Question

tem. In 2020, the company produced 27,900 units. Each unit took several pounds of direct materials ndard hourly rate of $13.0
What was the standard cost per unit of product? (Round answer to 2 decimal places, e-g. 2.75. $ Standard cost per unit


If the 2.75.) Is price variance was $2,606 favorable, what was the standard materials price per pound? (Round answ $ 0.95 Sta
Your answer is correct r was the standard material If the materials quantity variance was $17,765 unfavorable, what was the s
Your answer is correct. What were the standard hours allowed for the units produced? 4640 hours Standard hours allowed
quantity variance was $6,500 unfavorable, what were the actual direct labor hours worked? If the labor 45140 hours Actual hou
If the labor price variance was $9,028 favorable, what was the actual rate per hour? (Round answer to 2 decimal places, eg $
Your answer is correct. If total budgeted manufacturing overhead was $328,020 at normal capacity, what was the predetermined
tem. In 2020, the company produced 27,900 units. Each unit took several pounds of direct materials ndard hourly rate of $13.00. Normal capacity was 49,700 direct labor hours. During the year, 1.30.300 pounds and 1.6 standard hours of direct labor at a purchased at $0.93 per pound. All materials purchased were used during the year
What was the standard cost per unit of product? (Round answer to 2 decimal places, e-g. 2.75. $ Standard cost per unit
If the 2.75.) Is price variance was $2,606 favorable, what was the standard materials price per pound? (Round answ $ 0.95 Standard materials price per pound
Your answer is correct r was the standard material If the materials quantity variance was $17,765 unfavorable, what was the standard materials quantity per unit? Standard materials quantity per unit pounds
Your answer is correct. What were the standard hours allowed for the units produced? 4640 hours Standard hours allowed
quantity variance was $6,500 unfavorable, what were the actual direct labor hours worked? If the labor 45140 hours Actual hours worked
If the labor price variance was $9,028 favorable, what was the actual rate per hour? (Round answer to 2 decimal places, eg $ 12.80 Actual rate per hour
Your answer is correct. If total budgeted manufacturing overhead was $328,020 at normal capacity, what was the predetermined overhead rate based on direct labor hours? (Round answer to 2 decimal places, e.g. 2.75 Predetermined overhead rate S$
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Actual Output = 27900 units
Standard Labour Hours = 1.6 Hrs. per Unit = 27900*1.6 = 44640 hrs.
Standard Labour Rate = $ 13 per hour
Standard Labour Cost = 44640*13 = 580320
Actual Qty. Used = 130300 pounds
Actual Cost per pound = $0.93
Actual Material Cost = 130300*0.93 = 121179
Material Price Variance = 2606 Favourable
Material Qty. Variance = 17765 Adverse
Material Cost Variance = 15159 Adverse
Material Cost Variance = Standard Material Cost (SMC)-Actual Material Cost
-15159 = SMC-121179
SMC = 121179-15159
SMC = 106020
Total Standard Cost = Standard labour Cost+Standard Material Cost
= 580320+106020
= 686340
Standard Cost per unit = Total Standard Cost/Actual Output
= 686340/27900
= 24.6
Material Price Variance = (Standard material price (SMC)-Actual material price)*Actual Qty.
2606 = (SMC-0.93)*130300
SMC = (2606/130300)+0.93
SMC = 0.02+0.93
SMC per pound = $0.95
Material Qty Variance = (Standard material Qty (SMQ)-Actual material Qty)*Standard Material Price
-17765 = (SMQ-130300)*0.95
SMQ = (-17765/0.95)+130300
SMQ = 130300-18700
SMQ = $111,600.00
SMQ per Unit = SMQ/Actual ouput
SMQ per Unit = 111600/27900
SMQ per Unit = 4
Standard Hours allowed for the unit produced = Standard labour hours per unit*Actual output
= 1.6*27900
= 44640
Labour Qty Variance = (Standard Hours Worked -Actual Hours Worked(AHW))*Standard Labour Rate
-6500 = (44640-AHW)*13
AHW = 44640+(6500/13)
AHW = 44640+500
AHW = 45140
Labour Price Variance = (Standard Labour Rate -Actual Labour Rate (ALR))*AHW
9028 = (13-ALR)*45140
ALR = 13-(9028/45140)
ALR = 13-0.20
ALR = 12.80
Total Budgeted Manfacturing Overhead = $328,020
Direct Labour Hour at Normal Capacity = 49700
Predetermined Rate = Total Budgeted Manfacturing Overhead/Direct Labour Hour at Normal Capacity
Predetermined Rate = 328020/49700
Predetermined Rate = 6.6
Add a comment
Know the answer?
Add Answer to:
tem. In 2020, the company produced 27,900 units. Each unit took several pounds of direct materials ndar...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Direct Materials Variances Bellingham Company produces a product that requires 6 standard pounds per unit. The standard...

    Direct Materials Variances Bellingham Company produces a product that requires 6 standard pounds per unit. The standard price is $10 per pound. If 6,300 units required 36,300 pounds, which were purchased at $10.3 per pound, what is the direct materials (a) price variance, (b) quantity variance, and (c) total direct materials cost variance? Enter a favorable variance as negative number using a minus sign and an unfavorable variance as a positive number. 10,890 Unfavorable a. Direct materials price variance b....

  • Direct Materials Variances Bellingham Company produces a product that requires 15 standard pounds per unit. The...

    Direct Materials Variances Bellingham Company produces a product that requires 15 standard pounds per unit. The standard price is $8 per pound. If 5,600 units required 87,400 pounds, which were purchased at $8.24 per pound, what is the direct materials (a) price variance, (b) quantity variance, and (c) total direct materials cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct materials price variance b. Direct...

  • 1) Stefani Company has gathered the following information about its product. Direct materials: Each unit of...

    1) Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 4.50 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 1.50 pounds. Materials cost $3 per pound, but Stefani always takes the 5.00% cash discount all of its suppliers offer. Freight costs average $0.30 per pound. Direct labor. Each unit requires 1.70 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average...

  • Kansas Company uses a standard cost accounting system. In 2017, the company produced 28,500 units. Each...

    Kansas Company uses a standard cost accounting system. In 2017, the company produced 28,500 units. Each unit took several pounds of direct materials and 1.6 standard hours of direct labor at a standard hourly rate of $13.00. Normal capacity was 49,900 direct labor hours. During the year, 131,300 pounds of raw materials were purchased at $0.91 per pound. All materials purchased were used during the year. (a) Your answer is correct. If the materials price variance was $5,252 favorable, what...

  • Direct Materials Variances Bellingham Company produces a product that requires 11 standard pounds per unit. The...

    Direct Materials Variances Bellingham Company produces a product that requires 11 standard pounds per unit. The standard price is $6 per pound. If 2,000 units required 21,100 pounds, which were purchased at $6.18 per pound, what is the direct materials (a) price variance, (b) quantity variance, and (c) total direct materials cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct materials price variance Unfavorable X...

  • Jones Company has the following standards for its single product: standard quantity standard price direct materials...

    Jones Company has the following standards for its single product: standard quantity standard price direct materials 11 pounds per unit $4.25 per pound direct labor 8 hours per unit $14.00 per hour variable overhead 8 hours per unit ?????? per hour Jones Company reported the following information for the month of October: 1. 9,140 units were produced. 2. The direct material quantity variance was $36,295 favorable. 3. The variable overhead spending variance was $1,520 favorable. 4. The total direct labor...

  • Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting system. In 2017, the...

    Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting system. In 2017, the company produced 27,600 units. Each unit took several pounds of direct materials and 1.6 standard hours of direct labor at a standard hourly rate of $13.00. Normal capacity was 49,700 direct labor hours. During the year, 130,800 pounds of raw materials were purchased at $0.91 per pound. All materials purchased were used during the year. (a) Your answer is correct. If the materials price...

  • A company uses the following standard costs to produce a single unit of output. Direct materials...

    A company uses the following standard costs to produce a single unit of output. Direct materials Direct labor Manufacturing overhead 6 pounds at $1.2 per pound 0.40 hour at $10.00 per hour 0.40 hour at $4.90 per hour -$7.20 - $4.00 -$1.96 During the latest month, the company purchased and used 56,000 pounds of direct materials at a price of $1.50 per pound to produce 10,000 units of output. Direct labor costs for the month totaled $35,616 based on 3,710...

  • Bellingham Company produces a product that requires 14 standard pounds per unit. The standard price is...

    Bellingham Company produces a product that requires 14 standard pounds per unit. The standard price is $11.5 per pound. If 3,100 units used 44,300 pounds, which were purchased at $11.15 per pound, what is the direct materials (a) price variance, (b) quantity variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct materials price variance $ Favorable b. Direct materials quantity variance $...

  • Direct Materials Variances Bellingham Company produces a product that requires six standard pounds per unit. The...

    Direct Materials Variances Bellingham Company produces a product that requires six standard pounds per unit. The standard price is $10 per pound. If 2,200 units used 12,800 pounds, which were purchased at $10.4 per pound, what is the direct materials (a) price variance, (b) quantity variance, and (c) cost variance? Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number. a. Direct materials price variance Unfavorable b. Direct materials quantity...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT