A famous IT consulting firm BracKenzie and Co, henceforth called the Firm, has a consulting project implementing ERP at a large telecom firm, henceforth called the Client. The project manager, Mr. Grisham, is in the process of submitting a staffing proposal to his client for the project. The labor requirement is estimated to follow a normal distribution with mean 3000 person-hours and a standard deviation of 400 person-hours.
Because the Client is large and influential, the Client pays the Firm for exactly as many hours as are required to complete the project. It is unlikely however, that unutilized time of the consultants will be used up on other projects on short notice, and therefore the Firm will continue to pay $175 per hour to its project staff, per hour without any revenue.
On the other hand, since the project is high-profile, if the work requirements exceed the budgeted person-hours, the Client will hold the Firm accountable for project completion. The Firm will then have to pay $250 per person-hour to hire contract consultants on short notice to make-up for the remaining work requirements.
The Firm Should Allocate Person-Hours
$ per Person-Hour
Expected number of contract consultant hours is
The Firm Should Allocate Person-Hours:
Mean |
Standard Deviation |
Min Person per Hour |
Max Person per Hour |
3000 |
400 |
2600 |
3400 |
There is a possibility of the requirement of 3400 people per hour in certain circumstances, considering the mean 3000 people per hour and Standard deviation 400 Person per hour.
In order to avoid shortage during the project, it is advisable to have 3400 people per hour.
Given: The Firm will continue to pay $175 per hour to its project staff, per hour without any revenue. But in case of the unexpected situation, the firm may be forced to pay $250 if the project is not completed on time.
I would recommend paying $175 per hour even though the client couldn’t complete within the given time frame. So that the client will try to complete on time.
$per Person-Hour = 3000*175 = $525000 for project or $175 per person hour
Expected number of contract consultant hours = 3400 * 250 = $850,000
A famous IT consulting firm BracKenzie and Co, henceforth called the Firm, has a consulting proje...
c. How much should both red and blue GloFish while man duced at the Texas farm? Premier Consulting's two consultants, Avery and Baker, can be sch clients up to a maximum of 160 hours each over the next four week tant, Campbell, has some administrative assignments already planned clients up to a maximum of 140 hours over the next four weeks. The clients with projects in process. The estimated hourly requirements for eac over the four-week period are as follows:...
4. The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants -- Charlie, Gerald. Johnny, and Rick -- to complete any of the four projects, as indicated in the table below. Consultant Charlie Gerald Johnny Rick Project (hours) A B 15 16 13 15 15 21 17 19 с 12...
4. The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants -- Charlie, Gerald, Johnny, and Rick - to complete any of the four projects, as indicated in the table below. Consultant Charlie Gerald Johnny Rick Project Chours) A B 15 16 13 15 15 21 17 19 с 12...
4. The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants -- Charlie, Gerald, Johnny, and Rick -- to complete any of the four projects, as indicated in the table below. Consultant Charlie Gerald Johnny Rick Project (hours) А B 15 16 13 15 15 21 17 19 с 12...
Best Practices, Inc., is a management consulting firm. Its Corporate Division advises private firms on the adoption and use of cost management systems. Government Division consults with state and local governments. Government Division has a client that is interested in implementing an activity-based costing system in its public works department. The division’s head approached the head of Corporate Division about using one of its associates. Corporate Division charges clients $645 per hour for associate services, the same rate other consulting...
PRIMUS CONSULTING GROUP Primus is a firm of consultants that focuses on process reengineering and quality improvement initiatives. Northwood Industries has asked Primus to conduct a study aimed at improving on-time delivery. Normal practice for Primus is to bill for consultant time at standard rates plus actual travel costs and estimated overhead. However, Northwood has offered a flat $85,000 for the job. Currently Primus has excess capacity in that it can take on the Northwood job without turning down other business and without hiring...
please help!! Western, Inc. is a technology consulting firm focused on Web site development and integration of Internet business applications. The president of the company expects to incur $640,000 of indirect costs this year, and she expects her firm to work 4.000 direct labor hours. Western's systems consultants provide direct labor at a rate of $280 per hour Clients are billed at 160% of direct labor cost. Last month, Western's consultants spent 170 hours on Halbert's engagement Requirements 1. Compute...
Lim & Joyce Consulting, a Perth (Australia) based firm, provides consulting services related to project management and analytical support. It operates in a very tight local labour market and is having difficulty finding quality staff. The firm bills $350 per hour for services performed. The labour cost per hour paid by Lim & Joyce Consulting for professional staff time is $135. Additional information is provided as follows: • Billable hours to clients for the year ended totalled 10 000, consisting...
Printed (Chinese) Name: THU ID: Class: Problem 8 (10 points) The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Betty, Johnny, and Rick-to complete any of the four projects, as follows: Project (Hours) Consultant A B Charlie .-13+1 16 11 1 3 21 Betty 11, 13DV 14 - 18...
Peters Realtors, a real estate consulting firm, specializes in advising companies on potential new plant sites. The company uses a job order costing system with a predetermined overhead allocation rate, computed as a percentage of direct labor costs. At the beginning of 2018, managing partner Lee Peters prepared the following budget for the year: (Click the icon to view the prepared budget.) (Click the icon to view additional information.) Read the requirements. Requirement 1. Compute Peters Realtors' (a) hourly direct...