(a) | Calculation of total borrowing cost incurred during the year ended 30th June, 2019 | |||||||||||
Particulars | Calculation | Amount | ||||||||||
5% HK $ 40 Million Loan | 40,000,000 * 5% | 2,000,000.00 | ||||||||||
7.5% HK $ 20 Million Loan | 20,000,000 * 7.5% | 1,500,000.00 | ||||||||||
10% HK $ 40 Million Loan | 40,000,000 * 10% | 4,000,000.00 | ||||||||||
7,500,000.00 | ||||||||||||
Calculation of Borrowing cost eligible for capitalzation | ||||||||||||
Expenditures incurred in obtaining a qualifying asset are first
allocated to any specific borrowings. The remaining expenditures are allocated to any general borrowings |
||||||||||||
Amt(HK $) | Months | Amount Allocated to general Borrowings | Weighted for period outstanding | Amount | ||||||||
1-Jul-18 | 20,000,000.00 | 12 | 0 | 0 | ||||||||
1-Nov-18 | 26,000,000.00 | 8 | 6,000,000.00 | 6,000,000 x 8/12 = | 4,000,000.00 | |||||||
1-Feb-19 | 18,000,000.00 | 5 | 18,000,000.00 | 18,000,000 x 5/12 = | 7,500,000.00 | |||||||
30-Jun-19 | 16,000,000.00 | 0 | 16,000,000.00 | - | ||||||||
80,000,000.00 | 11,500,000.00 | |||||||||||
The
capitalisation rate relating to general borrowings is the weighted
average of the borrowing costs applicable to the |
||||||||||||
entity’s
borrowings that are outstanding during the period, other than borrowings made specifically for the purpose of obtaining a qualifying asset. |
||||||||||||
20,000,000.00 | 7.50% | 1,500,000.00 | ||||||||||
40,000,000.00 | 10% | 4,000,000.00 | ||||||||||
60,000,000.00 | 5,500,000.00 | |||||||||||
WACR | 9% | (5500000/60000000) | ||||||||||
Hence Borrowings to be capitalised: | ||||||||||||
Specific Borrowings | ||||||||||||
40,000,000.00 | 5% | 2,000,000.00 | ||||||||||
Less: Income on temporary iNvest. | (500,000.00) | |||||||||||
1,500,000.00 | ||||||||||||
General Borrowings | ||||||||||||
11,500,000.00 | 9% | 1,054,166.67 | ||||||||||
Total Borrowing cost to be capitalised | 2,554,166.67 | |||||||||||
Note: | As per para
21 of the HKAS 21, An entity also does not suspend capitalising borrowing costs when a temporary delay is a |
|||||||||||
necessary part of the process of getting an asset ready for its intended use or sale. Hence suspension of 3 weeks will not effect capitalization process. | ||||||||||||
(b) | As per para
8 of HKAS 23 - Borrowing Cost An entity shall capitalise borrowing
costs that are directly attributable to the acquisition, |
|||||||||||
construction or production of a qualifying asset as part of the
cost of that asset. An entity shall recognise other borrowing costs as an expense in the period in which it incurs them. |
||||||||||||
Borrowing
costs that are directly attributable to the acquisition,
construction or production of a qualifying asset are included in the cost of that asset. Such borrowing |
||||||||||||
Costs are
capitalised as part of the cost of the asset when it is probable
that they will result in future economic benefits to the entity and the costs can be measured reliably |
||||||||||||
Hence based on the above provisions, Out of total borrowing Cost of HK $ 7,500,000, HK $ 2,554,166.67 shall be capitalised with the cost of the assets and remaining amount will | ||||||||||||
be charged to Statement of profit and loss during the year. | ||||||||||||
(C ) | Building A A/c Dr. | 2,554,166.67 | ||||||||||
To, Finance Cost | 2,554,166.67 | |||||||||||
(Being expense capitalised) | ||||||||||||
(d) | Calculation of the carrying amount of the Building | |||||||||||
Expenses incurred | 80,000,000.00 | |||||||||||
Add: Borrowing Cost | 2,554,166.67 | |||||||||||
82,554,166.67 | ||||||||||||
Question 4 (30 marks) Sunlight Property Development Limited (Sunlight) is a company which acquires and develops...
Question 1 Extractive Industries (18 marks) ABC Mining company paid $5.6 million for a mining property on 1 July 2016 after the geologists of the exploration company estimated that a gold deposit found on the property would produce 42 000 ounces of gold. In each of the years 2016-2017 and 2017-2018, ABC spent $225 000 per annum developing the property and, during 2017-2018, the company purchased and installed the following assets: Estimated useful life Asset Cost Mine building $500 000...
Undeniably, profitability is the ultimate goal of companies and readers of a company’s financial statements are very much interested in the reported profit figure. The profit figure is achieved by the preparation of the statement of profit or loss and the statement of financial position. If the foregoing is the 3 case, why then bother about the statement of cash flows? B. Globally, accounting standards are developed based on different methods. It is generally agreed that the nature of accounting...
A company constructs a building for its own use. Construction began on January 1 and ended on December 30. The expenditures for construction were as follows: January 1, $540,000; March 31, $640,000; June 30, $440,000; October 30, $720,000. To help finance construction, the company arranged a 7% construction loan on January 1 for $780,000. The company’s other borrowings, outstanding for the whole year, consisted of a $5 million loan and a $7 million note with interest rates of 9% and...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: points 8 03:03:29 January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,070,000 840,000 380,000 710,000 1,170,000 1.485.000 2,700,000 eBook Print References On January 1, 2018, the company obtained a $3...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,000.000 840,000 480.009 630.000 630,eee 945,000 1,620, DBC On January 1, 2018, the company obtained a $3 million construction loan with a 11% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $1,000,000 March 1, 2018 600,000 800,000 June 30, 2018 October 1, 2018 600,000 270,000 January 31, 2019 April 30, 2019 585,000 August 31, 2019 900,000 On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest rate....
Could you show how this problem is worked, when according to the last sentence of the paragraph ( Assume the $3million loan is not specifically tied to construction of building)? In one instance there's specific borrowing and in another there is non- specific. I want to see the difference and answer to this problem. On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters The building was completed on September...
explain it please Check my work On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,000,000 600,000 800,000 600.000 270,000 585,000 900,000 On January 1, 2018, the company obtained a $3 million construction...
help please On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019 Expenditures on the project were as follows: January 1, 2018 March 1, 2018 June 30, 2018 October 1, 2018 January 31, 2019 April 30, 2019 August 31, 2019 $1,070,e00 840,000 380, e00 Dok nt 710,000 1,170,000 1,485,000 2,700,e0e nces On January 1, 2018, the company obtained a $3 million construction...