole number.)

What is the total fire cost for this production plan? (Display your answer to the nearest whole number.)

What is the total cost (sum of all costs) for this production plan? (Display your answer to the nearest whole number.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

The total demand for 6 months is 336000 units. We have 6000 units in hand. This means the net requirement is 330000 units. This results in a monthly requirement of 55000 SSDs.

This means that we need a total of 55000/200 = 275 employees per month. This means we will need to hire 75 employees.The plan is shown below

Supply/Demand Info Beginning Jan Feb Mar Apr May Jun
Forecast (demand) 48,000 52,000 60,000 54,000 58,000 64,000
Regular production 55000 55000 55000 55000 55000 55000
Overtime production 0 0 0 0 0 0
Subcontract production 0 0 0 0 0 0
Ending inventory 6,000 13,000 16,000 11,000 12,000 9,000 0
Hired employees 75 0 0 0 0 0
Fired employees 0 0 0 0 0 0
Total employees 200 275 275 275 275 275 275

The regular production cost will be 55000*2*6 = 660000

Total overtime cost will be 0

Total subcontract cost will be 0

Total holding cost will be (based on ending inventory) = 61000*8 = 488000

Total hire cost will be = 75*2500 = 187500

Total fire cost will be = 0

Total cost will be = 660000+488000+187500 = 1335500

Add a comment
Know the answer?
Add Answer to:
I only have 1 hour left, please help!! PP.62 A manufacturer of solid state drives (SSDs)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • PP.72 A manufacturer of solid state drives (SSDs) has projected the next six months of demand...

    PP.72 A manufacturer of solid state drives (SSDs) has projected the next six months of demand to be as shown the table below: Supply/Demand Info Beginning Jan Feb Mar Apr May Jun Forecast (demand) 48,000 52,000 60,000 54,000 58,000 64,000 Regular production Overtime production Subcontract production Ending inventory 6,000 Hired employees Fired employees Total employees 200 Cost variables as as follows: Cost Variables Labor cost/hour $14 Overtime cost/unit $32 Subcontracting cost/unit $29 Holding cost/unit/month $8 Hiring cost/employee $2,500 Firing cost/employee...

  • PP.63 Jupiter, a large candy company, is having great success with its "Swan" family of candy...

    PP.63 Jupiter, a large candy company, is having great success with its "Swan" family of candy bars. Due to a number of factors they like to plan their production at least nine months into the future. The table below contains their demand projections (in tons) for April through December: Supply/Demand Info Beginning Apr May Jun Jul Aug Sep Oct Nov Dec Predicted sales 3,000 2,200 1,900 2,000 2,400 3,200 4,800 2,700 3,600 Regular production Overtime production Subcontract production Ending inventory...

  • PP.61 A small manufacturer of specialty welding equipment has developed a level production plan for the...

    PP.61 A small manufacturer of specialty welding equipment has developed a level production plan for the next four quarters, as seen below: Supply/Demand Info Pre-Q1   Q1 Q2 Q3 Q4 Forecast (demand) 4,600 4,600 3,680 6,440 Regular production 4,830 4,830 4,830 4,830 Subcontract production Ending inventory Hired employees 12 Fired employees Total employees 30 42 42 42 42 Additional Information: Capacity Information & Cost Variables    Production rate (units/employee/quarter) 115 Subcontractor capacity (units/quarter) 480 Regular production cost/unit $70 Holding cost/unit/quarter $14...

  • Show excel work PP.52 A manufacturer of solid state drives (SSDs) has projected the next six...

    Show excel work PP.52 A manufacturer of solid state drives (SSDs) has projected the next six months of demand to be as shown the table below Jan 48,00052,00060,00054,00058,00064,000 Feb Mar Apr May Jun Supply/Demand Info Beginning Forecast (demand) Regular production Overtime production Subcontract production Ending inventory Hired employees Fired employees Total employees Cost variables as as follows: 6,000 200

  • A small manufacturer of specialty welding equipment has developed a level production plan for the next...

    A small manufacturer of specialty welding equipment has developed a level production plan for the next four quarters, as seen below: Supply/Demand Info Pre-Q1   Q1 Q2 Q3 Q4    Forecast (demand) 2,300 2,760 3,680 5,980 Regular production 3,680 3,680 3,680 3,680 Subcontract production Ending inventory Hired employees 11 Fired employees Total employees 21 32 32 32 32 The table below shows additional relevant information: Capacity Information & Cost Variables    Production rate (units/employee/quarter) 115 Subcontractor capacity (units/quarter) 480 Regular production...

  • Jose Martinez of El Paso has developed a polished stainless steel tortilla machine that makes it...

    Jose Martinez of El Paso has developed a polished stainless steel tortilla machine that makes it a​ "showpiece" for display in Mexican restaurants. His forecast of capacity and demand​ follows: Assume that back-orders are not permitted. Using the transportation​ method, the total cost of the optimal plan is $_______. ​(enter your response as a whole​ number). Month 2 150 140 130 220 230 Demand Capacity Regular time Overtime 140 140 150 10 150 10 30 20 Subcontracting: 100 units available...

  • Please answer only the empty boxes (bottom table and the questions below it) The total subtracting cost= $_______ The t...

    Please answer only the empty boxes (bottom table and the questions below it) The total subtracting cost= $_______ The total inventory holding cost for January through August= $_____ The total​ cost, excluding normal time labor​ costs, for Plan E= $_____ Will thumps up if answers is correct! The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: 1,400 1,700 May 2,300 January February 2,300 June March 1,700 1,700 July April...

  • An electronics manufacturer makes video security systems for parking lots. The "Clear-Shot" is a system that pr...

    An electronics manufacturer makes video security systems for parking lots. The "Clear-Shot" is a system that provides 3-D graphic images of the parking lot. Operations manager of the company obtained forecasted demand for "Clear-Shot" and available capacity (in units) they have (shown below) to develope a four-month aggregate plan for manufaturing. Capacity & Demand Month 2 Month 1 Month 3 Month 4 Regular time Overtime 225 300 275 300 15 28 24 26 18 Subcontract 12 17 15 240 316...

  • Ram Roy's firm has developed the following supply, demand, cost, and inventory data Supply Available Regular...

    Ram Roy's firm has developed the following supply, demand, cost, and inventory data Supply Available Regular Time 30 30 40 Demand Period Overtime Subcontract Forecast 15 15 20 40 45 60 Initial inventory Regular-time cost per unit Overtime cost per unit Subcontract cost per unit Carrying cost per unit per month 20 units $100 $150 $200 $6 Assume that the initial inventory has no holding cost in the first period and backorders are not permitted Allocating production capacity to meet...

  • A manager has projected demand for the next six months (below). Given this information, prepare a...

    A manager has projected demand for the next six months (below). Given this information, prepare a LEVEL aggregate plan for production. Assume maximum regular time production is 350 units per month. Overtime is limited to 75 units per month. The limit for subcontracting is 400 per month. The company has a zero beginning inventory and cannot have ending inventory or a backlog at the end of the 6th period. Unit costs are as noted below. Regular Time Cost: $10/unit Overtime...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT