Computation of Effective Price of a Ton | ||
Milan | Dundee | |
Average purchase Price/ Ton(a) | 18 | 20 |
Additional cost of Late delivery per ton (b) | 15.5 | 15.5 |
Probability of late delivery ( c) | 25% | 10% |
Expected Cost of Late Delivery (d=bXc) | 3.875 | 1.55 |
Effective Cost per Ton (a+d) | 21.875 | 21.55 |
Working Note:- | |
Computation of cost of late delivery per ton | |
No ton
delivered (140000*25%+60000*10%) (a) |
41000 |
Cost of late deliveries (b) | 635500 |
Cost of Late delivery per Tonn (b/a) | 15.5 |
Dear student kindly let me know, if you are having any doubt and please mark with positive rating. |
Hult Games buys electronic components for manufacturing from two suppliers, Milan Components and ...
Hult Games buys electronic components for manufacturing from two suppliers, Milan Components and Dundee Parts. If the components are delivered late, the shipment to the customer is delayed. Delayed shipments lead to contractual penalties that call for Hult to reimburse a portion of the purchase price to the customer. During the past quarter, the purchasing and delivery data for the two suppliers showed the following. Milan Dundee Total Total purchases (cartons) 84,000 36,000 120,000 Average purchase price (per carton) $...
Required information [The following information applies to the questions displayed below.) Hult Games buys electronic components for manufacturing from two suppliers, Milan Components and Dundee Parts. If the components are delivered late, the shipment to the customer is delayed. Delayed shipments lead to contractual penalties that call for Hult to reimburse a portion of the purchase price to the customer. During the past quarter, the purchasing and delivery data for the two suppliers showed the following. Total purchases (cartons) Average...
Required information [The following information applies to the questions displayed below.) Hult Games buys electronic components for manufacturing from two suppliers, Milan Components and Dundee Parts. If the components are delivered late, the shipment to the customer is delayed. Delayed shipments lead to contractual penalties that call for Hult to reimburse a portion of the purchase price to the customer. During the past quarter, the purchasing and delivery data for the two suppliers showed the following. Total purchases (cartons) Average...
Benson Manufacturing is considering ordering electronic components from three different suppliers. The suppliers may differ in terms of quality in that the proportion or percentage of defective components may differ among the suppliers. To evaluate the proportion defective components for the suppliers, Benson has requested a sample shipment of 500 components from each supplier. The number of defective components and the number of good components found in each shipment is as follows. Supplier Component 10 35 Good 490 465 455...
Benson Manufacturing is considering ordering electronic components from three different suppliers. The suppliers may differ in terms of quality in that the proportion or percentage of defective components may differ among the suppliers. To evaluate the proportion defective components for the suppliers, Benson has requested a sample shipment of 500 components from each supplier. The number of defective components and the number of good components found in each shipment is as follows. Supplier Component Defective Good 10 25 50 490...
Benson Manufacturing is considering ordering electronic components from three different suppliers. The suppliers may differ in terms of quality in that the proportion or percentage of defective components may differ among the suppliers. To evaluate the proportion defective components for the suppliers, Benson has requested a sample shipment of 500 components from each supplier. The number of defective components and the number of good components found in each shipment is as follows. Supplier Component A B C Defective 15 35...
The following are summary statistics from last year's purchases from the two suppliers Kilda Toorak Gravel corp 400 Number of loads 1e0 Average tons per load Average price per ton Number of initial inspections passed Number of delayed deliveries 10,000 5,000 $ 5.90 6.00 94 300 10 80 The sales manager of Kilda Corporation has proposed to the purchasing manager at RCC that KC be given an exclusive contract to supply the aggregate. Assume that the total annual demand remains...
Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company's needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows: Component Supplier 1 2 $12 $13 $11 $12 3 $10 $10 Se 2 Each supplier has a limited capacity in terms of the total number of components it can supply. However, as long as...
Problem 4-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company's needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows: Supplier Component 1 2 13 1 $12 $13 510 2 $11 $12 s10 Each supplier has a limited capacity in terms of the total number of components it can supply. However,...
Problem 4-11 (Algorithmic) Edwards Manufacturing Company purchases two component parts from three different suppliers. The suppliers have limited capacity, and no one supplier can meet all the company's needs. In addition, the suppliers charge different prices for the components. Component price data (in price per unit) are as follows Supplier Component $10 $14 $10 $12$12 $10 Each supplier has a limited capacity in terms of the total number of components it can supply. However, as long as Edwards provides sufficient...