Question

A process has 3 steps with the following IPYs: 99%, 98%, and 96% Determine the DPMO for the entire process: 1- 2- If you hav

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.

RTY = IPY1 x IPY2 x IPY3 = 0.99 x 0.98 x 0.96 = 0.931392

So, DPMO = (1 - 0.931392) x 106 = 68,608

2.

RTY = 0.93

DPMO = (1 - 0.93) x 106 = 70,000

3.

More information is required such as confidence level, power of test.

Add a comment
Know the answer?
Add Answer to:
A process has 3 steps with the following IPY's: 99%, 98%, and 96% Determine the DPMO for the entire process: 1- 2-...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • EOY 0 1 2 3 4 5 6 96 97 98 99 100 550 550 550...

    EOY 0 1 2 3 4 5 6 96 97 98 99 100 550 550 550 1,100 1,100 1,650 1,650 2,200 2.2001 2,750 2,750 Problem 5-5 (algorithmic) What is the capitalized worth of a project that has an indefinitely long study period and dollar cash flows that repeat as diagram. The interest rate is 18% per year. Click the icon to view the diagram for cash flows. Click the icon to view the interest and annuity table for discrete compounding...

  • a process has ten steps with the following data Operation Defects Units 1 12 380 2...

    a process has ten steps with the following data Operation Defects Units 1 12 380 2 72 943 3 22 220 4 85 1505 5 23 155 6 23 255 7 102 1023 8 93 843 9 55 285 10 68 1132 Calculate the DPU and operation yield for each step. Showing each step in excel determine the rolled throughput yield and total defects per unit Describe the manufacturing /business process and or six sigma project situations for the origination...

  • 24. United Widget Manufacturing has a problem with defective widgets. Employees make hundreds of thousands of...

    24. United Widget Manufacturing has a problem with defective widgets. Employees make hundreds of thousands of them each day, and many are defective. United has instituted training for the workers, and you would like to predict the number of defects per week based on the number of days of training an employee has received. You obtain the following data: Employee number 1015 2023 1153 4029 1117 0012 Days of training 4 5 6 4 3 2 Defects per week (100's)...

  • References 93 Review Questions 1. In the following data set the absolute frequency for 99/min is:...

    References 93 Review Questions 1. In the following data set the absolute frequency for 99/min is: Date and Time Pulse Rate Recorded Jan. 5, 8:00 a.m. 100/min Jan. 5, 12:00 noon 102/min Jan. 5, 4:00 p.m. 99/min Jan. 5, 8:00 pm 99/min Jan. 5. 12:00 midnight 102/min Jan. 6, 4:00 am 98/min Jan 6, 8:00 am 99/min a. 1 b. 2 c. 3 d. 4 2. Using the data set from question 1, the relative frequency for 102/min would be...

  • Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The...

    Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary to make many changes in operating procedures. Progress has been slow, particularly in trying to develop new performance measures for the factory. In an effort to evaluate performance and determine where improvements can be made, management has gathered the following data relating to activities over the last four months: Month 1 2 3 4 Quality control...

  • Problem 11-19 Internal Business Process Performance Measures (LO11-3] Tombro Industries is in the process of automating...

    Problem 11-19 Internal Business Process Performance Measures (LO11-3] Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary to make many changes in operating procedures. Progress has been slow, particularly in trying to develop new performance measures for the factory. In an effort to evaluate performance and determine where improvements can be made, management has gathered the following data relating to activities over the last four...

  • PA3-1 (Algo) Preparing a Process Costing Production Report (Weighted Average Method) [LO 3-2, 3-3, 3- 4]...

    PA3-1 (Algo) Preparing a Process Costing Production Report (Weighted Average Method) [LO 3-2, 3-3, 3- 4] Sandia Corporation manufactures metal toolboxes. It adds all materials at the beginning of the manufacturing process. The company has provided the following information: Costs Units 36,000 $ 30,000 100,000 $130,000 82,000 Beginning work in process (30% complete) Direct materials Conversion cost Total cost of beginning work in process Number of units started Number of units completed and transferred to finished goods Ending work in...

  • Problem 11-19 Internal Business Process Performance Measures (LO11-3] Tombro Industries is in the process of automating...

    Problem 11-19 Internal Business Process Performance Measures (LO11-3] Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary to make many changes in operating procedures. Progress has been slow, particularly in trying to develop new performance measures for the factory. In an effort to evaluate performance and determine where improvements can be made, management has gathered the following data relating to activities over the last four...

  • Process Costing- FIFO Assumptions A. Required: Complete the following sequence of steps for Department B 1....

    Process Costing- FIFO Assumptions A. Required: Complete the following sequence of steps for Department B 1. Compute physical flow and equivalent full units. finished units in both of its manufacturing operations. Production and cost data for the prior month for both Departments is provided below: no Department A Beginning of Month 24,000 100% End of Month 20,000 100% 2. Compute unit costs. Beginning units Percentage completion: Direct material Direct labor and overhead 75% 60% Beginning Costs S 188,000 3. Determine...

  • manufacturing process 1) A customer order of 50 pieces one carat LGDs is to be processed...

    manufacturing process 1) A customer order of 50 pieces one carat LGDs is to be processed through plant 1. Seed materials are supplied by the customer. The total time for processing the LGDs (including setup and other direct labor) is 500 hr. Direct labor cost is $25.00/hr. The factory overhead is 250% and the corporate overhead rate is 600%. Computer the cost of the job assumes the company's markup (profit) is 60%. 2) the following data are given: direct labor...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT