LO. 4 (Cost Accumulations;assigning costs to jobs)

Mystic Inc. uses a job order costing system and applies overhead to jobs at a predetermined rate of $4.25 per direct labor dollor. During April 2010, the company spent$29,600 on direct material and $3,900 on direct labor for Job # 344. Budgeted factory overhead for the company for the year was $1,275,000.

a. How did Mystic Inc. compute the predetermined overhead rate for 2010?
B. Journalize the application of overhead to all jobs, assuming that April's total direct labor cost was $22,700.
c. How much overhead was assigned to Job #344 during April?
d. Job #344 had a balance of $18,350 on April 1. What was the April 30 balance?
1 0
Add a comment Improve this question Transcribed image text
Answer #1
a. How did Mystic Inc. compute the predetermined overhead rate for 2010?
Over head rate =
For 2010 ,the Over head cost will be allocated :
= Pre determined over head rate * Laborcost (allocation base)
= $4.25 * 3900 per dollar of direct labor
= $16575
For job 344, The over head cost = $16575

B. Journalize the application of overhead to all jobs, assuming that April's total direct labor cost was $22,700.
Then the allocated over head cost will be for april month :
= Pre determined over head rate * Labor cost (allocation base)
$4.25*22700
= $96475

c. How much overhead was assigned to Job #344 during April?
Asigned Over head for job 344 = $4.25*$3900
= $16575


The balnce of $18350 is actual over head incurred for job 344
But applied over head = $16575
The balance is under applied = [ 18350-16575]
= $1775

Manfacturing Over head

Actual over head

$18350

Applied over head

$16575

Under applied

1775

$18350

$18350

The journal entry to eliminate the under applied amount:
Cost of goods sold

$1775

Manfacturing Over head

$1775

The totla cost for job 344 as follows :

$

Direct Material

$29600

Direct Laobor

$3900

Over head

$16575

Cost of goods sold (Under applied)

$1775

Total

$51850


Add a comment
Know the answer?
Add Answer to:
LO. 4 (Cost Accumulations;assigning costs to jobs)
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • apter 21 E2-11 (Algo) Calculating Cost of Jobs in Work in Process, Finished Goods, and Cost...

    apter 21 E2-11 (Algo) Calculating Cost of Jobs in Work in Process, Finished Goods, and Cost of Goods Sold [LO 2- Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April Jobs A and B were in process at the beginning of April....

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...

    Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...

  • E2-11 (Algo) Calculating Cost of Jobs in Work in Process, Finished Goods, and Cost of Goods...

    E2-11 (Algo) Calculating Cost of Jobs in Work in Process, Finished Goods, and Cost of Goods Sold [LO 2- Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A...

  • 9.09 points Jenkins Company uses a job order cost system with overhead applied to jobs on...

    9.09 points Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during Apri, but not sold. Job...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT