Answer
Question 10 Buckley Manufacturing reported the following budgeted and actual figures for one of its products: $2.00 $43...
The following data is given for the Bahia Company: Budgeted production 1,040 units Actual production 906 units Materials: Standard price per pound $1.866 Standard pounds per completed unit 11 Actual pounds purchased and used in production 9,667 Actual price paid for materials $19,817 Labor: Standard hourly labor rate $14.62 per hour Standard hours allowed per completed unit 4.0 Actual labor hours worked 4,665.9 Actual total labor costs $71,155 Overhead: Actual and budgeted fixed overhead $1,181,000 Standard variable overhead rate $26.00...
Fletcher Company collected the following data regarding production of one of its products. Compute the variable overhead efficiency variance. Direct labor standard (2 hrs. @ $12.40/hr.) $ 24.80 per finished unit Actual direct labor hours 96,500 hrs. Budgeted units 56,000 units Actual finished units produced 47,500 units Standard variable OH rate (2 hrs. @ $15.00/hr.) $ 30.00 per finished unit Standard fixed OH rate ($526,400/56,000 units) $ 9.40 per unit Actual cost of variable overhead costs incurred $ 1,417,000 Actual...
Norwall Company’s budgeted variable manufacturing overhead cost is $1.30 per machine-hour and its budgeted fixed manufacturing overhead is $30,624 per month. The following information is available for a recent month: The denominator activity of 9,570 machine-hours is used to compute the predetermined overhead rate. At a denominator activity of 9,570 machine-hours, the company should produce 3,300 units of product. The company’s actual operating results were: Number of units produced 4,570 Actual machine-hours 10,090 Actual variable manufacturing overhead cost $ 14,630...
Lossing Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual overhead costs for the most recent month appear below: Original Budget Actual Costs $ $ 7,800 10,720 7,990 10,070 Variable overhead costs: Supplies Indirect labor Fixed overhead costs: Supervision Utilities Factory depreciation Total overhead cost 15,610 14,900 59,970 $109,000 14,490 14,950 61,040 $108,540 The company based its original budget on 7,800 machine-hours. The company actually worked 7,760 machine-hours during the month. The standard hours...
Behring Corporation applies manufacturing overhead to products on the basis of standard machine-hours. Budgeted and actual fixed manufacturing overhead costs for the most recent month appear below: Original Budget Actual Costs Fixed overhead cost: Supervision $4,680 $4,800 Utilities 6,120 5,820 Factory depreciation 21,240 20,720 Total fixed manufacturing overhead cost $32,040 $31,340 The company based its original budget on 3,600 machine-hours. The company actually worked 3,570 machine-hours during the month. The standard hours...
Performance Report Based on Budgeted and Actual Levels of Production Bowling Company budgeted the following amounts: Variable costs of production: Direct materials 3 pounds @ $0.60 per pound Direct labor 0.5 hr. @ $16.00 per hour VOH 0.5 hr. @ $2.20 FOH: Materials handling $6,200 Depreciation $2,600 At the end of the year, Bowling had the following actual costs for production of 3,800 units: Direct materials $6,800 Direct labor 30,500 VOH 4,200 FOH: Materials handling 6,300 Depreciation $2,600 Required: 1....
Norwall Company’s budgeted variable manufacturing overhead cost is $1.95 per machine-hour and its budgeted fixed manufacturing overhead is $36,036 per month. The following information is available for a recent month: The denominator activity of 18,480 machine-hours is used to compute the predetermined overhead rate. At a denominator activity of 18,480 machine-hours, the company should produce 6,600 units of product. The company’s actual operating results were: Number of units produced 7,550 Actual machine-hours 19,630 Actual variable manufacturing overhead cost $ 41,223...
The following data are given for Harry Company: Budgeted production 1,054 units Actual production 937 units Materials: Standard price per ounce $1.919 Standard ounces per completed unit 11 Actual ounces purchased and used in production 10,616 Actual price paid for materials $21,763 Labor: Standard hourly labor rate $14.76 per hour Standard hours allowed per completed unit 4.3 Actual labor hours worked 4,826 Actual total labor costs $78,423 Overhead: Actual and budgeted fixed overhead $1,025,000 Standard variable overhead rate $24.00 per...
The following data are given for Stringer Company: Budgeted production 909 units Actual production 1,036 units Materials: Standard price per ounce $1.82 Standard ounces per completed unit 12 Actual ounces purchased and used in production 12,805 Actual price paid for materials $26,250 Labor: Standard hourly labor rate $14.95 per hour Standard hours allowed per completed unit 4.4 Actual labor hours worked 5,335.4 Actual total labor costs $81,365 Overhead: Actual and budgeted fixed overhead $1,110,000 Standard variable overhead rate $28.00 per...
ABC Company has the following standards and flexible budget data: Standard Variable Overhead Rate $5.40 Per direct labour hour Standard quantity of direct labor $1.80 hours per unit of output Budgeted fixed overhead rate $100,000 Budgeted Output 25,000 units Standard Variable Overhead $10.80 per unit Standard Fixed Overhead $3.60 per unit Actual Results for November are given below: Actual Output 30,000 units Actual variable overhead $360,000 Actual Fixed Overhead $106,000 Actual Direct Labor 56,000 hours REQUIRED: A) Variable manufacturing overhead...