The formula for computing Manufacturing Cycle Efficiency (MCE) is a.Cycle time per unit × velocity. b.Theoretical...

The formula for computing Manufacturing Cycle Efficiency (MCE) is

a.Cycle time per unit × velocity.

b.Theoretical Capacity / Production hours available.

c.Processing Time / (Processing time + Move time + Inspection time + Waiting time + Other non-value-added time).

d.None of these choices are correct.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Option C

Manufacturing cycle efficiency

= Value added production time / Total cycle time

Add a comment
Know the answer?
Add Answer to:
The formula for computing Manufacturing Cycle Efficiency (MCE) is a.Cycle time per unit × velocity. b.Theoretical...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Cycle Time and Velocity, MCE Computador has a manufacturing plant in Des Moines that has the...

    Cycle Time and Velocity, MCE Computador has a manufacturing plant in Des Moines that has the theoretical capability to produce 243,000 laptops per quarter but currently produces 91,125 units. The conversion cost per quarter is $7,290,000. There are 60,750 production hours available within the plant per quarter. In addition to the processing minutes per unit used, the production of the laptops uses 10 minutes of move time, 10 minutes of wait time, and 10 minutes of rework time. (All work...

  • Cycle Time and Velocity, MCE Computador has a manufacturing plant in Des Moines that has the...

    Cycle Time and Velocity, MCE Computador has a manufacturing plant in Des Moines that has the theoretical capability to produce 180,750 laptops per quarter but currently produces 72,300 units. The conversion cost per quarter is $7,230,000. There are 60,250 production hours available within the plant per quarter. In addition to the processing minutes per unit used, the production of the laptops uses 9 minutes of move time, 19 minutes of wait time, and 5 minutes of rework time. (All work...

  • Cycle Time and Velocity, MCE Computador has a manufacturing plant in Des Moines that has the...

    Cycle Time and Velocity, MCE Computador has a manufacturing plant in Des Moines that has the theoretical capability to produce 193,500 laptops per quarter but currently produces 77,400 units. The conversion cost per quarter is $9,288,000. There are 64,500 production hours available within the plant per quarter. In addition to the processing minutes per unit used, the production of the laptops uses 11 minutes of move time, 19 minutes of wait time, and 6 minutes of rework time. (All work...

  • Determine the manufacturing cycle efficiency (MCE) for the recent month. Waymouth Manufacturing operates a contract manufacturing...

    Determine the manufacturing cycle efficiency (MCE) for the recent month. Waymouth Manufacturing operates a contract manufacturing plant located in Dublin, Ireland. The plant provides a variety of electronics products and components to consumer goods manufacturers around the world. Cycle time is a critical success factor for Waymouth, which has developed a number of measures of manufacturing speed. Waymouth has studied the matter and found that competitive contract manufacturers have manufacturing cycle times (MCE) of about 37%. When last calculated, Waymouth's...

  • Cycle Time and velocity, MCE Computador has a manufacturing plant in Des Moines that has the theoretical capability to...

    Cycle Time and velocity, MCE Computador has a manufacturing plant in Des Moines that has the theoretical capability to produce 260,000 laptops per quarter but currently produces 78,000 units. The conversion cost per quarter is $8,190,000. There are 65,000 produ the processing minutes per unit used, the production of the laptops uses 9 minutes of move time, 21 minutes of wait time, and 6 minutes of rework time. (All work is done by cell workers.) Required: 1. Compute the theoretical...

  • Schurz Corporation's management reports that its average delivery cycle time is 29 days, its average throughput time is 13.0 days, its manufacturing cycle efficiency (MCE) is 0.20, its average mo...

    Schurz Corporation's management reports that its average delivery cycle time is 29 days, its average throughput time is 13.0 days, its manufacturing cycle efficiency (MCE) is 0.20, its average move time is 0.6 day, and its average queue time is 3.0 days Required: Round your answer to 1 decimal place What is the Wait Time? Process Time? inspection Time? days days days Schurz Corporation's management reports that its average delivery cycle time is 29 days, its average throughput time is...

  • Check my w Inspection time Wait time (from order to start of production) Process time Move...

    Check my w Inspection time Wait time (from order to start of production) Process time Move time Queue time 0.5 days 15.4 days 3.2 days 0.9 days 4.3 days Required: 1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your percentage answer to nearest whole percent.) 3. What percentage of the throughput time was spent in non-value-added activities? (Round your percentage answer to nearest whole percent.)...

  • 4. During the most recent month at Hybarger Corporation, queue time was 3.0 days, inspection time...

    4. During the most recent month at Hybarger Corporation, queue time was 3.0 days, inspection time was 0.8 day, process time was 2.8 days, wait time was 11.8 days, and move time was 0.6 day. Required: (15%) a. Compute the throughput time. b. Compute the manufacturing cycle efficiency (MCE). c. What percentage of the production time is spent in non-value-added activities? d. Compute the delivery cycle time.

  • Ruiz Foods makes energy bars using a traditional manufacturing process. Raw materials are stored in inventory...

    Ruiz Foods makes energy bars using a traditional manufacturing process. Raw materials are stored in inventory and then moved into production. Work in process inventory is moved across the company's three separate departments. The information below (in the Traditional column) is available for a recent order. If the company adopts lean manufacturing, management believes both move time and wait time can be reduced, as shown in the Lean column. Activity Traditional Lean Process time Inspection time Move time 20 hours...

  • MCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 100 units (per hour) Move time: 18 minutes Inspection time: 13 minu...

    MCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 100 units (per hour) Move time: 18 minutes Inspection time: 13 minutes Rework time: 15 minutes Required: 1. Calculate MCE. If required, round your answer to two decimal places. 2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places. Theoretical cycle time minutes Actual cycle time...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT