Answer (a):
Direct material cost per unit = Direct material per unit in kgs * £5 per kg
Direct labor cost per unit (for welding) = Direct labor required for welding per unit * £20
Direct labor cost per unit (for assembly and finishing) = Direct labor hours required for assembly or finishing per unit * £15
Answer (b):
Limiting factor is Skilled labor required for welding process.
Contribution per unit of limiting factor is calculated below:
Answer (c):
Skilled labor is in short supply but they are just enough to meet budgeted production.
Budgeted production is 250 units of each product
Available skilled labor = 250 * (4 + 4.5 + 4.5 + 3.5) = 4125 hours
As calculated in answer b above:
The highest contribution per limiting factor is from product C:
Hence to maximize contribution:
1. Produce Product C up to units as Max Sales
Skilled labor required = 280 * 4.5 = 1260 hours
Balance of skilled labor = 4125 - 1260 = 2865 hours
2. Next best contribution per unit of limiting factor is from Product B
Produce Product B up to units as Max Sales
Skilled labor required = 300 * 4.5 = 1350 hours
Balance of skilled labor = 2865 - 1350 =1515 hours
3. Next best contribution per unit of limiting factor is from Product A
Maximum sales units of product A = 400 units
Available skilled labor = 1515 hours
Produce product A = 1515/ 4 = 378.75 units or 379 units
As such optimized production plan will be:
Product A = 378.75 units (for calculations we are taking units in fraction)
Product B = 300 units
Product C = 280 units
Product D = 0 unit
Maximum total contribution that can be obtained = £1,472,750
The statement is as follows:
Q.3 Answer all parts Total 20 marks] The Engineering Manager in A Company Ltd. is responsible...
Q.3 Answer all parts Total 20 marks] The Engineering Manager in A Company Ltd. is responsible for maximising the profit from four product lines A, B, C and D. They have been provided with the following information; Direct materials (kgs) 80 90 95 70 Direct labour (hrs) Welding Assembly Finishing 4.5 9.5 4 3.5 4 8 4 4.5 4 Selling price per unit (E) 1500 2500 3000 1000 300 450 Max.sales for the period (in units) 400 280 250 Budgeted...
The Engineering Manager in A Company Ltd. is responsible for maximising the profit from four product lines A, B, C and D. They have been provided with the following information Direct materials (kgs) 80 90 95 70 Direct labour (hrs) Welding Assembly Finishing 4.5 3.5 9.5 4 Selling price per unit (E) 1500 2500 3000 1000 Max.sales for the period in units) 400 300 280 450 250 250 250 250 Budgeted production (in units) Additional information is also provided i....
The Engineering Manager in ABC Ltd is responsible for maximising the profit from three product lines X, Y ,Z. He/she has been provided with the following information: (b) The Engineering Manager in ABC Ltd is responsible for maximising the profit from three product lines X, Y and Z. He/she has been provided with the following information 85 120 Direct materials (E) Direct labour (hrs) Fabrication Assembly Finishing Selling price per unit (£) 100 4 2 3.75 550 210 3.5 2...
Q.2 As Engineering Manager in Your Company Ltd. you are responsible for maximising the profit from four product lines W, X, Y and Z. You have been provided with the following information Direct materials (kg) 75 90 85 70 Direct labour (h) 3.5 Fabrication Assembly Packaging 4.5 8 3.5 4.5 9.5 4 Selling price per unit (£) 1400 2350 3000 1200 300 450 Max. sales for the period (in units) 400 280 280 Budgeted production (in units) 300 270 270...
SECTION A Q.2 As Engineering Manager in Your Company Ltd. you are responsible for maximising the profit from four product lines W, X, Y and Z. You have been provided with the following information: Direct materials (kg) 75 90 85 70 Direct labour (h) Fabrication Assembly Packaging 4.5 8 3.5 4.5 9.5 4 3.5 6 Selling price per unit (S) 1400 2350 3000 1200 280 Max. sales for the period (in units) 400 300 450 Budgeted production 300 270 270...
Q.3 (a) Within the context of the manufacturing environment, explain the terms (i) Relevant cost (ii) Opportunity cost (iii) Contribution to profit (6 marks) (b) The Engineering Manager in ABC Ltd is responsible for maximising the profit from three product lines X, Y and Z. He/she has been provided with the following information Direct materials (E) Direct labour (hrs) Fabrication Assembly Finishing Selling price per unit (E) 100 85 120 4 2 3.75 550 210 3.5 2 3.5 480 220...
Question 3 Time: 20 minutes Total: 12 marks Orville Company’s standard and actual costs per unit are provided below for the most recent period. During this time period 650 units were actually produced. Standard Actual Materials: Standard: 2.5 metres at $2.7 per m. $6.75 Actual: 2.1 metres at $2.60 per m. $5.46 Direct labour: Standard: 1.6 hrs. at $8.40 per hr. 13.44 Actual: 1.7 hrs. at $8.50 per hr. 14.45 Variable overhead: Standard: 1.6 hrs....
(a) Phoenix Corporation has 4 departments in its factory consisting of two service departments, Human Resources (HR) and Information System (IS), and two production departments, Machining and Assembly. Each of the production departments produce a single product. The current costs of each department are: $60,000 $2,400,000 $8,756,000 S12,542,000 HR IS Machining Assembly The distribution and consumption of departments' services is given as follows: Service provided to: Machining Assembly HR IS Services provided by: 40% 35% HR 25% 10% IS 30%...
Belfast Industries manufactures a single product, the standard cost of which is: Direct materials - 6 kgs @ £4 kg Direct labour - 2 hour @ £8 hour Variable overhead - 2 hour @ £6 hr Fixed overhead - 2 hour @ £10 hr Total per unit £24.00 £16.00 £12.00 £20.00 £72.00 Other data relating to the standard cost: • • The fixed overhead rate is based on a budgeted output of 4,000 units per month The standard selling price...
Q.2 (Max Marks:90) Bombera Ltd operates at capacity and makes glass-topped dining tables and wooden chairs, which are then typically sold as sets of four chairs with one table. However, some customers purchase replacement or extra chairs, and others buy some chairs or a table only, so the sales mix is not exactly 4:1. Bombera Ltd is planning its annual budget for the financial year 2018. Information for 2018 follows: Input prices Direct materials Wood $5.30 per board metre Glass...