Question

38. Calculate the pieces per hour and the hours per unit for the following: Hours per 1,000 Pieces Time StandardPieces per Ho

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

38)

Time standard is given in minutes; it means standard time required to process a unit.

Pieces per hour = (60 minutes/hour)/(standard time in minutes/piece)

Hours per piece = (standard time in minutes/piece) / (60 minutes/hour)

Standard time (minutes)

Pieces per hour

Hours per Piece

1.000

60/1 = 60

1/60 = 0.0166

0.500

120

0.0083

0.167

359.28

0.0027

2.500

24

0.0416

0.650

92.3

0.0108

0.050

1200

0.0008

Add a comment
Know the answer?
Add Answer to:
38. Calculate the pieces per hour and the hours per unit for the following: Hours per 1,000 Piece...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A Plant Manager who has worked for a manufacturing facility for 32 years operates the plant...

    A Plant Manager who has worked for a manufacturing facility for 32 years operates the plant as follows: •Two eight (8) hour shifts per day •Two 10-minute breaks per shift •10 minute clean-up allowed each shift •Unpaid 30 minute lunch •10,000 pieces of inventory •95,000 packages are shipped 20 days per month •2 day lead time for all material •5 minute clean up before lunch •5 minute lag after Lunch •15 minute meeting at start of each shift Help this...

  • CSM for HW 4 to calculate takt time, let's assume the following: 8.5 working hours per...

    CSM for HW 4 to calculate takt time, let's assume the following: 8.5 working hours per day, 30 minute lunch, and two 10 minute breaks, 30 day shipping per month. You can propose the total cycle time for the FSM. Forecost Altono Costing Supplies Forecast XYZ Weekl control Assembly Weekly otal 20,000 part/mon ,000 A 2,000 4,000 C Weekly schedule Assembly A, B Raw costings 6 days A 1800 Predut 8-600 Uptrne 97% 500 1000 Ch 4 Ume-65%--ll A 750...

  • KRM 6.12 Figure 6.15 provides a new current state value stream map for the family of...

    KRM 6.12 Figure 6.15 provides a new current state value stream map for the family of retainers at the Jensen Bearings, Inc. firm described in Example 6.1. This map depicts the value stream after Kline Steel agrees to accept daily orders for steel sheets and Jensen Bearings continues to deliver the finished goods on a daily basis. Operators work 5 days/week, one shift/day, 8 hours per shift with two 30 minute lunch breaks. Figure 6.15 New Current State Value Stream...

  • An assembly operation is to be done in a single shift, 8 hours per day and...

    An assembly operation is to be done in a single shift, 8 hours per day and 10% allowed for breaks (PF&D). The operators are expected to have an 85% performance and the following parts are required: Part X, requirement is 10,000 per week, at 100% one operator can produce 150 pieces per hour. Part Y, requirement is 15,000 per week, at 100% one operator can produce 220 pieces per hour. Part Z, requirement is 20,000 per week, at 100% one...

  • 1. Suppose an oil pump is producing 800 gallons per hour for the first 5 hours...

    1. Suppose an oil pump is producing 800 gallons per hour for the first 5 hours of operation. For the next 4 hours, the pumps production is increased to 900 gallons per hour, and then for the next 3 hours, the production is cut to 600 gallons per hour. Gollow how a) Make a graph modeling this situation. b) The term "area under a graph" is the area between the graph and the horizontal axis. Find the area under the...

  • Cycle Time and Velocity Norton Company has the following data for one of its production departments: Theoretical velocity: 180 units per hour Productive minutes available per year: 62,000,000 A...

    Cycle Time and Velocity Norton Company has the following data for one of its production departments: Theoretical velocity: 180 units per hour Productive minutes available per year: 62,000,000 Annual conversion costs: $372,000,000 Actual velocity: 72 units per hour Required: 1. Calculate the actual conversion cost per unit using actual cycle time and the standard cost per minute. Round your actual cycle time answer to three decimal places and your cost per unit answer to the nearest cent. Actual cycle time...

  • Overall Equipment Effectiveness Exercise for Case Study E Directions: Using your Overall Equipment Effectiveness Calculation Worksheet and th information provided below, determine the Overall Equ...

    Overall Equipment Effectiveness Exercise for Case Study E Directions: Using your Overall Equipment Effectiveness Calculation Worksheet and th information provided below, determine the Overall Equipment a typical Assembly plant for Availability Assumptions: At a typical plant, the constraint in the Widget production process is the machining line. The following information applies to the line for the week of June 5 through June 11. The line was schedulėd to run two &-bour shifts Monday through Friday, and one 9-hour shift on...

  • cost sheet for Largo Corp, showed the following material cost related to one unit of produet:...

    cost sheet for Largo Corp, showed the following material cost related to one unit of produet: 4pieces at $4 per piece $16 per unit During February 19X1,10,000 units were produced.The costs recorded showed the following Purchase of material 8000 pieces at $3.80 Issue of material 43,000 pieces Determine the material Give the significance and possible explanation of each materials variance What are some causes of unfavorable materials purchase price variances? The purchasing department of a large corporation using the responsibility...

  • 1) Following is cost structure of an independent comic book publisher:     Fixed cost = 75,000...

    1) Following is cost structure of an independent comic book publisher:     Fixed cost = 75,000     Variable cost = 8.00 per book     Selling price = 13.00 per book Compute the following: How many books have to be sold to make a profit of 2000 dollars? (3 points) The publisher has an estimate of demand of 5000 books. At what selling price would the publisher break even? (6 points) #2) TransCanada Corp. is in the business of manufacturing toys...

  • 2. Set up a ratio to represent the following: One-half of an hour (hours) to 18...

    2. Set up a ratio to represent the following: One-half of an hour (hours) to 18 minutes (Hint: hour: hour or minute : minute) 3. The cost of a unit is made up of $120.00 direct material cost, $80.00 direct labour cost, and S20.00 overhead. What is the ratio that exists between the three elements of cost? 4. Departments A, B, and C occupy floor space of 310, 120 and 475 square meters respectively. If the total rental for the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT