Question
1.using the ABC system, how much total manufacturing overhead cost would ge assigbed to product Y (Round your immediate calculations and final answers to 2 decimal places. Round your answers to the nearest dollar amonut)

2. using the ABC system, how much total manufacturing overhead cost would ge assigbed to product Z (Round your immediate calculations and final answers to 2 decimal places. Round your answers to the nearest dollar amount)

3. Using the Plantwide overhead rate, what PERCENTAGE of the total overhead cost is allocated to Prodcut Y and Product Z? (Round your immediate calculations to 2 decimal places. Round your answer to 2 decimal places)

4. Using the ABC system, what PERCENTAGE of the Machining costs is assinged to Prodcut Y and Product Z? (Round your immediate calculations to 2 decimal places. Round your answer to 2 decimal places)

5. Using the ABC system, what PERCENTAGE of the Machine Setups costs is assinged to Prodcut Y and Product Z? (Round your immediate calculations to 2 decimal places. Round your answer to 2 decimal places)

6. Using the ABC system, what PERCENTAGE of the Product Design cost is assinged to Prodcut Y and Product Z? (Round your answers to 2 decimal places)

7. Using the ABC system, what PERCENTAGE of the General Factory cost is assinged to Prodcut Y and Product Z? (Round your immediate calculations and final answers to 2 decimal places)

completion. Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7,000 units of Pro
Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7,000 units of Product Z. The
0 0
Add a comment Improve this question Transcribed image text
Answer #1
1
Total manufacturing overhead cost 461120
2
Total manufacturing overhead cost 234880
3
Total overhead cost:
Product Y 84% =8400/10000
Product Z 16% =1600/10000
4
Machining costs:
Product Y 76.36% =8400/11000
Product Z 23.64% =2600/11000
5
Machine Setups costs:
Product Y 25% =60/240
Product Z 75% =180/240
6
Product Design cost:
Product Y 50% =1/2
Product Z 50% =1/2
7
General Factory cost:
Product Y 84% =8400/10000
Product Z 16% =1600/10000
Workings:
Activity rate:
Machining 20.4 =224400/11000
Machine setups 540 =129600/240
Production design 44000 =88000/2
General factory 25.4 =254000/10000
Product Y:
Machining 171360 =8400*20.4
Machine setups 32400 =60*540
Production design 44000
General factory 213360 =8400*25.4
Total manufacturing overhead cost 461120
Product Z:
Machining 53040 =2600*20.4
Machine setups 97200 =180*540
Production design 44000
General factory 40640 =1600*25.4
Total manufacturing overhead cost 234880
Add a comment
Know the answer?
Add Answer to:
1.using the ABC system, how much total manufacturing overhead cost would ge assigbed to product Y (Round your immediate...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z?...

    Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z? (Round your intermediate calculations to 2 decimal places. Round your answers to the nearest dollar amount.) Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your answers to 2 decimal places.) Using the ABC system, what percentage of the Machining costs is assigned to...

  • A. using the abc system, how much total manufacturing overhead cost would be assigned to product...

    A. using the abc system, how much total manufacturing overhead cost would be assigned to product Y? B. Using ABC system, how mych total manufacturing overhead cost woykd be assigned to product Z? C.using the plabtwide iverhead rate, what percentage if the total overbead cost is allocated to product Y and product Z? D. Using ABC system, what percebtage if the machining costs is assigned to product Y and product Z? E. what percentage if machine setups cost is assigned...

  • Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y?...

    Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Y? Using the ABC system, how much total manufacturing overhead cost would be assigned to Product Z? Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product Z? Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z? Using the ABC system, what percentage of Machine Setups cost...

  • 12. Using the ABC system, what percentage of the Machining costs is assigned to Product Y...

    12. Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your answers to 2 decimal places.) 13. Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z? (Round your intermediate calculations to 2 decimal places. Round your answers to 2 decimal places.) 14. Using the ABC system, what percentage of the Product Design cost...

  • product and role 2 Hound your 12. Using the ABC system, what percentage of the Machining...

    product and role 2 Hound your 12. Using the ABC system, what percentage of the Machining costs is assigned to Product Y and Product Z? (Round your "Percentage" answers to 2 decimal places.) Product Y Product Z Machining cost 13. Using the ABC system, what percentage of Machine Setups cost is assigned to Product Y and Product Z? (Round your "Percentage" answers to 2 decimal places.) Product Y Product z Machine setups cost % 14. Using the ABC system, what...

  • Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 198,000...

  • What is the company’s plantwide overhead rate? Using the plantwide overhead rate, how much manufacturing overhead...

    What is the company’s plantwide overhead rate? Using the plantwide overhead rate, how much manufacturing overhead cost is allocated to Product Y and Product Z? What is the activity rate for the Machining activity cost pool? What is the activity rate for the Machine Setups activity cost pool? What is the activity rate for the Product Design activity cost pool? What is the activity rate for the General Factory activity cost pool? Using the ABC system, how much total manufacturing...

  • Greenwood Company manufactures two products-13,000 units of Product Y and 5,000 units of Product Z. The...

    Greenwood Company manufactures two products-13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number of setups...

  • Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product...

    Required information Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Machining Machine setups Production design General factory Activity Measure Machine-hours Number...

  • Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7,000 units of Product...

    Required information Greenwood Company manufactures two products-15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z Estimated Overhead Expected Activity 11,000 MHs Activity Cost Pool Machining Machine setups Production design...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT