For project A, the change in net working capital is expected to be 900 dollars at time 0, the cash flow effect from the change in net working capital is expected to be -300 dollars at time 1, and the level of net working capital is expected to be 1,600 dollars at time 2. What is the cash flow effect from the change in net working capital expected to be at time 2?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

If Cash flow effect from change in NWC is - 300 means Change NWC is $ 300

NWC at Time 1 = NWC at Time 0 + Change in NWC at Time 1

= $ 900 + $ 300

= $ 1200

Change IN NWC at Time2 = NWC at Time 2 - NWC at Time 1

= $ 1600 - $ 1200

= $ 400

Cash flow effect from change in NWC is -$ 400

Add a comment
Know the answer?
Add Answer to:
For project A, the change in net working capital is expected to be 900 dollars at...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • For project A, the change in net working capital is expected to be 400 dollars at...

    For project A, the change in net working capital is expected to be 400 dollars at time 0, the cash flow effect from the change in net working capital is expected to be -500 dollars at time 1, and the level of net working capital is expected to be 1,400 dollars at time 2. What is the cash flow effect from the change in net working capital expected to be at time 2?

  • For project A, the cash flow effect from the change in net working capital is expected...

    For project A, the cash flow effect from the change in net working capital is expected to be 100 dollars at time 2, the level of net working capital is expected to be 500 dollars at time 0, and the level of net working capital is expected to be 1,600 dollars at time 2. What is the cash flow effect from the change in net working capital expected to be at time 1?

  • For project A, the cash flow effect from the change in net working capital is expected...

    For project A, the cash flow effect from the change in net working capital is expected to be 100 dollars at time 2 and the level of net working capital is expected to be 1,800 dollars at time 1. What is the level of current assets for project A expected to be at time 2 if the level of current liabilities for project A is expected to be 1,600 dollars at time 2?

  • For project A, the cash flow effect from the change in net working capital is expected...

    For project A, the cash flow effect from the change in net working capital is expected to be -900 dollars at time 2 and the level of net working capital is expected to be 1,700 dollars at time 1. What is the level of current liabilities for project A expected to be at time 2 if the level of current assets for project A is expected to be 3,000 dollars at time 2?

  • For project A, the cash flow effect from the change in net working capital is expected...

    For project A, the cash flow effect from the change in net working capital is expected to be -700 dollars at time 2 and the level of net working capital is expected to be 1,500 dollars at time 2. What is the level of current liabilities for project A expected to be at time 1 if the level of current assets for project A is expected to be 7,200 dollars at time 1?

  • For project A, the cash flow effect from the change in net working capital is expected...

    For project A, the cash flow effect from the change in net working capital is expected to be -500 dollars at time 2 and the level of net working capital is expected to be 1,900 dollars at time 2. What is the level of current assets for project A expected to be at time 1 if the level of current liabilities for project A is expected to be 5,000 dollars at time 1?

  • For project A, the cash flow effect from the change in net working capital is expected...

    For project A, the cash flow effect from the change in net working capital is expected to be -100 dollars at time 2 and the level of net working capital is expected to be 1,700 dollars at time 1. What is the level of current assets for project A expected to be at time 2 if the level of current liabilities for project A is expected to be 2,200 dollars at time 2?

  • The project requires a level of net working capital in the amount equal to 12% of...

    The project requires a level of net working capital in the amount equal to 12% of the next year’s sales. Any increase in NWC is a negative cash flow, and any decrease is a positive cash flow. This project has a 4-year operating life, so any NWC expenditures will be recovered in Year 4. (That is, accounts receivables are received and inventories are drawn down.) Year 0 Year 1 Year 2 Year 3 Year 4 Sales $250,000 $257,500 $265,225 $273,188...

  • A project requires an increase in net working capital of $425,000 at time 0 that will...

    A project requires an increase in net working capital of $425,000 at time 0 that will be recovered at the end of its 20 year life. If opportunity cost of capital is 12%, what is the effect on the NPV of the project? Enter your answer rounded to two decimal places. Effect on NPV= Number

  • On the cash flow statement, there is "Change in Net Working Capital". Can change in "Net...

    On the cash flow statement, there is "Change in Net Working Capital". Can change in "Net Working Capital" be broken up into "Accounts Payable" and "Accounts Receivable". If so, where would accounts like PREPAID EXPENSES and DEFERRED REVENUE? Would they be considered Accounts Receivable? What about ACCRUED EXPENSES? Would an accrued expense be considered A/P?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT