Question

Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press DepartmAssuming that the estimated costs for November are the same as for October, prepare a flexible factory overhead cost budget f

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Leno Manufacturing Company - Press Department

Factory Overhead Cost Budget—Press Department

For the Month Ended November 30

Direct labour hours

16,000

18,000

20,000

Variable overhead cost:

Indirect factory labour

147200

165600

184000

Power and light

6240

7020

7800

Indirect materials

43200

48600

54000

Total variable overhead cost

196640

221220

245800

Fixed overhead cost:

Supervisory salaries

77430

77430

77430

Depreciation of plant and equipment

48670

48670

48670

Insurance and property taxes

30970

30970

30970

Total fixed overhead cost

157070

157070

157070

Total factory overhead cost

353710

378290

402870

Note:

Here fixed overhead will not change because fixed overhead cost will remain same at any level of production. The only change take place will be in variable cost

Working notes for the above answer is as under


20,000 Leno Manufacturing Company - Press Department Factory Overhead Cost Budget-Press Department For the Month Ended Novemb

E F Leno Manufacturing Company - Press Department Factory Overhead Cost Budget-Press Department For the Month Ended November

Add a comment
Know the answer?
Add Answer to:
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 18,000 hours of productive capacity in the department: Variable overhead cost: Indirect factory labor Power and light $144,000 6,480 45,000 $195,480 Indirect materials Total variable overhead cost Fixed overhead cost: Supervisory salaries Depreciation of plant and equipment Insurance and property taxes $68,420 43,010 27,370 Total fixed overhead cost 138,800 Total factory...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 18,000 hours of productive capacity in the department: $162,000 5,400 55,800 $223,200 Variable overhead cost: Indirect factory labor Power and light Indirect materials Total variable overhead cost Fixed overhead cost: Supervisory salaries Depreciation of plant and equipment Insurance and property taxes Total fixed overhead cost Total factory overhead cost $78,120 49,100...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 18,000 hours of productive capacity in the department: Variable overhead costs:    Indirect factory labor $142,200    Power and light 7,020    Indirect materials 46,800       Total variable overhead cost $196,020 Fixed overhead costs:    Supervisory salaries $68,610    Depreciation of plant and equipment 43,120    Insurance and property taxes 27,440       Total fixed overhead cost 139,170 Total factory...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 16,000 hours of productive capacity in the department: Variable overhead cost: Indirect factory labor $115,200 Power and light 6,880 Indirect materials 35,200 Total variable overhead cost $157,280 Fixed overhead cost: Supervisory salaries $55,050 Depreciation of plant and equipment 34,600 Insurance and property taxes 22,020 Total fixed overhead cost 111,670 Total factory...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 20,000 hours of productive capacity in the department: Variable overhead costs: Indirect factory labor $180,000 Power and light Indirect materials 12,000 64,000 Total variable overhead cost $256,000 Fixed overhead costs: Supervisory salaries $ 80,000 50,000 Depreciation of plant and equipment Insurance and property taxes 32,000 Total fixed overhead cost 162,000 Total...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 14,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $109,200    Power and light 4,480    Indirect materials 44,800       Total variable overhead cost $158,480 Fixed overhead cost:    Supervisory salaries $55,470    Depreciation of plant and equipment 34,870    Insurance and property taxes 22,190       Total fixed overhead cost 112,530 Total factory...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 15,000 hours of productive capacity in the department: Variable overhead cost: Indirect factory labor $121,500 Power and light 6,450 Indirect materials 43,500 Total variable overhead cost $171,450 Fixed overhead cost: Supervisory salaries $60,010 Depreciation of plant and equipment 37,720 Insurance and property taxes 24,000 Total fixed overhead cost 121,730 Total factory...

  • Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October...

    Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 16,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $145,600    Power and light 5,120    Indirect materials 44,800       Total variable overhead cost $195,520 Fixed overhead cost:    Supervisory salaries $68,430    Depreciation of plant and equipment 43,010    Insurance and property taxes 27,370       Total fixed overhead cost 138,810 Total factory overhead cost $334,330...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected Department for October of the current year, during which it expected to require 9,000 hours of productive capacity in the department: Variable overhead cost: Indirect factory labor $88,200 Power and light 2,610 Indirect materials 26,100 Total variable overhead cost $116,910 Fixed overhead cost: Supervisory salaries $40,920 Depreciation of plant and equipment 25,720 Insurance...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 12,000 hours of productive capacity in the department: Variable overhead cost: Indirect factory labor $99,600 Power and light 5,640 Indirect materials 36,000 Total variable overhead cost $141,240 Fixed overhead cost: Supervisory salaries $49,430 Depreciation of plant and equipment 31,070 Insurance and property taxes 19,770 Total fixed overhead cost 100,270 Total factory...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT