Question

which two project management knowledge areas described in Exhibit 11.5 do you consider to be the most important? Why?

which two project management knowledge areas described in Exhibit 11.5 do you consider to be the most important? Why?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

These are the 10 Project Management information territories:

1.         Project Integration Management

2.         Project Scope Management

3.         Project Schedule Management

4.         Project Cost Management

5.         Project Quality Management

6.         Project Resource Management

7.         Project Communications Management

8.         Project Risk Management

9.         Project Procurement Management

10.       Project Stakeholder Management

Among these 10, I consider beneath 2 territories are significant:

Undertaking Scope Management

This information region includes the task scope, that is, the work that is incorporated inside the venture. Since scope changes are one of the top reasons for venture changes and melancholy when all is said in done, it is significant that the limits of the task be all around characterized from the start and checked thoroughly. It is simple for individuals to embed unapproved work into the undertaking when the venture gives off an impression of being huge enough to retain it, however most tasks are assessed with the base expense.

While vieing for (or getting) work, we are propelled towards the base extension. However, when the venture has started we are persuaded towards the most extreme.

1.         Plan Scope Management. The Scope Management Plan is a piece of the venture the executives design and can be a segment inside it as opposed to an independent report.

2.         Collect Requirements. At this stage the point by point necessities of the last item or administration are collected and ordered.

3.         Define Scope. A degree proclamation is made which can be in sentence structure or bulleted. You can't outline each extend limit, however the degree explanation should be complete enough that it decreases a portion of the significant dangers to the undertaking.

4.         Create WBS. A Work Breakdown Structure (WBS) contains either a graphical or table-style breakdown of the task work.

5.         Validate Scope. During the task the expectations are "approved" which means they are affirmed by the beneficiary. Note this shows up during the Monitoring and Controlling procedure gathering, and it alludes to the proper acknowledgment of the expectations after they have been submitted, not the particulars for the expectations during the arranging stage.

6.         Control Scope. The degree explanation must be returned to normally considering the task work that has been finished and current venture status. On the off chance that you are bogged down, for instance, you may wish to incline toward a base satisfactory extension instead of the considerable number of fancy odds and ends you needed to deliver in the first place.

Task Schedule Management

This is typically the most tedious of the information regions. During arranging, the venture supervisor must separation the undertaking into assignments and make both a timetable (begin and finish dates for each errand) and spending plan for each assignment. During the undertaking, earned worth administration decides the venture status at customary status interims. Since most undertaking changes include a change to the timetable, it must be persistently re-baselined and the venture the executives plan refreshed (and affirmed by the task support).

1.         Plan Schedule Management. The Schedule Management Plan contains data, for example, how the calendar will be made, who will be answerable for it, how forceful it will be, and under what conditions it will be changed.

2.         Define Activities. The venture is isolated into undertakings. Note that as per the PMBOK this procedure is not the same as Create WBS inside the Scope Management information region, however by and by they are commonly the equivalent. An errand list is created which characterizes the entirety of the task (not the greater part of it!).

3.         Sequence Activities. The errands are "sequenced" that is, they are requested and the connections between them are built up. These connections appear as Finish-to-Start (FS), Finish-to-Finish (FF), Start-to-Start (SS) and Start-to-Finish (SF). For little activities with straightforward calendars this isn't essential.

4.         Estimate Activity Durations. Utilizing its asset list, a span is assessed for each undertaking.

5.         Develop Schedule. Initially, a system graph is delivered which decides the basic way just as buoys for each undertaking. Besides, a graphical bar diagram plan is made with every movement plotted on their ambitious start dates. In conclusion the asset utilization is plotted and undertakings are moved along their buoys to level the asset use. This is called asset leveling.

6.         Control Schedule. Earned esteem investigation is performed on ordinary venture status interims to decide if the undertaking is ahead or bogged down, and by how much, at that status point.

Add a comment
Know the answer?
Add Answer to:
which two project management knowledge areas described in Exhibit 11.5 do you consider to be the most important? Why?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT