Question

sisas (19-21). A manager has prepared a forecast of expected aggregate demand for the nest s perods Develop an aggregate plan

0 0
Add a comment Improve this question Transcribed image text
Answer #1

THE GIVEN INFORMATION IN THE ABOVE SHOWN IN THE TABLE BELOW

We are assuming that the beginning inventory is 0 as no specific information is given below. Also we assume a total production of 300 units per period is considered while ignoring specific regular, overtime and subcontract production.

Period 1 2 3 4 5 6 Total
Forecast 200 200 300 400 500 100 1700
Output 300 300 300 300 300 300 1800
Regular time
Overtime
Subcontract
Inventory
Beginning 0 100 200 200 100 0 600
Ending 100 200 200 100 0 100 700
Average 50 150 200 150 50 50 650
Backlog 0 0 0 0 100 100

FOR THE ABOVE QUESTIONS ANSWERS

1)0(A)

2)50(B)

3)PERIOD 6(D)

THANK YOU PLEASE RATE IT

Add a comment
Know the answer?
Add Answer to:
sisas (19-21). A manager has prepared a forecast of expected aggregate demand for the nest s perods Develop an aggregate plan to meet this demand given these additional information . A level produ...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Aggregate Planning

    A While the demand for regular fabric has declined, the demand for medical-grade fabric has been surging in the market. In response, the management at Fabric Mills quickly bumped up the regular output of medical-grade fabric by reassigning workers from the production of regular fabric and rehiring retired workers. Table 2 shows the demand forecast and capacity for medical-grade fabric. Note that overtime is limited to 20% of the regular capacity. The availability of subcontract is also limited due to...

  • A manager has projected demand for the next six months (below). Given this information, prepare a...

    A manager has projected demand for the next six months (below). Given this information, prepare a LEVEL aggregate plan for production. Assume maximum regular time production is 350 units per month. Overtime is limited to 75 units per month. The limit for subcontracting is 400 per month. The company has a zero beginning inventory and cannot have ending inventory or a backlog at the end of the 6th period. Unit costs are as noted below. Regular Time Cost: $10/unit Overtime...

  • Manager Chris Channing of Fabric Mills, Inc., has developed the forecast shown in the table for...

    Manager Chris Channing of Fabric Mills, Inc., has developed the forecast shown in the table for bolts of cloth. The figures are in hundreds of bolts. The department has a normal capacity of 275(00) bolts per month, except for the seventh month, when capacity will be 250(00) bolts. Normal output has a cost of $40 per hundred bolts. Workers can be assigned to other jobs if production is less than normal. The beginning inventory is zero bolts. Month 1 2...

  • Nowjuice, Inc., produces bottled pomegranate juice. A planner has developed an aggregate forecast for demand for...

    Nowjuice, Inc., produces bottled pomegranate juice. A planner has developed an aggregate forecast for demand for the next six months. Month             May                Jun                  jul                    Aug                 Sep                  oct Forecast           4000                4800                5600                7200                6400                5000 Use the following information to develop aggregate plans. Regular production cost          $ 10 per case Regular production capacity   5000 cases Overtime production cost       $ 16 per case Subcontracting cost                $ 20 per case Inventory cost                         $ 1 per case per month Beginning inventory               0 Develop...

  • You are developing an aggregate plan for a toolbox maker which sells to professional mechanics. The...

    You are developing an aggregate plan for a toolbox maker which sells to professional mechanics. The relevant cost and demand data are shown below: Holding cost $8/toolbox/month Month Demand Subcontract $80/toolbox July 400 Regular time $45/toolbox August 500 OT Regular time cost plus additional $20 per toolbox September 500 Capacity increase $50/unit October 700 Capacity decrease $90/unit November 800 Backlog cost $10/toolbox/month December 700 June capacity and demand 500 toolboxes Beginning inventory 0 toolboxes Plan A: Try a level strategy...

  • The following forecast constitutes the demand for relay switches. John Smith, the production planner, has assembled...

    The following forecast constitutes the demand for relay switches. John Smith, the production planner, has assembled the following cost data and the quarterly demand forecast: QUARTER FORECAST 1,800 1 2 1,100 3 1,600 900 4 Costs/Other Data Previous quarter's output = 1300 cases Beginning inventory 350 cases Stockout cost = $110 per case Inventory holding cost $30 per case at the end of quarter Hiring employees = $40 per case Terminating employees = $75 per case Subcontracting cost = $60...

  • Kangaroo P/L has the following demand forecast next year, expressed in six bimonthly (2-month) periods: Period...

    Kangaroo P/L has the following demand forecast next year, expressed in six bimonthly (2-month) periods: Period Forecast Demand (Standard U nits of Work) 1 400 2 380 3 470 4 530 5 610 6 500 The following costing data have been obtained: Each employee works 176 regular working hours per month Each unit requires 20 standard hours to produce The labour costs are $6 per normal hour and $9 per overtime hour It costs $3 per month to hold an...

  • USE LEVEL AGGREGATE PLAN: Cost data Regular time labor cost per hour $10 Overtime time labor...

    USE LEVEL AGGREGATE PLAN: Cost data Regular time labor cost per hour $10 Overtime time labor cost per hour $15 Subcontracting cost per unit $80 Back order cost per unit per period                           $20 Inventory holding cost per unit per period           $10 Hiring cost per employee $400 Firing cost per employee $500 Capacity data Beginning workforce                                                             40 employees Beginning inventory 0 units Beginning backorders 0 units Production standard per unit (hours)                       2 hours of labor per unit Regular time available per...

  • Gang Aft Agley, a manufacturing company, faces the aggregate planning problem shown in the table below....

    Gang Aft Agley, a manufacturing company, faces the aggregate planning problem shown in the table below. Cost of regular production is $5 per unit, the cost of producing the same unit on overtime is $7.50, the cost of subcontracting is S9 per unit, an<d the cost of carrying a unit in inventory from one month to the next is $2 The labor contract at the plant prohibits overtime output to exceed 300 units in any five month window (that is...

  • The president of Hill Enterprises, Terri Hil, projects the firm's aggregate demand requirements over the next...

    The president of Hill Enterprises, Terri Hil, projects the firm's aggregate demand requirements over the next 8 months as follows: May January February ,600 June March April 1.700 August 2,300 2,300 1,900 1,400 1,700July Her operations manager is considering a new plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is $60 per unit. Inventory holding cost is $20 per unit per month. Ignore any dle-time costs. Evaluate the following plans D...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT