Question

Scope = 10chairs @ $10.00-$100.00 Timeframe 10 days At the End of the 5th day 4 chairs were Completed at a cost of $11.00 each PV: AC EV CPI- sv=

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Project ABC: Assume that each chair cost $10 and take one day to complete

Planned Value (PV) is the value which was supposed to earn at that point of time

Planned value (PV) calculation at the end of 5th day

PV = (% planned completion) * Budgeted Cost

= 50% * $100 = $50

Earned Value (EV) is valued earned to the proportion of the completion of the task at point of time

EV = (% completion) * Budgeted Cost

= 40% * $100 = $40

The actual cost (AC) of project = completed chairs * Actual Cost

= 4 *$11 = $44

Cost variance (CV) = EV – AC

= $40 - $44 = -$4

Cost performance index               (CPI) = EV/AC = $40 /$44 = 0.91

Schedule Variance (SV) = Earned Value (EV) - Planned Value (PV)

= $40 - $50 = -$10

Schedule performance index (SPI) = EV/PV = $40/$50 = 0.8

Critical Ratio (CR) is a product of the cost performance index (CPI) and schedule performance index (SPI)

CR = CPI * SPI = 0.91 * 0.8 = 0.73

Add a comment
Know the answer?
Add Answer to:
Scope = 10chairs @ $10.00-$100.00 Timeframe 10 days At the End of the 5th day 4...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days...

    Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days AC = At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CV = CPI= SV = SPI= CR = To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total of 20 weeks. After 12 weeks and...

  • Complete the following exercises and submit them in a word document (10 points). Project ABC Scope...

    Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...

  • Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question...

    Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....

  • You have a project to plant corn in 4 fields each having an area of 20...

    You have a project to plant corn in 4 fields each having an area of 20 ha (200000 m2). Each field is to take one day to plant, and $1,000 has been budgeted per field. The fields were planned to be planted one after the other. Today is the end of day 3. Using the following project status chart, calculate PV, EV, etc., in the spaces provided. Activity Day1 Day 2 Day3 Day 4 Status at the end of day...

  • The following table shows the current status data for a project at the end of month...

    The following table shows the current status data for a project at the end of month 3. PV (Planned Value) EV (Earned Value) AC (Actual Cost) SV CV SPI CPI $18,461.54 $35,673.08 $20,673.08 If you were the project manager for this project, should you have any concerns about this data? If yes, then what are your concerns? what might be some underlying causes? how might you combat these in the future? If no, then explain why not.

  • Earned value calculation Based on the following Project data, answer the questions a and b. Activity...

    Earned value calculation Based on the following Project data, answer the questions a and b. Activity Duration Predecessors Task Budget A 7 days -- $16,850 B 10 days -- $22,500 C 8 days B $16,000 D 10 days A $12,790 E 7 days B $8,500 F 4 days D $10,550 At the end of Day 10, the status of the project is as follows. Activity % Complete Actual Cost A 100% $18,000 B 100% $23,000 C 0% $0 D 10%...

  • Here is a practical example of EVM (Earned Value Management). Three values, BCWS, BCWP, and AC,...

    Here is a practical example of EVM (Earned Value Management). Three values, BCWS, BCWP, and AC, are all cumulative. Acronyms: BCWS (Budgeted Cost of Work Scheduled) is equal to PV (Planned Value). BCWP (Budgeted Cost of Work Performed) is equal to EV (Earned Value). AC (Actual Cost) is the actual costs that we pay for the works. Variances: Schedule variance: when BCWP - BCWS is negative, the project is behind schedule, when the value is 0, it is on schedule,...

  • 3) You are in charge of the Aurora Project. Given the following project network, baseline, and...

    3) You are in charge of the Aurora Project. Given the following project network, baseline, and status information, (40 Points) B DI OA E • Develop status reports for periods 7 and complete the performance indices table. . Calculate the EAC, and VAC. Based on your data, what is the current status of the project? At completion? Rule 1 0% complete 2-50/50 3 - 0/100 ID LF SL Schedule information Total 0 1 2 PV 3 4 30 5 6...

  • use your own words, don't copy and paste, don't use handwriting, please. please help me to...

    use your own words, don't copy and paste, don't use handwriting, please. please help me to answer all Questions please:( ______________________ Q2: Suppose a project X is half completed by the end of first month. Upto this duration the rate of performance is 50 percent. Complete the below table by using given values and explain about the budget and schedule on the basis of calculations. Earned value calculations for project X after 1 month are as follows: PV=8000 SR                     AC=20000...

  • I need help with the attached assignment. I attached the question and completed assigment. I just...

    I need help with the attached assignment. I attached the question and completed assigment. I just need help with answering one more question which is which is: Discuss a strategy that you would use to communicate the status of the project to stakeholders? Project Monitoring and Control Assignment Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project Case in Larson and Gray. Respond to Questions 1 and 2 of the case. Use Microsoft...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
Active Questions
ADVERTISEMENT