Manufacturing cycle efficiency | 28.57% |
Manufacturing cycle efficiency measures the proportion of production time spent on value-added activities. | ||
To calculate the measurement, divide value-added production time by total cycle time. | ||
Total cycle time is the aggregate amount of all process time, inspection time, queue time, and move time. |
Activity | Average Time (Hours) | Remarks |
New Product Development | 24 | Not Relevant |
Materials Handling | 0.5 | Non Value Added activity |
Order Setup | 4.5 | Non Value Added activity |
Machine Maintenance | 1.5 | Non Value Added activity |
Order Scheduling | 4 | Not Relevant |
Inspection of Completed Order | 3.5 | Non Value Added activity |
Pack and move to storage or ship | 0.5 | Non Value Added activity |
Manufacturing assembly | 18 | Value Added activity |
Order taking and checking | 1.5 | Not Relevant |
Receiving and stocking raw materials | 4.5 | Not Relevant |
Inspection of raw materials at start of production | 0.5 | Non Value Added activity |
Total Cycle Time | 63 | |
(Time taken by Value added and non Value added activities) | ||
Total Processing Time | 18 | |
(Manufacturing assembly) | ||
Manufacturing cycle efficiency | 28.57% | =18/63 |
Please give positive rating.
Check my work Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant...
Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth, which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 37%. When last calculated, Waymouth's MCE was 32% Key measures from the recent month's production,...
Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth, which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 32%. When last calculated, Waymouth's MCE was 24% Key measures from the recent month's production,...
Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth. which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 40%. When last calculated, Waymouth's MCE was 35%. Key measures from the recent month's production,...
Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth, which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 40%. When last calculated, Waymouth's MCE was 35%. Key measures from the recent month's production,...
13-5 Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth, which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 32%. When last calculated, Waymouth’s MCE was 25%. Key measures from the recent month’s...
Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cyde time is a critical success factor for Weymouth which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 37% When last calculated Waymouth's MCE was 32% Key measures from the recent month's production,...
Determine the manufacturing cycle efficiency (MCE) for the recent month. Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth, which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 37%. When last calculated, Waymouth's...
due at midnight, drop venmo for a tip Check my work Problem 11-14 Measures of Internal Business Process Performance (LO11-3) DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data...
DataSpan, Inc, automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 2 3 4 Throughput time (days) Delivery cycle...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...