Question

4force 000 lbf 001 0.002 ,sec 1000lbf 5. A load cell (second-order model) has the specifications as follows Undamped natural

0 0
Add a comment Improve this question Transcribed image text
Answer #1
  • project network diagram of above project is shown below.

    path 1 time 98 10 6 25 path 2 time 90 95 20 12 30 15 7 end 4 1 2 start 5 30 15 10 15 5 critical path - path 3 -> 1->2->5->8->

    The project has 3 paths.

    1. Start -> 1 -> 2 -> 3 -> 6 -> 9 -> 11 -> End, time: 98 days.
    2. Start -> 1 -> 2 -> 4 -> 7 -> 9 -> 11 -> End, time: 90 days.
    3. Start -> 1 -> 2 -> 5 -> 8 -> 10 -> 11 -> End, time: 115 days.

    c)

    The critical path is the path has longest path . In the above network 3 rd path is the critical path with time = 115

    The critical path of the project => start -> 1 -> 2 -> 5 -> 8 -> 10 -> 11 -> end => time = 115.

    b) slack (SL) or float of the path is defined as delaying time to complete the waiting time.i.e difference between critical path time and time for the corresponding path.

    -> SL of first path = critical path time - first  path time = 115 - 98 = 17

    -> SL of second path = critical path time - second path time = 115 - 90 = 25

    -> SL of critical path always zero.

    Calculating Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each node in the network

    Calculating Early Start (ES), Early Finish (EF) for each node in the path 1

    -> Using password pass, ES and EF are calculated from starting node.

    ES of initial node always starts with 1 ,because every project starts from first day.

    So , ES of node 1 = 1

    formula for ES = EF of previous node + 1 (from second node onwards)

    formula for EF =  Activity time + ES of the node - 1 .

    S0, EF of node 1 = 30 + 1` - 1 = 30.

    formula for ES = EF of previous node + 1

    ES of node 2 = 30 +1 =31

    EF of node 2 = 20 + 31` - 1 = 50.

    ES of node 3 = 50 +1 =51

    EF of node 3 = 25 + 51` - 1 = 75.

    ES of node 6 = 75 +1 =76

    EF of node 6 = 10 + 76` - 1 = 85.

    ES of node 9 = 85 +1 =86

    EF of node 9 = 8 + 86` - 1 = 93

    ES of node 11 = 93 +1 =94

    EF of node 11 = 5 + 94` - 1 = 98.

    Calculating Early Start (ES), Early Finish (EF) for each node in the path 2

    -> Using password pass, ES and EF are calculated from starting node.

    ES of initial node always starts with 1 ,because every project starts from first day.

    So , ES of node 1 = 1

    formula for ES = EF of previous node + 1 (from second node onwards)

    formula for EF =  Activity time + ES of the node - 1 .

    S0, EF of node 1 = 30 + 1` - 1 = 30.

    formula for ES = EF of previous node + 1

    ES of node 2 = 30 +1 =31

    EF of node 2 = 20 + 31` - 1 = 50.

    ES of node 4 = 50 +1 =51

    EF of node 4 = 15 + 51` - 1 = 65.

    ES of node 7 = 65 +1 =66

    EF of node 7 = 12 + 66` - 1 = 77.

    ES of node 9 = 77 +1 =78

    EF of node 9 = 8 + 78` - 1 = 85

    ES of node 11 = 85 +1 =86

    EF of node 11 = 5 + 86` - 1 = 90.

    Calculating Early Start (ES), Early Finish (EF) for each node in the path 3

    -> Using password pass, ES and EF are calculated from starting node.

    ES of initial node always starts with 1 ,because every project starts from first day.

    So , ES of node 1 = 1

    formula for ES = EF of previous node + 1 (from second node onwards)

    formula for EF =  Activity time + ES of the node - 1 .

    S0, EF of node 1 = 30 + 1` - 1 = 30.

    formula for ES = EF of previous node + 1

    ES of node 2 = 30 +1 =31

    EF of node 2 = 20 + 31` - 1 = 50.

    ES of node 5 = 50 +1 =51

    EF of node 5 = 30 + 51` - 1 = 80.

    ES of node 8 = 80 +1 =81

    EF of node 8 = 15 + 81` - 1 = 95.

    ES of node 10 = 95 +1 =96

    EF of node 10 = 15 + 96` - 1 = 110

    ES of node 11 = 110 +1 =111

    EF of node 11 = 5 + 111` - 1 = 115

    Calculating Late Start (LS), Late Finish (LF) for each node in the path 1

    -> Using backword pass, LS andLF are calculated from ending node.

    LF of last node always starts with critical path time ,because every project not completes before critical time.

    So , LF of node 11 = 115

    formula for LF = LS of successor activity – 1 (from next node onwards)

    formula for LS =  LF of activity – activity time + 1 .

    So, LS of node 11 = 115 - 5 + 1` = 111

    LF of node 9 = 111 - 1 = 110

    LS of node 9 = 110 - 8 + 1 = 103

    LF of node 6 = 103 - 1 = 102

    LS of node 6 = 102 - 10 + 1 = 93

    LF of node 3 = 93 - 1 = 92

    LS of node 3 = 92 - 10 + 1 = 83

    -> node 2 has 3 successor nodes , So which node has least LS will be taken as LF of successor activity.

    since edge 2<->4 is least .so Late start of node 2 is 30 + 20 + 15 +1 = 66 (it will be got LS from path 2)

    LF of node 2 = 66 - 1 = 65

    LS of node 2 = 65 - 15 + 1 = 51

    LF of node 1 = 51 - 1 = 50

    LS of node 1 = 50 - 20 + 1 = 31

    => similarily for path2 and path3 can be calculated.

    Comment

Practice with similar questions

Q:

Load cells measure force using internal strain gages. A properly designed load cell has a very small mass compared to the effective mass of the load. The load cell and its load operate together as a second-order dynamic system. A load cell has a range of 0 to 500. lbf and a maximum deflection of 0.0100 inches. The effective mass of the load is 20.0 lbm, and the damping ratio is...

A:

See answer

100% (1 rating)

Q:

Load cells measure force using internal strain gages. A properly desi gned load cell has a very small mass compared to the effective mass of the load. The load cell and its load operate together as a second-order dynamic system. A load cell has a range of 0 to 500. lbf and a maximum deflection of0.0100 inches. The effective mass of the load is 20.0 lbm, and the damping ratio is...

A:

See answer

100% (1 rating)

Show more

O

Add a comment
Know the answer?
Add Answer to:
4force 000 lbf 001 0.002 ,sec 1000lbf 5. A load cell (second-order model) has the specifications ...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Do only parts C and D 1. A second-order system has the following transfer function that...

    Do only parts C and D 1. A second-order system has the following transfer function that describes its response: F(s)- s2 +as + 9 A. For a -3, calculate the following performance specifications of the system: Natural frequency (on) Damping ratio( Estimated rise time and settling time with ±5% change (tr, ts) Estimated overshoot (MP) . B. Label (a) ±5% range of steady state, (b) tr, (c) ts, and (d) MP on the step response curve below (You may also...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT