Determine the manufacturing cycle efficiency (MCE) for the recent month.
Ans. | Manufacturing cycle efficiency = Total processing time / Total cycle time * 100 | ||
2 / 31 * 100 | |||
6.45% | |||
*Calculations for Total processing time: | |||
Manufacturing assembly hours are the total processing time. | |||
*Calculations for Total cycle time: | |||
Materials handling | 1.50 | ||
Order setup | 5.50 | ||
Machine maintenance | 2.50 | ||
Order scheduling | 14.00 | ||
Inspection of completed order | 2.00 | ||
Pack and move to storage or ship | 0.50 | ||
Manufacturing assembly | 2.00 | ||
Receiving and stocking raw materials | 2.00 | ||
Inspection of raw materials at start of production | 1.00 | ||
Total Cycle Time | 31.00 | ||
*New product development and Order taking & checking are not included in the | |||
calculation of Total cycle time. | |||
Determine the manufacturing cycle efficiency (MCE) for the recent month. Waymouth Manufacturing operates a contract manufacturing...
Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth, which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 37%. When last calculated, Waymouth's MCE was 32% Key measures from the recent month's production,...
Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth. which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 40%. When last calculated, Waymouth's MCE was 35%. Key measures from the recent month's production,...
Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth, which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 32%. When last calculated, Waymouth's MCE was 24% Key measures from the recent month's production,...
Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth, which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 40%. When last calculated, Waymouth's MCE was 35%. Key measures from the recent month's production,...
Check my work Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth, which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 37%. When last calculated, Waymouth's MCE was 32% 0.31 points Key measures...
Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cyde time is a critical success factor for Weymouth which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 37% When last calculated Waymouth's MCE was 32% Key measures from the recent month's production,...
13-5 Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth, which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 32%. When last calculated, Waymouth’s MCE was 25%. Key measures from the recent month’s...
The formula for computing Manufacturing Cycle Efficiency (MCE) is a.Cycle time per unit × velocity. b.Theoretical Capacity / Production hours available. c.Processing Time / (Processing time + Move time + Inspection time + Waiting time + Other non-value-added time). d.None of these choices are correct.
Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary to make many changes in operating procedures. Progress has been slow, particularly in trying to develop new performance measures for the factory In an effort to evaluate performance and determine where improvements can be made, management has gathered the following data relating to activities over the last four months Month Quality control measures: Number of defects...
Tombro Industries is in the process of automating one of its plants and developing a flexible manufacturing system. The company is finding it necessary to make many changes in operating procedures. Progress has been slow, particularly in trying to develop new performance measures for the factory. In an effort to evaluate performance and determine where improvements can be made, management has gathered the following data relating to activities over the last four months: Month 1 2 3 4 Quality control...