A large and growing retail chain is opening a new warehousing operation that will operate 8...

A large and growing retail chain is opening a new warehousing operation that will operate 8

hours per day. They expect 256 trucks to drop off and then pick up products each weekday.

Trucks enter each loading dock one

at a time and it takes 50 minutes to unload and then refill a

truck before it can leave. Each truck carries an average of 24 pallets of merchandise at any one

time.

Truck teams of two people are responsible for moving merchandise on and off of the trucks

and

tracking inventory received and sent. Each of these teams is assigned to a loading dock. For

every three truck teams, there is one extra employee that will cover breaks and help coordinate

work.Lift trucks are used to pick up merchandise from the loading docks and place it in its proper

storage area of the warehouse. On their return, these lifts bring other merchandise from the

warehouse and deliver it to the loading docks to later be placed on trucks for delivery. It takes an

average of 2.5 minutes for a lift truck to transport merchandise between the loading dock and the

storage areas (one way). Lifts are not assigned to specific loading docks and each can carry only

one pallet at a time.

Using the Naïve approach, calculate the minimum requirements for:

a)

The number of loading docks that need to be built (Facility requirements)

b)

The number of Lift trucks needed (Equipment requirements)

c)

The number of employees working as part of the truck teams (Labour requirements)

d)

How many more trucks could be serviced (if any) without having to build more loading

docks?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Number of trucks available - 256 trucks/ day

Number of hours per day - 8

Average time taken to refill and unload a truck - 50 minutes/ truck

Average number of pallets carried by each truck - 24 pallets

1) Number of docks required :

Number of trucks serviced in an 8-hour shift per dock

= 8 hours * 60 minutes / (50 minutes per truck + 2.5 minutes to transport)

= 480 / 52.5 = 9 trucks

For 256 trucks, number of docks required = 256 docks / 9 = 28.4 docks = 28 docks

2) Number of lift trucks needed :

Each dock has one lift truck. Hence, number of docks = Number of lift trucks

Number of lift trucks needed = 28

3) Number of employees working on the truck team :

As per the case, number of people working on one truck = 2

One person additional for every 3 trucks.

Total number of employees = 2 * 9 + 3 (one employee per 3 trucks)

= 21 employees

Add a comment
Know the answer?
Add Answer to:
A large and growing retail chain is opening a new warehousing operation that will operate 8...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Peoblem 110 saiato If a warehouse receive 40 trucks per day (each truck carries 36 pallets-loads). Using an standard time of 5 minutes for loading/unloading a pallet-load, what is the minimum numb...

    Peoblem 110 saiato If a warehouse receive 40 trucks per day (each truck carries 36 pallets-loads). Using an standard time of 5 minutes for loading/unloading a pallet-load, what is the minimum number of docks required. Peoblem 110 saiato If a warehouse receive 40 trucks per day (each truck carries 36 pallets-loads). Using an standard time of 5 minutes for loading/unloading a pallet-load, what is the minimum number of docks required.

  • The Europa Company has a large warehouse in Florida to store its inventory of goods until...

    The Europa Company has a large warehouse in Florida to store its inventory of goods until they are needed by the company’s many furniture stores in that area. A single crew with four members is used to unload and/or load each truck that arrives at the loading dock of the warehouse. Management currently is downsizing to cut costs, so a decision needs to be made about the future size of this crew. Trucks arrive randomly at the loading dock at...

  • the pre 5.22, The Seaboard Shipping Company has a warehouse terminal in ta Spartanburg, South Carolina....

    the pre 5.22, The Seaboard Shipping Company has a warehouse terminal in ta Spartanburg, South Carolina. The capacity of each terminal dock is three trucks. As trucks enter the terminal, the drivers receive num- bers, and when one of the three dock spaces becomes available, the truck with the lowest number enters the vacant dock. Truck arrivals are Poisson distributed, and the unloading and loading times (service th of d times) are exponentially distributed. The average arrival rate at the...

  • Hi HA1-R12 (Home assignment #1 based on theRIchärdsbookOhipterawmarehouseoostn Calculate answers to all the questions below. Then...

    Hi HA1-R12 (Home assignment #1 based on theRIchärdsbookOhipterawmarehouseoostn Calculate answers to all the questions below. Then go to Assessments Quizzes on Western Online and enter the answers into HA1-R12. Each answer is worth 2 points. You will have two attempts. Exercise 1. RO A warehouse manager is considering purchasin g an electric forklift for loading/unloading and handling of pallets on the dock, the operations that are currently performed with a hand pallet truck. The cost of a forklift is $20,000...

  • Problem: Rockford Corporation is a wholesale plumbing supply distributor. The corporation was organized in 1981, under...

    Problem: Rockford Corporation is a wholesale plumbing supply distributor. The corporation was organized in 1981, under the laws of the State of Illinois, with an authorized capitalization of 10,000 shares of no-par common stock with a stated value of $30 per share. The common stock is sold over the counter in the local area. You have been hired as of Friday, December 26, 2014, to replace the controller, who has resigned. As controller, you are responsible for the corporation’s accounting...

  • Three days before Hurricane Harvey hit Texas, hardware retailer Home Depotreceived an alert from a weather...

    Three days before Hurricane Harvey hit Texas, hardware retailer Home Depotreceived an alert from a weather service and activated its disaster-response plan to get supplies to those in the storm’s path, while turning a profit, too. Over the next three days—as Harvey gained power and made landfall early on Saturday—the world’s largest home improvement retailer set up a temporary hurricane command center at its Atlanta headquarters. It told managers to freeze prices and move plywood, generators, chainsaws and other storm-related...

  • Help needed for Project procurement to answer Questions 1-10: Building Trust   Pauly Shore is a junior...

    Help needed for Project procurement to answer Questions 1-10: Building Trust   Pauly Shore is a junior procurement manager for the Goldwell Restaurant Group. He is responsible for the procurement of IT commodities for the data center. After months of negotiating with the three best and lowest-priced bidders for the computer paper contract, Pauly selected Frankie’s Paper Company.  Pauly’s decision was made after a round of golf at Frankie’s country club. On the eighteenth hole, Frankie extended his hand to Pauly and...

  • 10. Write a one-page summary of the attached paper? INTRODUCTION Many problems can develop in activated...

    10. Write a one-page summary of the attached paper? INTRODUCTION Many problems can develop in activated sludge operation that adversely affect effluent quality with origins in the engineering, hydraulic and microbiological components of the process. The real "heart" of the activated sludge system is the development and maintenance of a mixed microbial culture (activated sludge) that treats wastewater and which can be managed. One definition of a wastewater treatment plant operator is a "bug farmer", one who controls the aeration...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT