Learning rate equation is -

Tn=T1nb

where,
n = the unit number
T1 = direct labor hours to produce first unit = 40
Tn = direct labor hours to produce nth unit
p = the learning rate = 0.79
b = In p / ln 2 = ln 0.79 / ln 2

Hence, T100=T1100b = 40*100(ln 0.79 / ln 2) = 8.354 direct labor hours

Hence, For 100th unit, 8.354 direct labor hours are required

Total Cost = Direct Labor Cost + Material Cost + Overhead cost

= 8.354*25 + 380 + 0.50(8.354*25) = $693.28

Profit Required = 20%

Hence Selling Price = Total Cost*(1+0.20 ) = 693.28(1+0.20) = $831.94

Add a comment
Know the answer?
Add Answer to:
ome / My courses / 2019 1A, FIN Finance for Engineers 100 100 in 2010 / Wook 2 102032010 Woor Care2.0a Horventer and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Answer the question The costs of manufacturing horizontal fixed-mount barcode scanners are as follows: Cost Element...

    Answer the question The costs of manufacturing horizontal fixed-mount barcode scanners are as follows: Cost Elements Cost Rate Direct labor $25 per hour Material $380 per unit Overhead costs 50% of direct labor The production has a 79% learning curve applied to labor required, and the time to complete the first unit wa 40 direct labor hours. Determine the unit selling price based on the estimated time to complete the 100th uni if the company wants to make a profit...

  • Vermont Instruments manufactures two models of calculators. The finance model is the Fin-X and the scientific...

    Vermont Instruments manufactures two models of calculators. The finance model is the Fin-X and the scientific model is the Sci-X. Both models are assembled in the same plant and require the same assembling operations. The difference between the models is in the cost of the parts. The following data are available for June: Fin-X Sci-X Total Number of units 11,000 40,000 51,000 Parts cost per unit $25 $30 Other costs: Direct labor $ 55,500 Indirect materials 18,100 Overhead 28,400 Total...

  • Chapter 23 Homework PR 23-1A Direct materials and direct labor variance analysis OBJ. 2,3 Fancy Fixture...

    Chapter 23 Homework PR 23-1A Direct materials and direct labor variance analysis OBJ. 2,3 Fancy Fixture Company manufactures faucets in a small manufacturing facility. The fau- cets are made from brass. Manufacturing has 100 employees. Each employee presently provides 10 hours of labor per week. Information about a production week is as follows: Standard wage per hr. $21.00 Standard labor time per faucet 20 min. Standard number of lbs. of brass 5 lbs. Standard price per lb. of brass $2.80...

  • Chapter 23 Homework PR 23-1A Direct materials and direct labor variance analysis OBJ. 2,3 Fancy Fixture...

    Chapter 23 Homework PR 23-1A Direct materials and direct labor variance analysis OBJ. 2,3 Fancy Fixture Company manufactures Faucets in a small manufacturing facility. The fau cets are made from brass. Manufacturing has 100 employees. Each employee presently provides 40 hours of labor per week. Information about a production week is as follows: Standard wage per hr. $21.00 Standard labor time per faucet 20 min. Standard number of lbs. of brass 5 lbs. Standard price per lb. of brass $2.80...

  • Excel 2010 Help 1) create sales budget 2) operating budget 3) production budget 4) material req...

    Excel 2010 Help 1) create sales budget 2) operating budget 3) production budget 4) material req budget 5) direct labor budget 6) manuf overhead budget 7) production per unit 8) projected income statement AB ales Projections In Units January February March April 20,609 26,521 27,815 49,644 47,350 Projected Sales Price/Unit $ 198.00 Monthly Projected Selling & Administrative Expenses Variable Cost/Unit Fixed Costs $5.00 $5,854 Production: 22.4% Desired Ending Inventory Beginning Inventory (new business) Materials 12.2% 14.0 Desired Ending Inventory Number...

  • Complete this question by entering your answers in the tabs below. Req 1A Req 1B Req...

    Complete this question by entering your answers in the tabs below. Req 1A Req 1B Req 2 Req 3A Req 3B Compute the unit product cost for one unit of each model. Unit Product Cost Flexible Rigid < Req 1A Req2 > Marine, Inc., manufactures a product that is available in both a flexible and a rigid model. The company has made the rigid model for years; the flexible model was introduced several years ago to tap a new segment...

  • Complete this question by entering your answers in the tabs below. Req 1A Reg 1B Req...

    Complete this question by entering your answers in the tabs below. Req 1A Reg 1B Req 2A Req 2B Prepare an income statement for the year. Assume that the company uses variable costing Lynch Company Variable Costing Income Statement < Req 2A Req 2B ) Lynch Company manufactures and sells a single product. The following costs were incurred during the company's first year of operations: Variable costs per unit: Manufacturing: Direct materials Direct labor Variable manufacturing overhead Variable selling and...

  • requiremnets 1a. 1b. 2a. 2b. Exercise 7-6 Variable and Absorption Costing Unit Product Costs and Income...

    requiremnets 1a. 1b. 2a. 2b. Exercise 7-6 Variable and Absorption Costing Unit Product Costs and Income Statements (L07-1, LO7 Lynch Company manufactures and sells a single product. The following costs were incurred during the company's first year of operations: Variable costa per uniti Manufacturing: Direct materials Direct labor Variable manufacturing overhead Variable selling and administrative Fixed costo per year. Fixed manufacturing overhead Fixed selling and administrative $276,000 $186.000 During the year, the company produced 23,000 units and sold 19,000 units....

  • Required information Problem 4-16 Contrasting ABC and Conventional Product Costs (LO4-2, LO4-3, LO4-4) [The following information...

    Required information Problem 4-16 Contrasting ABC and Conventional Product Costs (LO4-2, LO4-3, LO4-4) [The following information applies to the questions displayed below.) For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.80 hours of direct labor time per unit...

  • Check my work Exercise 4-10 Contrasting ABC and Conventional Product Costs [LO4-2, LO4-3, L04-4] Rocky Mountain...

    Check my work Exercise 4-10 Contrasting ABC and Conventional Product Costs [LO4-2, LO4-3, L04-4] Rocky Mountain Corporation makes two types of hiking boots-Xactive and Pathbreaker. Data concerning these two product lines appear below: points Skipped Direct materials per unit Direct labor cost per unit Direct labor-hours per unit Estimated annual production and sales Xactive $ 65.40 $ 18.80 1.4 DLHS 31,000 units Pathbreaker $ 51.60 $ 13.60 1 DLES 81,000 units eBook The company has a conventional costing system in...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT