Capital Expenditures Budget On January 1, 2016, the controller of Omicron Inc. is planning capital expenditures for the years 2016–2019. The following interviews helped the controller collect the nece...

Capital Expenditures Budget

On January 1, 2016, the controller of Omicron Inc. is planning capital expenditures for the years 2016–2019. The following interviews helped the controller collect the necessary information for the capital expenditures budget:

Director of Facilities: A construction contract was signed in late 2015 for the construction of a new factory building at a contract cost of $10,000,000. The construction is scheduled to begin in 2016 and be completed in 2017.

Vice President of Manufacturing: Once the new factory building is finished, we plan to purchase $1.5 million in equipment in late 2017. I expect that an additional $200,000 will be needed early in the following year (2018) to test and install the equipment before we can begin production. If sales continue to grow, I expect we'll need to invest another $1,000,000 in equipment in 2019.

Chief Operating Officer: We have really been growing lately. I wouldn't be surprised if we need to expand the size of our new factory building in 2019 by at least 35%. Fortunately, we expect inflation to have minimal impact on construction costs over the next four years. Additionally, I would expect the cost of the expansion to be proportional to the size of the expansion.

Director of Information Systems: We need to upgrade our information systems to wireless network technology. It doesn't make sense to do this until after the new factory building is completed and producing product. During 2018, once the factory is up and running, we should equip the whole facility with wireless technology. I think it would cost us $800,000 today to install the technology. However, prices have been dropping by 25% per year, so it should be less expensive at a later date.

Chief Financial Officer: I am excited about our long-term prospects. My only short-term concern is managing our cash flow while we expend the $4,000,000 of construction costs on the portion of the new factory building scheduled to be completed in 2016.

Use this interview information to prepare a capital expenditures budget for Omicron Inc. for the years 2016–2019. Enter all amounts as positive numbers.

Omicron Inc.
Capital Expenditures Budget
For the Four Years Ending December 31, 2016-2019
2016 2017 2018 2019
Building $ $ $
Equipment $
Information systems
Total $ $ $ $
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Given that the following information about the

On January 1, 2016, the controller of Omicron Inc. is planning capital expenditures for the years 2016–2019. The following interviews helped the controller collect the necessary information for the capital expenditures budget:

  • Director of Facilities.
  • Vice President of Manufacturing.
  • Chief Operating Officer.
  • Director of Information System.
  • Chief Financial Officer.

Omicron Inc.

Capital expenditure budget

For the Four Years Ending December 31, 2016-2019

Particulars

2016

2017

2018

2019

Building

$4,000,000

$6,000,000

$3,500,000

equipment

$1,500,000

$200,000

$1,000,000

information system

$450,000**

Total

$4,000,000

$7,500,000

$650,000

$4,500,000

**$800000*0.75*0.75

Add a comment
Know the answer?
Add Answer to:
Capital Expenditures Budget On January 1, 2016, the controller of Omicron Inc. is planning capital expenditures for the years 2016–2019. The following interviews helped the controller collect the nece...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On January 1, 20Y6, the controller of Omicron Inc. is planning capital expenditures for the years 20Y6–20Y9. The followi...

    On January 1, 20Y6, the controller of Omicron Inc. is planning capital expenditures for the years 20Y6–20Y9. The following interviews helped the controller collect the necessary information for the capital expenditures budget: Director of Facilities: A construction contract was signed in late 20Y5 for the construction of a new factory building at a contract cost of $10,000,000. The construction is scheduled to begin in 20Y6 and be completed in 20Y9. Vice President of Manufacturing: Once the new factory building is...

  • Capital Expenditures Budget On August 1, 20Y4, the controller of Handy Dan Tools Inc. is planning...

    Capital Expenditures Budget On August 1, 20Y4, the controller of Handy Dan Tools Inc. is planning capital expenditures for the years 2015-20Y8. The controller interviewed several Handy Dan executives to collect the necessary information for the capital expenditures budget. Excerpts of the interviews are as follows: Director of Facilities: A construction contract was signed in May 2014 for the construction of a new factory building at a contract cost of $12,000,000. The construction is scheduled to begin in 2015 and...

  • Capital Expenditures Budget On August 1, 20Y4, the controller of Handy Dan Tools Inc. is planning...

    Capital Expenditures Budget On August 1, 20Y4, the controller of Handy Dan Tools Inc. is planning capital expenditures for the years 20Y5–20Y8. The controller interviewed several Handy Dan executives to collect the necessary information for the capital expenditures budget. Excerpts of the interviews are as follows: Director of Facilities: A construction contract was signed in May 20Y4 for the construction of a new factory building at a contract cost of $9,500,000. The construction is scheduled to begin in 20Y5 and...

  • InnoTech Ltd (IT) is engaged in manufacturing of video game consoles. On 1 October 2016 IT...

    InnoTech Ltd (IT) is engaged in manufacturing of video game consoles. On 1 October 2016 IT began the construction of a new factory on a piece of freehold land. Costs information relating to the land and factory were as follows during the year ended 31 March 2017: s'ooo Purchase of land on which to build the factory 20,000 Cost of levelling the land prior to beginning construction 850 Cost of materials needed to construct the factory 7.500 Monthly employment costs...

  • ABC has the following accounts in the Property, Plant and Equipment (PPE) section of its balance sheet: Land, Buildings,...

    ABC has the following accounts in the Property, Plant and Equipment (PPE) section of its balance sheet: Land, Buildings, and Equipment. Each non-current asset account has a separate accumulated depreciation contra-account except for Land. ABC uses the historical cost principle to value its fixed assess after acquisition. ABC completed the following transactions in fiscal year 2017. ABC has a fiscal year end of 31st December. 3rd January 2017: ABC exchanged old equipment with accumulated depreciation of €130,000 (cost of acquisition...

  • ABC has the following accounts in the Property, Plant and Equipment (PPE) section of its balance sheet: Land, Buildings,...

    ABC has the following accounts in the Property, Plant and Equipment (PPE) section of its balance sheet: Land, Buildings, and Equipment. Each non-current asset account has a separate accumulated depreciation contra-account except for Land. ABC uses the historical cost principle to value its fixed assess after acquisition. ABC completed the following transactions in fiscal year 2017. ABC has a fiscal year end of 31st December. 3rd January 2017: ABC exchanged old equipment with accumulated depreciation of €130,000 (cost of acquisition...

  • kindly answer from number 4 to 8 exce Midwest Manufacturing Statement of Income 2018 2017 2016 s 5,645,357 5,814,718 6...

    kindly answer from number 4 to 8 exce Midwest Manufacturing Statement of Income 2018 2017 2016 s 5,645,357 5,814,718 6,163,601 Sales Cost of Goods Sold 1,467,793 1,395,532 1,787,444 523,325 Variable Costs 369,816 395,175 Fixed Costs 1,862,968 1,918,857 2,157,260 Total Cost of Goods Sold 3,782,389 3,895,861 4,006,341 Gross Profit Administrative& Selling Expenses: Variable Administrative & Selling Costs Fixed Administrative & Selling Costs 523,906 523,325 395,175 959,711 1,104,796 1,016,994 1,354,886 1,628,121 1,540,900 Total Administrative Costs 2,427,504 2,267,740 2,465,440 Net Income Supplemental Information...

  • The Thompson Corporation, a manufacturer of steel products, began operations on October 1, 2016. The accounting...

    The Thompson Corporation, a manufacturer of steel products, began operations on October 1, 2016. The accounting departmento Thompson has started the fixed-asset and depreciation schedule presented below. You have been asked to assist in completing the schedule. In addition to ascertaining that the data already on the schedule are correct, you have obtained the following information from the company's records and personnel (FV of $1. PV of $1. FVA of $1. PVA of $1. FVAD of $1 and PVAD of...

  • The Thompson Corporation, a manufacturer of steel products, began operations on October 1, 2016. The accounting department of Thompson has started the fixed-asset and depreciation schedule prese...

    The Thompson Corporation, a manufacturer of steel products, began operations on October 1, 2016. The accounting department of Thompson has started the fixed-asset and depreciation schedule presented below. You have been asked to assist in completing this schedule. In addition to ascertaining that the data already on the schedule are correct, you have obtained the following information from the company's records and personnel (FV of S1, PV of S1. EVA of S1. PVA of S1, FVAD of $1 and PVAD...

  • ved The Thompson Corporation, a manufacturer of steel products, began operations on October 1, 2016. The...

    ved The Thompson Corporation, a manufacturer of steel products, began operations on October 1, 2016. The accounting department of Thompson has started the fixed-asset and depreciation schedule presented below. You have been asked to assist in completing this schedule. In addition to ascertaining that the data already on the schedule are correct, you have obtained the following information from the company's records and personnel (FV of $1. PV of $1. EVA of $1. PVA of $1. FVAD of $1 and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT