Makes skis, unow boar and high end sledding equsipment As shown below,t Slopes & S the demand for...
How do I calculate the one time adjustment of workforce to support the level production plan? Problem information: Month: 1 2 3 4 5 6 7 8 9 10 11 12 Demand: 500 800 1000 1400 2000 3000 2700 1500 1400 1500 2000 1200 Management at the Kerby Corporation has determined the following aggregated demand schedule in Units. An employee can produce an average of 10 units per month. Each worker on the payroll costs $2,000 in regular time wages...
Management at the Kerby Corporation has determined the following aggregated demand schedule (in units): Month 1 2 3 4 Demand 500 800 1,000 1,400 Month 5 6 7 8 Demand 2,000 3,000 2,700 1,500 Month 9 10 11 12 Demand 1,400 1,500 2,000 1,200 An employee can produce an average of 10 units per month. Each worker on the payroll costs $2,000 in regular-time wages per month. Undertime is paid at the same rate as regular time. In accordance with...
Gang Aft Agley, a manufacturing company, faces the aggregate planning problem shown in the table below. Cost of regular production is $5 per unit, the cost of producing the same unit on overtime is $7.50, the cost of subcontracting is S9 per unit, an<d the cost of carrying a unit in inventory from one month to the next is $2 The labor contract at the plant prohibits overtime output to exceed 300 units in any five month window (that is...
Andree’s All-American manufactures fashionable tennis wear, needs help planning production for next year. Demand for tennis gear is fairly stable, but has peaks during the summer months. Month Demand Forecast January 500 February 300 March 200 April 1500 May 2500 June 3500 July 4500 August 2500 September 500 October 300 November 300 December 2500 Beginning workforce 9 workers Production per day 9 units per employee Production cost during regular time $50 per unit Subcontracting cost $75 per unit Increasing production...
Please answer only the empty boxes (bottom table and the questions below it) The total subtracting cost= $_______ The total inventory holding cost for January through August= $_____ The total cost, excluding normal time labor costs, for Plan E= $_____ Will thumps up if answers is correct! The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements over the next 8 months as follows: 1,400 1,700 May 2,300 January February 2,300 June March 1,700 1,700 July April...
Check The current aggregate demand requirements for a firm are shown below for the next six months: Month May June July Aug Sept Oct 230 Demand 210 210 210 240 260 Click here for the Excel Data File The firm always plans to meet all demand. The firm currently has 230 workers capable of producing 230 units in a month (1 unit/worker). The workforce can be increased (at a cost of $500 per worker) or decreased (at a cost of...
1. For the Red Tomato Garden Tools example, consider the following situation: The company has a Six month aggregate production planning procedure in place. The following factors are considered for planning. The planners use a 160 hour-month for planning purposes. The average labor wage is assumed to be $18.00 per hour. Overtime wage rate is 2.0 times that of regular wage. Federal regulations stipulate that overtime for a worker cannot be more than 15 hours a month. The demand is...
The current aggregate demand requirements for a firm are shown below for the next six months: Month May June July Aug Sept Oct Demand 230 210 210 210 240 260 PpictureClick here for the Excel Data File ped The firm always plans to meet all demand. The firm currently has 230 workers capable of producing 230 units in a month (1 unit/worker). The workforce can be increased (at a cost of $500 per worker) or decreased (at a cost of...
AGGREGATE PLANNING Garden Hub makes a single product, a garden tool that sells for $40. Garden Hub starts with 1000 of these tools in inventory and is expected to end with at least 500 in stock. Garden Hub can temporarily backlog demand for a cost, but at the end of the time horizon, they require their backlog to be zero – This is an important constraint to remember- if we forget it, we will get strange results . Production costs...
Using Excel method Using Excel Pl amaTech ic. a tc o al manufacturer of pharmaceutical pr ducts and medical supples cated n Zurich Switzer and uses sa es ช d opera ons pianing to set production, workforce, and inventory levels for its annual planning horizon. Among the variety of itemis the company produces one he tems used for S30P planning is a standard emergency medical kit that contains medical products that can be used to treat a variety of inures...