Question

Hubbard Building Company signed a contract with a customer on November 1, 2016. The contract called for construction of...

Hubbard Building Company signed a contract with a customer on November 1, 2016. The contract called for construction of a building to begin by December 31, 2016, and to be completed by December 31, 2017. The contract price was $8.0 million. Hubbard estimated that the building would cost $5 million. On November 15, 2016, the customer was required to make an advance payment of $1,000,000. No work was done on the project until January 2017. How much income from the project should Hubbard report in 2016?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Income from project to be reported by Hubbard in 2016 = 0

Explanation: Advance payment cannot be treated as income. Further no work was done till Jan 2017, therefore percentage of completion is 0%, hence no revenue could be recognized in 2016.

Add a comment
Know the answer?
Add Answer to:
Hubbard Building Company signed a contract with a customer on November 1, 2016. The contract called for construction of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • VIQUISepon ZUIY Complete this question by entering your answers in the tabs below. Required 1 Required...

    VIQUISepon ZUIY Complete this question by entering your answers in the tabs below. Required 1 Required 2 Required 3 Taylor Moore buys and sells real estate. On December 31, 2019, her inventory of property included a tract of undeveloped land for which she had paid $980,000. The fair market value of the land was $1,000,000 at that date. How much income should Moore report for 2019 in connection with this land? Income reported in connection with land < Required 1...

  • On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2017. Expenditures on the project were as follows: January 1, 2016 $ 1,000,000 March 1, 2016 600,000 June 30, 2016 800,000 October 1, 2016 600,000 January 31, 2017 270,000 April 30, 2017 585,000 August 31, 2017 900,000 On January 1, 2016, the company obtained a $3 million construction loan with a 10% interest...

  • IVE. O EnergyRadio.com ap Watch Bleach Anim. Dragon Ball Super E. Sradable Assignment i Savod Help...

    IVE. O EnergyRadio.com ap Watch Bleach Anim. Dragon Ball Super E. Sradable Assignment i Savod Help Save & For each of the following cases, respond to the question and indicate the accounting principle or concept that applies. Required: 1. Williamson, LLC, paid insurance premiums of $3,600 on December 1, 2019. These premiums covered a two-year period beginning on that date. Whiat amount, from this payment, should the corporation show as insurance expense for the year 2019? What accounting principles, conventions,...

  • Interest Costs During Construction Comprehensive Illustration: On November 1, 2016, Shalla Company contracted Pfeifer Construction Co....

    Interest Costs During Construction Comprehensive Illustration: On November 1, 2016, Shalla Company contracted Pfeifer Construction Co. to construct a building for $1,400,000 on land costing S100,000 (purchased from the contractor and included in the first payment). Shalla made the following payments to the construction company during 2017 January 1 $210,000 March 1 $300,000 May 1 $540,000 December 31 $450,000 Total $1,500,000 Interest Costs During Construction Pfeifer Construction completed the building, ready for occupancy, on December 31, 2017. Shalla had the...

  • On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2016, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2016, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2017, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2017 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2018 after additional costs of...

  • 1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp....

    1.Hometown Construction Corp. entered into a long-term contract to build an office building for Outsider Corp. at a fixed contract price of $27.5 million on 6/15/2016. Construction of the building is completed on 12/15/2018. Hometown Construction expects the building to be completed in two and a half years and uses the Percentage of Completion Method (cost to cost approach) to account for the contract. Cost information related to the contract are as follows: 2016 2017 2018 Actual Construction costs incurred...

  • In February 2020, Crane Construction signed a contract and commenced construction on a parking garage. The t...

    In February 2020, Crane Construction signed a contract and commenced construction on a parking garage. The total contract price was $89.8 million and was expected to be completed in July 2024 at a total estimated cost of $82.0 million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. The customer was to have control over the parking garage and was able to make major changes to the project...

  • 1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport...

    1- Bridgeport Construction Company began work on a $407,000 construction contract in 2020. During 2020, Bridgeport incurred costs of $272,000, billed its customer for $217,000, and collected $177,500. At December 31, 2020, the estimated additional costs to complete the project total $157,020. Prepare Bridgeport’s journal entry to record profit or loss, if any, using (a) the percentage-of-completion method and (b) the completed-contract method. 2- Waterway, Inc. began work on a $7,071,000 contract in 2020 to construct an office building. Waterway...

  • Fender period. Construction Company receives a contract to construct a building over a 3 year Information...

    Fender period. Construction Company receives a contract to construct a building over a 3 year Information relating to the performance of the contract is summarized as follows: 2015 2016 2017 S 16,000,000 Cumulative construction costs incurred to date Estimated costs to complete Billings during the year Cash collected during the year 6,000,000 8,000,000 6,000,000 3,000,000 8,000,000 7,000,000 4,000,000 5,000,000 Required: 1. How much is Fender Construction charging to build this athletic stadium? In other words, what is the contract price...

  • 23) A right of return exists when: A) the customer is entitled to a full or...

    23) A right of return exists when: A) the customer is entitled to a full or partial refund. B) the customer is entitled to a credit against amounts owed. C) the customer is entitled to another product in exchange. D) any one of these conditions is met. 19) Noah Construction Company is building a large complex for a contract price of $5,000,000. This is a three-year project and the requirements for recognizing revenue over time are met. The total estimated...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT