Aggregate Production Plan | ||||||||
Month | Demand | Regular Time Production | Over- time | Sub-conract | Inventory | No. of Workers | No. Hired | No. Fired |
50000 | 1250 | |||||||
January | 1000000 | 1200000 | 0 | 0 | 250000 | 1250 | 0 | 0 |
February | 1100000 | 1200000 | 0 | 0 | 350000 | 1250 | 0 | 0 |
March | 1000000 | 1200000 | 0 | 0 | 550000 | 1250 | 0 | 0 |
April | 1200000 | 1200000 | 0 | 0 | 550000 | 1250 | 0 | 0 |
May | 1500000 | 1200000 | 0 | 0 | 250000 | 1250 | 0 | 0 |
June | 1600000 | 1200000 | 150000 | 0 | 0 | 1250 | 0 | 0 |
July | 1600000 | 1200000 | 150000 | 0 | 0 | 1250 | 0 | 0 |
August | 900000 | 1185600 | 0 | 0 | 285600 | 1235 | 0 | 15 |
September | 1100000 | 1185600 | 0 | 0 | 371200 | 1235 | 0 | 0 |
October | 800000 | 1185600 | 0 | 0 | 756800 | 1235 | 0 | 0 |
November | 1400000 | 1185600 | 0 | 0 | 542400 | 1235 | 0 | 0 |
December | 1700000 | 1185600 | 22000 | 0 | 50000 | 1235 | 0 | 0 |
Total | 14900000 | 14328000 | 322000 | 0 | 0 | 15 | ||
Costs | ||||||||
Month | Material | Regular Time | Over- time | Sub-contracting | Inventory Holding | Hiring | Firing | |
January | 20000000 | 4000000 | 0 | 0 | 750000 | |||
February | 22000000 | 4000000 | 0 | 0 | 1050000 | |||
March | 20000000 | 4000000 | 0 | 0 | 1650000 | |||
April | 24000000 | 4000000 | 0 | 0 | 1650000 | |||
May | 30000000 | 4000000 | 0 | 0 | 750000 | |||
June | 32000000 | 4000000 | 750000 | 0 | 0 | |||
July | 32000000 | 4000000 | 750000 | 0 | 0 | |||
August | 18000000 | 4000000 | 0 | 0 | 856800 | |||
September | 22000000 | 4000000 | 0 | 0 | 1113600 | |||
October | 16000000 | 4000000 | 0 | 0 | 2270400 | |||
November | 28000000 | 4000000 | 0 | 0 | 1627200 | |||
December | 34000000 | 4000000 | 110000 | 0 | 150000 | |||
Total Cost | 298000000 | 48000000 | 1610000 | 0 | 11868000 | 0 | 0 | 0 |
b) For level production planning the fixed average demand of all months needs to be calculated and no of employees kept as close to that as possible to ensure overall production equals demand without any major modifications on a continuous basis.
c) We would hire them for March to July to avoid the loss of sales in July due to excessive seasonal demand remaining unmet in the final month. each extra worker makes 960 units a month giving 48,000 units for five months a total of 240,000 units which is close to overall loss from the shortage in July of 250,000.
d) Yes, There is definitely a value as overtime units would double to 300000 and be sufficient to cover shortages in any month allowing the exceptional facility in chase production plan by varying production to meet demand so minimizing cost from overheads due to excess inventory.
Skycell,a major European cell phone manufacturer, is making production plans for the coming year....
1 Skycell,a major European cell phone manufacturer, is making production plans for the coming year. Skycell has worked with its customers (the service providers) to come up with the forecasts of monthly requirements (in thousands of phones) as shown in the table. Manufacturing is primarily an assembly operation, and capacity is governed by the number of people on the production line. The plant operates for 20 days a month, eight hours each day. One person can assemble a phone every...
2. Skycell, a major European cell phone manufacturer, is making production plans for the coming year. Skycell has worked with its customers (the service providers) to come up with forecasts of monthly requirements (in thousands of phones) as shown in Table 3. Manufacturing is primarily an assembly operation, and capacity is governed by the number of people on the production line. The plant operates for 20 days a month, eight hours each day. One person can assembly a phone every...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Please help with the missing numbers above Also Total hiring cost $ _?(enter response as whole number) Total layoff cost $ _?(enter response as whole number) Total inventory carrying cost $ _?(enter response as whole number) Total stockout cost $ _?(enter response as whole number) Total cost, excluding normal time labor costs, for Plan B $ _?(enter response as whole number) The S&OP team at Kansas Furniture, has received estimates of demand requirements as shown in the table. Assuming one-time...
Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem The monthly forecasts for Product X for January February, and March 1010, 1510 and 1180 respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February, and 21 in March. Beginning inventory is 530 units Manufacturing cost is $180 por unit, storage cost is...
Plan production for the next year. The demand forecast is: spring, 19,500; summer, 9,400; fall, 15,000; winter, 18,800. At the beginning of spring, you have 66 workers and 990 units in inventory. The union contract specifies that you may lay off workers only once a year, at the beginning of summer. Also, you may hire new workers only at the end of summer to begin regular work in the fall. The number of workers laid off at the beginning of...
A disk drive manufacturer is in need of an aggregate plan for July to December. The company has gathered the following data: Month Demand Month Demand July 400 Oct 700 Aug 500 Nov 800 Sep 550 Dec 700 Item Cost Materials $35/disk Inventory $8/disk/month Subcontracting $80/disk Stock-out $15/disk Regular time labor $12/hour Overtime labor $18/hour (above 8 hrs) Hiring cost $40/worker Layoff cost $80/worker Other data include: Item Data Current workforce (June) 8 people Labor hours per disk 4 hrs...
Problem 8-14 (Algo) Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem. The monthly forecasts for Product X for January, February, and March are 1,010, 1,540, and 1,180, respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February and 21 in March. Beginning inventory is 530 units. Manufacturing cost is $180 per...
Problem 8-8 Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply,...