Question

Q.3 (a) Within the context of the manufacturing environment, explain the terms (i) Relevant cost (ii) Opportunity cost (iii) Contribution to profit (6 marks) (b) The Engineering Manager in ABC Ltd is responsible for maximising the profit from three product lines X, Y and Z. He/she has been provided with the following information Direct materials (E) Direct labour (hrs) Fabrication Assembly Finishing Selling price per unit (E) 100 85 120 4 2 3.75 550 210 3.5 2 3.5 480 220 3.75 4 625 180 Budgeted production (in units) Additional information is also provided There are no closing stocks The maximum sales achievable for each product in the period is 230 units The labour rate for fabrication and finishing is £13.50/hr. The labour rate for assembly work is £12.00/hr > The skilled labour required for the assembly process is in short supply although there is just enough to meet the current budgeted production Required () Prepare a statement showing the contribution from each product based on the budgeted production (6 marks) (ii) Calculate the contribution per unit of limiting factor (2 marks) (ii) Prepare a statement showing the maximum total contribution that can be obtained. Explain your rationale (6 marks)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

(a)(i) relevant cost is the cost which is relevant for the purpose of decision making. In other words, costs which differs amongst different alternatives is known as Relevant Cost. For example variable cost per unit

(ii)Opportunity Cost: Income earned in the next best alternative is opportunity cost. In other words, Income that could have been earned in case the said was decision was not taken is opportunity cost for the decision.

(iii)Contribution to Profit: Contribution Margin is Sales – Variable Cost.

(b) (i)Contribution from each product:

X

Y

Z

Selling price per Unit

550

480

625

Less: Variable Costs

Direct material

100

85

120

Direct Labor Hours*Cost per Hour

Fabrication

54

47.25

50.625

Assembly

24

24

18

Finishing

50.625

47.25

54

Contribution margin per Unit (A)

321.375

276.5

382.375

Budgeted Production (Units)

210

220

180

Total Contribution margin

67,488.75

60,830

68,827.5

Hours of Assembly Labor per Unit (B)

2

2

1.5

Contribution Margin per unit of limiting factor (A/B)

160.6875

138.25

254.917

(iii) Total hours available of limiting factor i.e. Assembly Labor = 210*2 +220*2 + 180*1.5

= 1,130 hours

Hours will first be used to produce Z since contribution per hours is highest in case of Z, followed by X and Y

Product

Units

Hours per Unit

Total Assembly Hours

Total Contribution Margin

X

230

2

460

73,916.25

Y

162.5

2

325

44,931.25

Z

230

1.5

345

87,946.25

Total

1,130

206,793.75

Hence, maximum contribution margin that can be obtained is $206,793.75

It has been assumed that half unit of Y will also be produced.

Add a comment
Know the answer?
Add Answer to:
Q.3 (a) Within the context of the manufacturing environment, explain the terms (i) Relevant cost (ii)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The Engineering Manager in ABC Ltd is responsible for maximising the profit from three product lines...

    The Engineering Manager in ABC Ltd is responsible for maximising the profit from three product lines X, Y ,Z. He/she has been provided with the following information: (b) The Engineering Manager in ABC Ltd is responsible for maximising the profit from three product lines X, Y and Z. He/she has been provided with the following information 85 120 Direct materials (E) Direct labour (hrs) Fabrication Assembly Finishing Selling price per unit (£) 100 4 2 3.75 550 210 3.5 2...

  • Q.3 Answer all parts Total 20 marks] The Engineering Manager in A Company Ltd. is responsible...

    Q.3 Answer all parts Total 20 marks] The Engineering Manager in A Company Ltd. is responsible for maximising the profit from four product lines A, B, C and D. They have been provided with the following information; Direct materials (kgs) 80 90 95 70 Direct labour (hrs) Welding Assembly Finishing 4.5 9.5 4 3.5 4 8 4 4.5 4 Selling price per unit (E) 1500 2500 3000 1000 300 450 Max.sales for the period (in units) 400 280 250 Budgeted...

  • Q.3 Answer all parts Total 20 marks] The Engineering Manager in A Company Ltd. is responsible...

    Q.3 Answer all parts Total 20 marks] The Engineering Manager in A Company Ltd. is responsible for maximising the profit from four product lines A, B, C and D. They have been provided with the following information; Direct materials (kgs) 80 95 70 Direct labour (hrs) Welding Assembly Finishing 4.5 9 4 4.5 9.5 4 3.5 4 8 4 Selling price per unit (E) 1500 2500 3000 1000 280 Max.sales for the period in units) 400 300 450 250 250...

  • The Engineering Manager in A Company Ltd. is responsible for maximising the profit from four product...

    The Engineering Manager in A Company Ltd. is responsible for maximising the profit from four product lines A, B, C and D. They have been provided with the following information Direct materials (kgs) 80 90 95 70 Direct labour (hrs) Welding Assembly Finishing 4.5 3.5 9.5 4 Selling price per unit (E) 1500 2500 3000 1000 Max.sales for the period in units) 400 300 280 450 250 250 250 250 Budgeted production (in units) Additional information is also provided i....

  • Q.2 As Engineering Manager in Your Company Ltd. you are responsible for maximising the profit from...

    Q.2 As Engineering Manager in Your Company Ltd. you are responsible for maximising the profit from four product lines W, X, Y and Z. You have been provided with the following information Direct materials (kg) 75 90 85 70 Direct labour (h) 3.5 Fabrication Assembly Packaging 4.5 8 3.5 4.5 9.5 4 Selling price per unit (£) 1400 2350 3000 1200 300 450 Max. sales for the period (in units) 400 280 280 Budgeted production (in units) 300 270 270...

  • SECTION A Q.2 As Engineering Manager in Your Company Ltd. you are responsible for maximising the...

    SECTION A Q.2 As Engineering Manager in Your Company Ltd. you are responsible for maximising the profit from four product lines W, X, Y and Z. You have been provided with the following information: Direct materials (kg) 75 90 85 70 Direct labour (h) Fabrication Assembly Packaging 4.5 8 3.5 4.5 9.5 4 3.5 6 Selling price per unit (S) 1400 2350 3000 1200 280 Max. sales for the period (in units) 400 300 450 Budgeted production 300 270 270...

  • Q.3 a Within the context of the manufacturing environment, explain the terms (i) Relevant cost (ii)...

    Q.3 a Within the context of the manufacturing environment, explain the terms (i) Relevant cost (ii) Opportunity cost (iii) Contribution to profit (6 marks)

  • LILI SDN BHD is a manufacturer and supplier of home cabinets. It has two main Departments...

    LILI SDN BHD is a manufacturer and supplier of home cabinets. It has two main Departments that is the Production Department and the Service Department. The Production department has three (3) sub-departments: Machining, Assembly and Finishing. All three departments are labor-intensive. The Service Department has two sub-department which is Maintenance and General Services. Cost Data Production Departments Service Departments Cost Items (RM) Fabrication Assembly Finishing Maintenance Gen.Services Indirect Supplies 3,000 2,500 2,000 1,000 2,500 Indirect Labour 18,000 10,000 8,000 4,500...

  • only use information for the Birdhouse.  This changes some dollar figures in the Cost of Goods Sold...

    only use information for the Birdhouse.  This changes some dollar figures in the Cost of Goods Sold Budget. The cost of the ending inventory Birdhouse will be $32 x 340 birdhouses Beginning Finished goods inventory $7,820 Ending FG inventory $10,880 Beginning WIP $14,500 Ending WIP $17,700 Chapter 22 Budgeting 1113 c. Desired inventories at January 31: Direct materials: Wood Plastic... . . . 32 Finished products: 340 units at $28per unit Y& 200 units at $34 per unit 180 ft. Birdhouse...

  • PR 21-3B Budgeted income statement and supporting budgets Obj. 4 4. Total direct labor cost in...

    PR 21-3B Budgeted income statement and supporting budgets Obj. 4 4. Total direct labor cost in Assembly Dept. The budget director of Gold Medal Athletic Co., with the assistance of the controller, treasurer production manager, and sales manager, has gathered the following data for use in developing the budgeted income statement for March: A. Estimated sales for March: $171,766 Batting helmet.... 1,200 units at $40 per unit 6,500 units at $160 per unit EXCEL TEMPLATE Football helmet B. Estimated inventories...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT