Question

The Camel Company is considering two mutually exclusive projects with the following cash flows. At what range of discoun...

The Camel Company is considering two mutually exclusive projects with the following cash

flows. At what range of discount rates would you accept project A and at what range of discount

rates would you accept project B (will accept answers that are within 1% of correct answer)?

Year

Project A

Project B

0

-$800

-$1000

1

650

650

2

400

650

0 0
Add a comment Improve this question Transcribed image text
Answer #1

A project is accepted when its discount rate is less than or equal to its Internal rate of return (IRR).

Please refer to below spreadsheet for calculation and answer. Cell reference also provided.

A В D 1 Project B 2 Project A Year -$1,000.00 -$800.00 0 $650.00 $650.00 4 1 $400.00 $650.00 2 6 IRR 22.17% 19.43% Range of D

Cell reference -

A D 1 Project A Project B 2 Year 3 0 -800 -1000 1 650 650 400 2 650 5 =IRR(D3 : D5) =IRR(C3:C5) IRR Range of Discount rate to

Hope this will help, please do comment if you need any further explanation. Your feedback would be highly appreciated.

Add a comment
Know the answer?
Add Answer to:
The Camel Company is considering two mutually exclusive projects with the following cash flows. At what range of discoun...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Bumble's Bees, Inc., has identified the following two mutually exclusive projects: Cash Flow (A) ...

    PLEASE SHOW WORK AND CALCULATIONS THANKS Bumble's Bees, Inc., has identified the following two mutually exclusive projects: Cash Flow (A) Cash Flow (B) Year 0 17,000 8,000 7,000 5,000 3,000 17,000 2,000 5,000 4 What is the IRR for each of these projects? If you apply the IRR decision rule, which project should the company accept? Is this decision necessarily correct? If the required return is 11%, what is the NPV for each of these projects? which project will you...

  • A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...

    A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 + Project - $1,000 $90 $300$400$650 Х Project -$1,000$1,100 $90 $45 $50 Y The projects are equally risky, and their WACC is 13%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations. %

  • A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...

    A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:    0 1 2 3 4 Project X -$1,000 $90 $320 $400 $650 Project Y -$1,000 $1,100 $90 $55 $55 The projects are equally risky, and their WACC is 13%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations. _____ %

  • A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...

    A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 Project X -$1,000 $100 $300 $370 $650 Project Y -$1,000 $1,000 $100 $50 $45 The projects are equally risky, and their WACC is 12%. What is the MIRR of the project that maximizes shareholder value? Do not round intermediate calculations. Round your answer to two decimal places. =___%

  • A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:...

    A firm is considering two mutually exclusive projects, X and Y, with the following cash flows:Project X -$1,000 $110 $320 $430 $650 Project Y -$1,000 $900 $110 $45 $55 The projects are equally risky, and their WACC is 9%. What is the MIRR of the project that maximizes shareholder value? Do not round intermediate calculations. Round your answer to two decimal places.

  • NPV versus IRR Piercy, LLC, has identified the following two mutually exclusive projects: Year Cash Flow...

    NPV versus IRR Piercy, LLC, has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) -$77,500 -$77,500 43,000 21,500 29,000 28,000 23,000 34,000 21,000 41,000 a. What is the IRR for each of these projects? If you apply the IRR decision rule, which project should the company accept? Is this decision necessarily correct? b. If the required return is 11 percent, what is the NPV for each of these projects? Which project will you choose...

  • A firm is considering two mutually exclusive projects, X and Y with the following cash flows:...

    A firm is considering two mutually exclusive projects, X and Y with the following cash flows: 2 3 Project X Project Y - $1,000 -$1,000 $100 $900 $320 $90 $430 $50 $650 $45 The projects are equally risky, and their WACC is 13%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations

  • MIRR A firm is considering two mutually exclusive projects, X and Y, with the following cash...

    MIRR A firm is considering two mutually exclusive projects, X and Y, with the following cash flows: 0 1 2 3 4 Project X -$1,000 $100 $300 $400 $650 Project Y -$1,000 $900 $100 $55 $50 The projects are equally risky, and their WACC is 12%. What is the MIRR of the project that maximizes shareholder value? Round your answer to two decimal places. Do not round your intermediate calculations. ? %

  • 12. NPV versus IRR (LO1, 5) Parkallen Inc. has identified the following two mutually exclusive projects:...

    12. NPV versus IRR (LO1, 5) Parkallen Inc. has identified the following two mutually exclusive projects: m Cash Flow (A) Cash Flow (B) Year -$29,000 14,400 -$29000 0 1 4,300 2 12,300 q.800 4.200 15,200 4 5,100 16,800 Click here for a description of Table: Questions and Problems 12. a. What is the IRR for each of these projects? Using the IRR decision rule, which project should the company accept? Is this decision necessarily correct? b. If the required return...

  • 14) Cedric is considering between two mutually exclusive projects. The following table gives the cash flows...

    14) Cedric is considering between two mutually exclusive projects. The following table gives the cash flows of each project: 0 1 2 3 4 A -$50 25 20 20 15 B -$100 20 40 50 60 a. If your discount rate is 6%, what are the NPVs of the two projects? b. What are the IRRs of the two projects? c. Why do IRR and NPV rank the two projects differently? NPV IRR

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT