Question

Gallo Cork Factory

Gallo Cork Factory

 

Number

of

Workers

 

Number

of

Machines

Output

(corks   produced

per hour)

 

Marginal   Product of Labor

 

Cost of   Workers

 

Cost of   Machines

 

Total

Cost

 1

 2

 5





 2

 2

 10





 3

 2

 20





 4

 2

 35





 5

 2

 55





 6

 2

 70





 7

 2

 80





 

 

1.     Refer to Table 13-4. Each worker at Gallo's cork factory costs $12 per hour. The cost of each machine is $20 per day regardless of the number of corks produced. If Gallo's produces at a rate of 70 corks per hour and operates 8 hours per day, what is Gallo’s total labor cost per day?

a.

$72

b.

$112

c.

$576

d.

$616

 

2.     Refer to Table 13-4. Each worker at Gallo's cork factory costs $12 per hour. The cost of each machine is $20 per day regardless of the number of corks produced. What is the total daily cost of producing at a rate of 55 units per hour if Gallo’s operates 8 hours per day?

a.

$480

b.

$576

c.

$520

d.

$616

 

 

3.     Refer to Table 13-4. Each worker at Gallo's cork factory costs $12 per hour. The cost of each machine is $20 per day regardless of the number of corks produced. Assume the number of machines does not change. If Gallo's produces at a rate of 78 corks per hour, what is the total machine cost per day?

a.

$20

b.

$40

c.

$240

d.

We are unable   to determine total machine costs from the information given.

 

 

4.     Refer to Table 13-4. Each worker at Gallo's cork factory costs $12 per hour. The cost of each machine is $20 per day regardless of the number of corks produced. If Gallo's produces at a rate of 35 corks per hour, what is the total labor cost per hour?

a.

$40

b.

$48

c.

$384

d.

$424

 

 

5.     Refer to Table 13-4. Assume Gallo's currently employs 5 workers. What is the marginal product of labor when Gallo's adds a 6th worker?

a.

5 corks per   hour

b.

15 corks per hour

c.

25 corks per   hour

d.

70 corks per   hour

 

 


0 0
Add a comment Improve this question Transcribed image text
Answer #1

(1) Option (c)


When output = 70, Number of workers = 6


Total labor cost = Number of workers x Number of hours per day x $12 = 6 x 8 x $12 = $576


(2) Option (c)


When output = 55, Number of workers = 5


Total labor cost = 5 x 8 x $12 = $480


Cost of machines = 2 x $20 = $40


Total cost ($) = Total labor cost + Cost of machines = 480 + 40 = 520


(3) Option (b)


Total machine cost = Number of machines x $20 = 2 x $20 = $40 (This is the fixed cost)


(4) Option (c)


When output = 35, Number of workers = 4


Total labor cost = 4 x 8 x $12 = $384


NOTE: As HOMEWORKLIB Answering guidelines, first 4 questions are answered.


Add a comment
Know the answer?
Add Answer to:
Gallo Cork Factory
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 20. Refer to Table 13-3. Gallo's cork factory experiences diminishing marginal product of labor with the additio...

    20. Refer to Table 13-3. Gallo's cork factory experiences diminishing marginal product of labor with the addition of which worker? a. The third worker. b. The fourth worker. c. The fifth worker. d. The sixth worker. Average total cost equals a. 21. change in total costs divided by quantity produced. b. change in total costs divided by change in quantity produced. (fixed costs+ variable costs) divided by quantity produced. c. d. (fixed costs + variable costs) divided by change in...

  • Question 6 S L 1 pts Table 13-5 Number of Output Workers 0 0 1 1 ,000 2 2 ,000 S32,700 4 3 ,200 5 3 ,500 6 3 ,600...

    Question 6 S L 1 pts Table 13-5 Number of Output Workers 0 0 1 1 ,000 2 2 ,000 S32,700 4 3 ,200 5 3 ,500 6 3 ,600 Refer to Table 13-5. Assume that fixed costs are $500, and variable costs are $100 per worker. For this firm, what are the shapes of the production function and the total cost curve? The production function is increasing at a decreasing rate, whereas the total cost function is increasing at...

  • 1. A firm uses labor (L) and machine (K) to assemble garden benches. The firm has...

    1. A firm uses labor (L) and machine (K) to assemble garden benches. The firm has the pro- duction function Q = F(L,K) = 207LVK, where L is the number of full-time workers the firm hires per day and K is the number of machines the firm uses per day. Both L and K can be non-integers (for example, a worker can work for half a day). Each worker costs $100 a day and each machine costs $200 a day....

  • Problem 2: A company wishes to assign multiple machines to an operator to minimize costs The foll...

    Problem 2: A company wishes to assign multiple machines to an operator to minimize costs The following times have been collected: Loading machine standard time 034 min Unloading machine standard time Walk time between machines Operator rate Machine rate Power feed time (machining time) 0.26 min 0.09 min $15.00/h S22.00/h 1.56 min - 1. 2. 3. 4. 5. Determine the optimal number of machines per operator to minimize unit cost. Create a worker-machine chart. (Suggestion: use Excel or insert a...

  • please answer all questions!!! Table 13-2 Adrianne's Premium Packaging Service subcontracts with a chocolate manufacturer to...

    please answer all questions!!! Table 13-2 Adrianne's Premium Packaging Service subcontracts with a chocolate manufacturer to box premium chocolates for their mail-order catalogue business. She rents a small room for $250 a week in the downtown business district that serves as her factory. She can hire workers for $275 a week Chocolates Marginal Number of Produced per Product of Workers Week Labour Cost of Factory Cost of Workers Total Cost 300 $250 $275 $525 630 $825 S1075 890 I s...

  • In a widget factory, the producer is able to produce 40 widgets per day when she...

    In a widget factory, the producer is able to produce 40 widgets per day when she hires two workers. The producer is able to produce 70 widgets per day when she hires three workers. If diminishing marginal product occurs with the fourth worker then the producer is able to produce less than 100 widgets per day when she hires four workers. True False In the short run total costs include both fixed costs and variable costs. Rent paid on the...

  • (1) Table 30 Country Gini Coefficient   Sweden 0.24 France 0.275 Italy 0.319 United Kingdom 0.334 Portugal...

    (1) Table 30 Country Gini Coefficient   Sweden 0.24 France 0.275 Italy 0.319 United Kingdom 0.334 Portugal 0.395 Latvia 0.377 Refer to Table 30. Which country has the most unequal income distribution? Latvia Portugal France Sweden (2) Table 20 Quantity of Number of Baseballs Labor Per Day 0 0 1 40 2 78 3 113 4 145 5 175 Refer to Table 20. This table describes the number of baseballs a manufacturing firm can produce per day with different quantities of...

  • Assume the price of steel per ton is 100$/ton for a steel factory when the factory...

    Assume the price of steel per ton is 100$/ton for a steel factory when the factory sells 100 tons perd ay. Also, assume for each additional 100 tons the price falls 7.5$. Assume in order to produce per 100 ton the factory employs 10 workers. Assume daily wage is 100$ per day. Take 100 tons as 1 unit. Also, assume the number of workers company hires and fires is a factor of 10. So calculate whenever you calculate marginal calculate,...

  • Each sweat shop worker at a computer factory can put together 4.1 computers per hour on...

    Each sweat shop worker at a computer factory can put together 4.1 computers per hour on average with a standard deviation of 1 computers. 45 workers are randomly selected to work the next shift at the factory. Round all answers to 4 decimal places where possible and assume a normal distribution. What is the distribution of X X ? X X ~ N(,) What is the distribution of ¯ x x¯ ? ¯ x x¯ ~ N(,) What is the...

  • Each sweat shop worker at a computer factory can put together 4.6 computers per hour on...

    Each sweat shop worker at a computer factory can put together 4.6 computers per hour on average with a standard deviation of 1 computers. 41 workers are randomly selected to work the next shift at the factory. Round all answers to 4 decimal places where possible and assume a normal distribution. a. What is the distribution of X? X-NC 0,1 b. What is the distribution of a? -NE c. What is the distribution of 2 --N d. If one randomly...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT