Question 16

Julia Penfield was working on a project and needed to update her boss on it’s CPI. If EV = 50,000, PV = 45,000, and AC = 41,000 what is the CPI?

Select one:

a. 1.21

b. 0.82

c. 1.16

d. 1.20

Q 17

Question 17

Kerri Lerner wanted to determine her project’s SPI. If EV = 42,000, PV = 40,000, and AC = 39,000, what is the SPI?

Select one:

a. 0.95

b. 0.98

c. 1.16

d. 1.05

Q 18

Question 18

If EV = 25,000, PV = 20,000, and AC = 29,000, what is the SV?

Select one:

a. -5,000

b. -1,000

c. 1,000

d. 5,000

Q 19

Question 19

If EV = 29,000, PV = 30,000, and AC = 25,000, what is the CV?

Select one:

a. -1,000

b. -4,000

c. 1,000

d. 4,000

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Q 16) EV = 50000

AC = 41000

CPI = EV/AC = 50000/41000 = 1.21

Q17) EV = 42000

PV = 40000

SPI = EV/PV = 42000/40000 = 1.05

Q18) EV = 25000

PV = 20000

SV = EV-PV = 25000-20000 = 5000

Q19) EV = 29000

AC = 25000

CV = EV-AC = 29000-25000 = 4000

Add a comment
Know the answer?
Add Answer to:
Q 16 Question 16 Julia Penfield was working on a project and needed to update her...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • to chapter 1. Given the following information for a one-year project, answer the following questions. Recall...

    to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...

  • Earned value calculation Based on the following Project data, answer the questions a and b. Activity...

    Earned value calculation Based on the following Project data, answer the questions a and b. Activity Duration Predecessors Task Budget A 7 days -- $16,850 B 10 days -- $22,500 C 8 days B $16,000 D 10 days A $12,790 E 7 days B $8,500 F 4 days D $10,550 At the end of Day 10, the status of the project is as follows. Activity % Complete Actual Cost A 100% $18,000 B 100% $23,000 C 0% $0 D 10%...

  • 3) You are in charge of the Aurora Project. Given the following project network, baseline, and...

    3) You are in charge of the Aurora Project. Given the following project network, baseline, and status information, (40 Points) B DI OA E • Develop status reports for periods 7 and complete the performance indices table. . Calculate the EAC, and VAC. Based on your data, what is the current status of the project? At completion? Rule 1 0% complete 2-50/50 3 - 0/100 ID LF SL Schedule information Total 0 1 2 PV 3 4 30 5 6...

  • I need help with the attached assignment. I attached the question and completed assigment. I just...

    I need help with the attached assignment. I attached the question and completed assigment. I just need help with answering one more question which is which is: Discuss a strategy that you would use to communicate the status of the project to stakeholders? Project Monitoring and Control Assignment Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project Case in Larson and Gray. Respond to Questions 1 and 2 of the case. Use Microsoft...

  • 19 This fact pattern provides information needed to answer Q#17-Q#21. Year 1 Transactions: On May 31,...

    19 This fact pattern provides information needed to answer Q#17-Q#21. Year 1 Transactions: On May 31, Year 1, Merle bought $14,000 of supplies on account on the day the firm was founded. This was the only purchase of supplies in Year 1. Later in Year 1, the firm returned defective supplies valued at $4,000 to the supplier. The cost of the supplies returned was deducted from Merle's account payable. At the end of Year 1, Merle's employees conducted a physical...

  • QUESTION 16 1. An occupational therapist must become aware of his or her dient's cultural background...

    QUESTION 16 1. An occupational therapist must become aware of his or her dient's cultural background to ensure: a reimbursement for occupational therapy services. h fair and equal treatment schedules c. accurate assessment and equitable treatment d appropriately biased opinions and perceptions. QUESTION 17 1. Which of the following statements best represents the concept of Spirituality: a the need to follow a daily ritual. h the strict celebration of certain holidays. c. the intentions to wear black clothing for mourning...

  • QUESTION 16 1. An occupational therapist must become aware of his or her dient's cultural background...

    QUESTION 16 1. An occupational therapist must become aware of his or her dient's cultural background to ensure: a reimbursement for occupational therapy services. h fair and equal treatment schedules c. accurate assessment and equitable treatment d appropriately biased opinions and perceptions. QUESTION 17 1. Which of the following statements best represents the concept of Spirituality: a the need to follow a daily ritual. h the strict celebration of certain holidays. c. the intentions to wear black clothing for mourning...

  • Question 9 Below is the time phased baseline budget for a project and a table showing...

    Question 9 Below is the time phased baseline budget for a project and a table showing the progress as of End of Period 7. 2 Baseline PV Total Task Time Period PV 0 1 3 5 6 7 8 10 11 A 30 15 15 40 20 20 с 80 10 10 10 10 20 20 D 30 5 5 5 5 10 E 20 5 5 5 5 F 40 10 20 5 5 10 5 5 PV by...

  • 20 This fact pattern provides information needed to answer Q#17-Q#21. Year 1 Transactions: On May 31,...

    20 This fact pattern provides information needed to answer Q#17-Q#21. Year 1 Transactions: On May 31, Year 1, Merle bought $14,000 of supplies on account on the day the firm was founded. This was the only purchase of supplies in Year 1. Later in Year 1, the firm returned defective supplies valued at $4,000 to the supplier. The cost of the supplies returned was deducted from Merle's account payable. At the end of Year 1, Merle's employees conducted a physical...

  • 1. How does Lexy’s age affect her decision to get an MBA?               A...

    1. How does Lexy’s age affect her decision to get an MBA?               A Aceto, Frank BUS 622 Week 3 Case Study Template F19- Excel AutoSave Off Share Review File Home Insert Page Layout Formulas Data View Help Tell me what you want to do AutoSum As 12A A Wrap Text Calibri General Fill Paste в I U Conditional Format as Insert Delete Format Sort & Find & - A 0 00 00 0 | Merge & Center...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT