41.      Assume that maintenance is a total of $90,000 at a level of 40,000 machine hours....

41.      Assume that maintenance is a total of $90,000 at a level of 40,000 machine hours. Also, assume that both 40,000 and 50,000 machine hours are within the relevant range for our company. If maintenance is a variable cost, compute the cost per machine hour at a level of 50,000 machine hours.

  1. $l.80 per hour
  2. $2.25 per hour
  3. It cannot be determined from the information given.

42.       Refer to the previous question. If maintenance is a mixed cost, compute the cost per machine hour at a level of 50,000 hours.

  1. $1.80 per hour
  2. $2.25 per hour
  3. It cannot be determined from the information given.

43.       Again, refer to question 3. If maintenance is a fixed cost, compute the cost per machine hour at a level of 50,000 hours.

  1. $1.80 per hour
  2. $2.25 per hour
  3. It cannot be determined from the information given.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

maintance total = $90000 level A mailine Herr = 40,000 torre at Relevant Rang of Company souro Hire al maintance is conable c41. a)$1.80 per hour

42. c) It can't be determined from the information given

43. b) $2.25 per hour

Add a comment
Know the answer?
Add Answer to:
41.      Assume that maintenance is a total of $90,000 at a level of 40,000 machine hours....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Deidoro Company has provided the following data for maintenance cost: Machine hours Maintenance cost Prior Year...

    Deidoro Company has provided the following data for maintenance cost: Machine hours Maintenance cost Prior Year 19,700 $36,300 Current Year 21,800 $39,450 Maintenance cost is a mixed cost with variable and fixed components. The fixed and variable components of maintenance cost are closest to: (Round your intermediate calculations to 2 decimal places.) Multiple Choice $6,750 per year; $1.810 per machine hour $6,750 per year: $1.500 per machine hour $36,300 per year; $1.810 per machine hour

  • Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...

    Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 54,000    $188,180        May 44,000    $163,980        June 64,000    $212,380        July 74,000    $236,580   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 52,800     Supervisory salaries (fixed) 44,000   Maintenance (mixed) 67,180   Total overhead cost $ 163,980 The...

  • Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...

    Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 54,000    $188,180        May 44,000    $163,980        June 64,000    $212,380        July 74,000    $236,580   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 44,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 52,800     Supervisory salaries (fixed) 44,000   Maintenance (mixed) 67,180   Total overhead cost $ 163,980 The...

  • At an activity level of 9,200 machine-hours in a month, Falks Corporation's total variable production engineering...

    At an activity level of 9,200 machine-hours in a month, Falks Corporation's total variable production engineering cost is $825,240 and its total fixed production engineering cost is $249,100. What would be the total production engineering cost per machine-hour, both fixed and variable, at an activity level of 9,400 machine-hours in a month? Assume that this level of activity is within the relevant range. (Round intermediate calculations to 2 decimal places.)

  • At an activity level of 8,500 machine-hours in a month, Falks Corporation's total variable production engineering...

    At an activity level of 8,500 machine-hours in a month, Falks Corporation's total variable production engineering cost is $708,900 and its total fixed production engineering cost is $168,210. What would be the total production engineering cost per machine-hour, both fixed and variable, at an activity level of 8,900 machine-hours in a month? Assume that this level of activity is within the relevant range. (Round intermediate calculations to 2 decimal places.)

  • At an activity level of 9,500 machine-hours in a month, Falks Corporation’s total variable production engineering...

    At an activity level of 9,500 machine-hours in a month, Falks Corporation’s total variable production engineering cost is $779,950 and its total fixed production engineering cost is $200,970. What would be the total production engineering cost per machine-hour, both fixed and variable, at an activity level of 9,900 machine-hours in a month? Assume that this level of activity is within the relevant range. (Round intermediate calculations to 2 decimal places.)

  • Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...

    Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 55,000 $ 183,500 May 45,000 $ 160,500 June 65,000 $ 206,500 July 75,000 $ 229,500 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 45,000 machine-hour level of activity is: Utilities (variable) $ 54,000 Supervisory salaries (fixed) 40,000 Maintenance (mixed) 66,500 Total overhead cost $ 160,500 Nova Company’s...

  • At an activity level of 9,900 machine-hours in a month, Falks Corporation's total variable production engineering...

    At an activity level of 9,900 machine-hours in a month, Falks Corporation's total variable production engineering cost is $882,090 and its total fixed production engineering cost is $196,000. What would be the total production engineering cost per machine-hour, both fixed and variable, at an activity level of 10,000 machine-hours in a month? Assume that this level of activity is within the relevant range. (Round intermediate calculations to 2 decimal places.) Multiple Choice $107.81 $108.88 $108.70 $108.35

  • Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown...

    Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 35.000 machine-hour level of activity is: Utilities (variable) Supervisory salaries (fixed) Maintenance (mixed) Total overhead cost $ 45,500 54,000 60,850 $160, 350 Nova Company's management wants to break down the maintenance cost into its variable and fixed cost elements. Required: 1. Estimate how much of the $236,250 of overhead cost in July was maintenance cost. (Hint: to do this,...

  • What is Dugan's variable cost component for maintenance costs? $  _____  per machine hour b) What is Dugan's fixed cost component for maintenance costs? $  c) What are the total expected maintenance cost when the activity level is 450 machine hours? $

    Dugan Industries has collected the following monthly expense data for use in analyzing the cost behaviour of maintenance costs:MonthTotal Maintenance CostsTotal Machine HoursJanuary$ 5,000400February$ 6,000500March$ 7,200700April$ 9,600900May$ 6,400600June$ 9,800890Use the high-low method to answer the following questions about Dugan Industries.Round your answers to two decimal places.a) What is Dugan's variable cost component for maintenance costs? $  _____  per machine hourb) What is Dugan's fixed cost component for maintenance costs? $ c) What are the total expected maintenance cost when the activity...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT