Question

On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used...

On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2017.

Expenditures on the project were as follows:

January 1, 2016 $ 1,000,000

March 1, 2016 600,000

June 30, 2016 800,000

October 1, 2016 600,000

January 31, 2017 270,000

April 30, 2017 585,000

August 31, 2017 900,000

On January 1, 2016, the company obtained a $3 million construction loan with a 10% interest rate. The loan was outstanding all of 2016 and 2017. The company’s other interest-bearing debt included two long-term notes of $4,000,000 and $6,000,000 with interest rates of 6% and 8%, respectively. Both notes were outstanding during all of 2016 and 2017. Interest is paid annually on all debt. The company’s fiscal year-end is December 31.

Assume the $3 million loan is not specifically tied to construction of the building.

Required:
1.

Calculate the amount of interest that Mason should capitalize in 2016 and 2017 using the weighted-average method. (Do not round your intermediate calculations. Round your answers to the nearest whole dollars.)

        

2.

What is the total cost of the building? (Do not round your intermediate calculations. Round your answer to the nearest whole dollar.)

        

3.

Calculate the amount of interest expense that will appear in the 2016 and 2017 income statements. (Do not round your intermediate calculations. Round your answers to the nearest whole dollars.)

      

0 0
Add a comment Improve this question Transcribed image text
Answer #1


Part 1: weighted avg method date Jan 1, 2016 Mar 1,2016 Jun 30, 2016 Oct 1,2016 calculation of average accumulated expenditur calculation of average accumulated expenditure-2017 date expenditure capitalisation period weight weighted expenditure b c=b/

Add a comment
Know the answer?
Add Answer to:
On January 1, 2016, the Mason Manufacturing Company began construction of a building to be used...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,000,000 March 1, 2021 600,000 June 30, 2021 800,000 October 1, 2021 600,000 January 31, 2022 270,000 April 30, 2022 585,000 August 31, 2022 900,000 On January 1, 2021, the company obtained a $3 million construction loan with a 10% interest...

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $1,000,000 March 1, 2018 600,000 800,000 June 30, 2018 October 1, 2018 600,000 270,000 January 31, 2019 April 30, 2019 585,000 August 31, 2019 900,000 On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,500,000 March 1, 2021 1,200,000 June 30, 2021 1,400,000 October 1, 2021 1,200,000 January 31, 2022 360,000 April 30, 2022 693,000 August 31, 2022 990,000 On January 1, 2021, the company obtained a $4,000,000 construction loan with a 14% interest rate....

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,000.000 840,000 480.009 630.000 630,eee 945,000 1,620, DBC On January 1, 2018, the company obtained a $3 million construction loan with a 11% interest...

  • help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to...

    help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: points 8 03:03:29 January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,070,000 840,000 380,000 710,000 1,170,000 1.485.000 2,700,000 eBook Print References On January 1, 2018, the company obtained a $3...

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,090,000 March 1, 2021 780,000 June 30, 2021 980,000 October 1, 2021 780,000 January 31, 2022 297,000 April 30, 2022 630,000 August 31, 2022 927,000 On January 1, 2021, the company obtained a $3,300,000 construction loan with a 16% interest rate....

  • help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to...

    help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,070,e00 840,000 380, e00 Dok nt 710,000 1,170,000 1,485,000 2,700,e0e nces On January 1, 2018, the company obtained a $3 million construction...

  • On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 $ 1,350,000 March 1, 2021 1,080,000 June 30, 2021 1,280,000 October 1, 2021 1,080,000 January 31, 2022 342,000 April 30, 2022 $675,000 August 31, 2022 $972,000 On January 1, 2021, the company obtained a $3,800,000 construction loan with a 15% interest rate....

  • On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used...

    On January 1, 2021, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2022. Expenditures on the project were as follows: January 1, 2021 March 1, 2021 June 30, 2021 October 1, 2021 January 31, 2022 April 30, 2022 August 31, 2022 $1,280,000 960,000 1,160,000 960,000 324,000 657,000 954,000 On January 1, 2021, the company obtained a $3,600,000 construction loan with a 15% interest rate. The...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT