Question

Answer the question The costs of manufacturing horizontal fixed-mount barcode scanners are as follows: Cost Elements Cost Rat
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Learning rate equation is -

Tn=T1nb

where,
n = the unit number
T1 = direct labor hours to produce first unit = 40
Tn = direct labor hours to produce nth unit
p = the learning rate = 0.79
b = In p / ln 2 = ln 0.79 / ln 2

Hence, T100=T1100b = 40*100(ln 0.79 / ln 2) = 8.354 direct labor hours

Hence, For 100th unit, 8.354 direct labor hours are required

Total Cost = Direct Labor Cost + Material Cost + Overhead cost

= 8.354*25 + 380 + 0.50(8.354*25) = $693.28

Profit Required = 20%

Hence Selling Price = Total Cost*(1+0.20 ) = 693.28(1+0.20) = $831.94

Add a comment
Know the answer?
Add Answer to:
Answer the question The costs of manufacturing horizontal fixed-mount barcode scanners are as follows: Cost Element...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • ome / My courses / 2019 1A, FIN Finance for Engineers 100 100 in 2010 / Wook 2 102032010 Woor Care2.0a Horventer and...

    ome / My courses / 2019 1A, FIN Finance for Engineers 100 100 in 2010 / Wook 2 102032010 Woor Care2.0a Horventer and into The costs of manufacturing hormonal fixed kunt barcode scanners are as follows: Cost Elements Cost Rate Direct labor $25 per hour Material $380 per unit Overhead costs 50% of direct labor The production has a 79% learning curve applied to labor required, and the time to complete the 40 direct labor hours. Determine the unit selling...

  • World Defense manufactures radar systems. It has just completed the manufacture of its first newly designed...

    World Defense manufactures radar systems. It has just completed the manufacture of its first newly designed system, RS-32. Manufacturing data for the RS-32 follow: (Click icon to view data) Requirement Calculate the total variable costs of producing 2, 4, and 8 units. Begin by calculating the total cumulative time in labor-hours. (Round the cumulative average time per unit to the nearest whole number.) Cumulative average time Number of Cumulative total time: units per unit: Labor-hours Labor-hours 3,145 6,290 2 2,673...

  • The Pacific Boat Company, which is under contract to the U.S. Navy, assembles troop deployment boats....

    The Pacific Boat Company, which is under contract to the U.S. Navy, assembles troop deployment boats. As part of its research program, it completes the assem of the first of a new model (PT109) of deployment boats. The Navy is impressed with the PT109. It requests that Pacific Boat submit a proposal on the cost of producing another six PT 109s Pacific Boat reports the following cost information for the first PT 109 assembled. Pacific Boat uses a 90% incremental...

  • Part IV-Problems (55 points) A. Highestec, Inc is beginning the production of a new product. Management...

    Part IV-Problems (55 points) A. Highestec, Inc is beginning the production of a new product. Management believes that 500 labor hours will be required to complete the new unit. A 90 percent cumulative average-time learning curve model for direct labor hours is assumed to be valid. Data on costs are as follows: S50,000 per unit s20 per direct labor hour $30 per direct labor hour Direct materials Direct labor Variable manufacturing overhead Required: a. Set up a table with columns...

  • E10-33 (similar to) Racing Radars manufactures radar systems. It has just completed the manufacture of its...

    E10-33 (similar to) Racing Radars manufactures radar systems. It has just completed the manufacture of its first newly designed system, RS-32. Manufacturing data for the RS-32 follow: E (Click icon to view data) Requirement Calculate the total variable costs of producing 2, 4, and 8 units A Data Table - X mber.) Direct material cost $80,000 per unit of RS-32 Direct manufacturing labor time for first unit 3,400 direct manufacturing labor-hours Learning curve for manufacturing labor time per radar system...

  • Assume Gasol Company has direct labor costs of $1,096, manufacturing overhead costs of $1,457 and prime...

    Assume Gasol Company has direct labor costs of $1,096, manufacturing overhead costs of $1,457 and prime costs of $3,242. What is Gasol's direct materials cost? =========== Assume Gasol Company has direct materials cost of $2,661, direct labor costs of $1,018, manufacturing overhead costs of $1,362. What is Gasol's prime cost? ============= Leonard, Inc., which uses a volume-based cost system, produces cat condos that sell for $104 each. Direct materials cost $11 per unit, and direct labor costs $23 per unit....

  • The following data has been provided by your manufacturing department to estimate the standard cost of...

    The following data has been provided by your manufacturing department to estimate the standard cost of producing a particular product. Direct Labor - $20 per hour. The first unit took 0.6 hours of direct labor but you want to base the cost estimate on the number of hours needed for the 25th unit. You expect a 75% learning curve to apply to the direct labor hours. Overhead-50% of Direct Labor Material $43.75 per 25 units What is your estimate of...

  • Wyckam Manufacturing Inc. has provided the following information concerning its manufacturing costs: Fixed Cost per Month...

    Wyckam Manufacturing Inc. has provided the following information concerning its manufacturing costs: Fixed Cost per Month Cost per Machine-Hour S 5.50 Direct materials Direct labor Supplies S 0.20 S 0.25 S 1,900 $14,800 $ 11,900 For example, utilities should be $1,900 per month plus $0.25 per machine-hour. The company expects to work 4,400 machine-hours in June. Note that the company's direct labor is a fixed cost Required: Complete the company's planning budget for manufacturing costs for June. Wyckam Manufacturing Inc....

  • Wyckam Manufacturing Inc. has provided the following information concerning its manufacturing costs: Fixed Cost per Month...

    Wyckam Manufacturing Inc. has provided the following information concerning its manufacturing costs: Fixed Cost per Month Cost per Machine-Hour $5.70 Direct materials Direct labor Supplies Utilities Depreciation Insurance $42,600 $ 0.20 $ 0.10 $ 1,300 $15,400 $11,600 For example, utilities should be $1,300 per month plus $0.10 per machine-hour. The company expects to wo 4,200 machine-hours in June. Note that the company's direct labor is a fixed cost. Required: Complete the company's planning budget for manufacturing costs for June. Wyckam...

  • 1. Total costs may be computed as follows: a.(Fixed costs per unit × Unit volume) +...

    1. Total costs may be computed as follows: a.(Fixed costs per unit × Unit volume) + Variable costs per unit b.Fixed costs per unit + (Variable costs per unit × Unit volume) c.Fixed costs + (Variable costs per unit × Unit volume) 2. A coefficient of determination of 0.91 means a.that the independent variable explains 91 percent of the cost. b.the model is significant 91 percent of the time. c.the two variables move together in the same direction and have...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT