STANDARD COST CALCULATION/ PER UNIT | |||||||
DIRECT MATERIALS (24 X16) | $ 384.00 | ||||||
DIRECT LABOR (4 X10) | $ 40.00 | ||||||
VARIABLE MOH (4 X4) | $ 16.00 | ||||||
FIXED MOH (4 X8) | $ 32.00 | ||||||
TOTAL STANDARD COST | $ 472.00 | ||||||
MATERIAL (BASED ON ACTUAL PURCHASE) | (AP-SP) X A.Q | ||||||
PRICE VARIANCE | |||||||
ACTUAL PRICE (YARD) | (A) | $ 15.70 | ($595815/37950) | ||||
STANDARD PRICE (PER YARD) | (B) | $ 16.00 | |||||
VARIANCE | C = (A-B) | $ (0.30) | |||||
ACTUAL QUANTITY (YARD) | D | 37,950.00 | |||||
DIRECT MATERIAL PRICE VARIANCE | C X D | $ (11,385.00) | FAVORABLE | ||||
QUANTITY VARIANCE (BASED ON ACTUAL USAGE) | (A.Q -SQ) X SP | ||||||
ACTUAL QUANTITY (YARD) | (A) | 35,100.00 | |||||
STANDARD QUANTITY (YARD) ( 1500 X 24) | (B) | 36,000.00 | |||||
VARIANCE | C = (A-B) | $ (900.00) | |||||
STANDARD PRICE (YARD) | D | $ 16.00 | |||||
QUANTITY VARIANCE | C X D | $ (14,400.00) | FAVORABLE | ||||
LABOR COST | |||||||
RATE VARIANCE | (AR-SR) X AH | ||||||
ACTUAL RATE PER HOUR | (A) | $ 10.20 | (58650/5750) | ||||
STANDARD RATE PER HOUR | (B) | $ 10.00 | |||||
VARIANCE | C = (A-B) | $ 0.20 | |||||
ACTUAL HOUR | D | 5,750.00 | |||||
DIRECT LABOR VARIANCE | C X D | $ 1,150.00 | UNFAVORABLE | ||||
EFFICIENCY VARIANCE | (AH-SH) X SR | ||||||
ACTUAL DIRECT LABOR HOUR | (A) | 5,750.00 | |||||
STANDARD DIRECT LABOR HOUR (1500 X 4) | (B) | 6,000.00 | |||||
VARIANCE | C = (A-B) | $ (250.00) | |||||
STANDARD RATE PER HOUR | D | $ 10.00 | |||||
EFFICIENCY VARIANCE VARIANCE | C X D | $ (2,500.00) | FAVORABLE | ||||
VARIABLE MANUFACTURING OVERHEAD RATE VARIANCE | (AR-SR) X A.H | ||||||
ACTUAL RATE PER HOUR | (A) | $ 4.10 | (23575/5750) | ||||
STANDARD RATE PER HOUR | (B) | $ 4.00 | |||||
VARIANCE | C = (A-B) | $ 0.10 | |||||
ACTUAL HOUR | D | 5,750.00 | |||||
VARIABLE OVERHEAD VARIANCE | C X D | $ 575.00 | UN FAVORABLE | ||||
VARIABLE MANUFACTURING OVERHEAD EFFICIENCY VARIANCE | (AH-SH) X SR | ||||||
ACTUAL DIRECT LABOR HOUR | (A) | 5,750.00 | |||||
STANDARD DIRECT LABOR HOUR | (B) | 6,000.00 | |||||
VARIANCE | C = (A-B) | (250.00) | |||||
STANDARD RATE PER HOUR | D | $ 4.00 | |||||
V.O.H EFFICIENCY VARIANCE | C X D | $ (1,000.00) | FAVORABLE | ||||
FIXED M.O.H BUDGET VARIANCE (B.F.H -A.F.H) | |||||||
BUDGETED F.O.H | A | $ 46,000.00 | |||||
ACTUAL FIXED OVERHEAD | B | $ 52,000.00 | |||||
FIXED M.O.H BUDGET VARIANCE | A-B | $ (6,000.00) | UNFAVORABLE | ||||
FIXED M.O.H VOLUME VARIANCE | |||||||
ACTUAL OUTPUT | A | $ 1,500.00 | |||||
STANDARD RATE | B | $ 32.00 | |||||
(A X B) | C | $ 48,000.00 | |||||
B F O H | D | $ 46,000.00 | $ 2,000.00 | UNFAVORABLE | |||
F.O.H VOLUME VARIANCE (C-D) | E |
help asap please Actual cost and operating data from the most recent month are as follows: EE (Click the loon t...
Purchased 41,800 yards at a total cost of $434,720 Used 38,800 yards in producing 1,900 awnings Actual direct labor cost of $67,100 for a total of 5,500 hours Actual variable MOH $22,550 Actual fixed MOH $47,800 Standards: Direct materials 21.0 yards per awning at $11.00 per yard Direct labor 3.0 hours per awning at $12.00 per hour Variable MOH standard rate $4.00 per direct labor hour Predetermined fixed MOH standard rate $8.00 per direct labor hour Total budgeted fixed MOH...
Standard Price and Volume Standards: Direct materials 21.0 yards per awning at $15.00 per yard Direct labor 5.0 hours per awning at $17.00 per hour Variable MOH standard rate $4.00 per direct labor hour Predetermined fixed MOH standard rate $7.00 per direct labor hour Total budgeted fixed MOH cost $78,200 Print Done X Actual Results 1 Purchased 51,750 yards at a total cost of $755,550 Used 47,500 yards in producing 2,300 awnings Actual direct labor cost of $194,256 for a...
Pender Awning manufactures awnings and uses a standard cost system. The company allocates overhead based on the number of direct labor hours. The following are the company's cost and standards data: Click the icon to view the standards.) Actual cost and operating data from the most recent month are as follows: B Click the icon to view the actual results.) All manufacturing overhead is allocated on the basis of direct labor hours. Read the requirements. Requirement 1. Calculate the standard...
Ander's Clothing manufactures embroidered jackets. The company uses a standard cost system to control manufacturing costs. The following data represent the standard unit cost of a jacket: i Data Table $4.15 per sq. ft.) Direct materials 3.0 sq. ft x 12.45 Direct labor $9.70 per hour) ( 2,0 hours x 19.40 Manufacturing overhead: Variable 2.0 hours x $0.68 per hour) 1.36 4.40 5.76 2.0 hours x $2.20 per hour) Fixed 37.61 Total standard cost per jacket Fixed overhead in total...
Ceramics Etc. is a manufacturer of large flower pots for urban settings. The company has these standards: i Standard Price and Volume Direct materials (resin) 12 pounds per pot at a cost of $3.00 per pound 2.0 hours at a cost of $15.00 per hour Direct labor Standard variable manufacturing overhead rate $3.00 per direct labor hour Budgeted fixed manufacturing overhead $27,400 $8.00 per direct labor hour (DLH) Standard fixed MOH rate - X Actual Results Ceramics Etc. allocated fixed...
Thompson Foods processes bags of organic frozen fruits sold at specialty grocery stores Click the loon to view additional information) Read the reviret Requirement 1. How much variable overhead would have been allocated to production? How much foed overhead would have been allocated to production? The variable overhead allocated to production is $ 31,125 Now determine the fixed overhead allocated to production The fxed overhead allocated to production is $ 697 200 Requirement 2. Compute the variable MOH rate variance...
Wright Foods processes bags of organic frozen fruits sold at specialty grocery stores. Click the icon to view additional information.) Read the requirements. Begin by determing the formula for the variable MOH rate variance, then calculate the variable overhead rate variance. (Enter the result as a positive number. Enter rates to two decimal places. Label the variance as favorable (F) or unfavorable (U).) Variable overhead rate variance ) = This variance tells managers that Wright Foods actually incurred on variable...
please help irements. + 1. How much variable overhead would have been allocated to production? How much fixed located to production? 0 More Info ine ver ent ell n The company allocates manufacturing overhead based on direct labor hours. Albert has budgeted fixed manufacturing overhead fe the year to be $625,000. The predetermined fixed manufacturing overhead rate is $16.20 per direct labor hour, while the standard variable manufacturing overhead rate is $0.60 per direct labor hour. The direct labor standard...
Data table provided Positive rating awarded upon completion thank you 0 More Info The company allocates manufacturing overhead based on direct labor hours. Martin has budgeted fixed manufacturing overhead for the year to be $627,000 The predetermined fixed manufacturing overhead rate is $16.20 per direct labor hour, while the standard variable manufacturing overhead rate is $0.80 per direct labor hour. The direct labor standard for each case is one-quarter (0.25) of an hour The company actually processed 160,000 cases of...
FlowerMate is a manufacturer of large flower pots for urban settings. The company has these standards: (Click the icon to view the standards.) E: (Click the icon to view the actual results.) Requirements 1. Compute the direct material price variance and the direct material quantity variance. 2. Who is generally responsible for each variance? 3. Interpret the variances. Requirement 1. Compute the direct material price variance and the direct material quantity variance. (Enter the variances as positive numbers. Enter currency...