Question

The director of continuing education at Bluebird University just approved the planning for a sales training...

The director of continuing education at Bluebird University just approved the planning for a sales training seminar. Her administrative assistant identified the various activities that must be done and their relationships to each other as shown below.

Time Estimates

Activity

Description

Immediate

Predecessor(s)

Optimistic

Most likely

Pessimistic

A

Prepare course outline

None

3

4

5

B

Identify potential teachers

None

4

6

8

C

Send potential students course outline

A

8

10

12

D

Select teacher

B

2

3

4

E

Register students

C

4

8

9

F

Select classroom

D, E

1

2

6

G

Notify students and teacher of class location

F

2

4

6

  1. Draw the project network diagram
  2. Identify all the paths through the network and their lengths
  3. Identify all the critical activities and path. How long will the entire project take?
  4. The director wants to conduct the seminar 30 days from now. What is the probability that everything will be ready in time?
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Te = (4*Tm + To+Tp)/6

Var = [ (Tp-To)/6}2

activity To Tm Tp Te (Var)^0.5 Var
A 3 4 5 4 0.333333 0.111111
B 4 6 8 6 0.666667 0.444444
C 8 10 12 10 0.666667 0.444444
D 2 3 4 3 0.333333 0.111111
E 4 8 9 7.5 0.833333 0.694444
F 1 2 6 2.5 0.833333 0.694444
G 2 4 6 4 0.666667 0.444444

a.

There are two paths in the diagram

ACEFG with length = 28 ( this is critical path)

BDFG with length = 15.5

Variance of the critical path = 2.388

SD of the critical path = (Var)1/2

= 1.545

The activities on critical path are A, C, E, F, G and the duration is 28.

Probability that the project will finish before 30 days is given by

z = value in case - mean / SD

= 30-28 / 1.545 =1.294

which gives probability of 0.902

Add a comment
Know the answer?
Add Answer to:
The director of continuing education at Bluebird University just approved the planning for a sales training...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • (15. Doug Casey is in charge of planning and coordinating next spring's sales management training program...

    (15. Doug Casey is in charge of planning and coordinating next spring's sales management training program for his company. Doug listed the following activity information for this project: Immediate Predecessor M Time (weeks) Most Probable Activity Optimistic 1.5 2.0 Pessimistic 2.5 2.0 2.5 6.0 2.0 Description Plan topic Obtain speakers List meeting locations Select location Finalize speaker travel plans Make final check with speakers Prepare and mail brochure Take reservations Handle last-minute details BD Ε B, D G F, H...

  • uction needs to complete construction of Shopping Mall project, which is start in August. They are...

    uction needs to complete construction of Shopping Mall project, which is start in August. They are concerned with the completion time. Some of the ighly unreliable. List of activities and their optimistic, pessimistic, and most ion times in weeks) are given in following table: Optimistic Most Likely Pessimistic E(t) 3 5 9 13 11 0.1111 2.7778 7 Immediate Predecessor(s) None A None None AC D, E D, E F G F DF 2 6 9 5 10 6 5 2...

  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • Problem 9-09 (Algorithmic) At a local university, the Student Commission on Programming and Entertainment (SCOPE) is...

    Problem 9-09 (Algorithmic) At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully produce this rock concert, SCOPE has listed the requisite activities and related information in the following table (duration estimates measured in days). Immediate Most Activity Predecessor(s) Optimistic Probable Pessimistic A: Negotiate contract with - 9 10 11 selected musicians B: Reserve site - 7 9 11 C: Manage travel logistics A...

  • Complete an AON network diagram based on the scenario below. Make sure you respond to each of the...

    Complete an AON network diagram based on the scenario below. Make sure you respond to each of the following five requirements. Construct an AON diagram using the process described in the videos. Calculate the estimated time for each activity using the three estimates provided. Determine the length of all paths and identify which path is the critical path. During the play, one of the activities on the critical path is delayed by one day. Is this serious? Qualitatively discuss the...

  • Florida Power & Light is attempting to modernize the meters placed at people houses. The company...

    Florida Power & Light is attempting to modernize the meters placed at people houses. The company Operations Manager, Mr. Jacob Marina, has asked for your assistance in preparing part of the project plan. Mr. Marina has identified the tasks, durations (in days), and predecessor relationships, and provides them in the following table: Immediate Most Activity Predecessor(s) Optimistic Likely Pessimistic A -- 1 2    4 B A 2 4    8 C B 3 5 15 D C 3 5 12 E...

  • Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their...

    Pik-Fast, a chain of convenience stores, is planning to open a new store.  The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...

  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Immediate Predecessor Activity A B С D E...

  • 1. The activities needed for a new project your company is undertaking are listed in the...

    1. The activities needed for a new project your company is undertaking are listed in the following table. ACTIVITY IMMEDIATE PREDECESSOR(S) A ---- B ---- C A D A, B E B F C, D, E G D, E H F I F, G J G The activity times were determined for the project, and were as below. ACTIVITY ACTIVITY TIME (days) A 11 B 9 C 7 D 12 E 8 F 9 G 10 H 6 I 7...

  • You have recently been hired to help with planning for a music festival in Sydney, Australia...

    You have recently been hired to help with planning for a music festival in Sydney, Australia planned for late December 2020. Much still needs to be done in order for the event to go ahead. As the project manager working with the city, you are tasked with determining whether it is feasible to put on the event by the proposed date. The following activities would have to be undertaken before the festivities. Activity A B C D E F G...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT