Steve Hannon, sales manager, has received an order for 250 stairways from Community Builders, Inc., a large housing developme
Your answer is correct. Calculate total overhead assigned under ABC. Total overhead assigned 79460 Click if you would like to
(c3) x Your answer is incorrect. Try again. What is the manufacturing cost per stairway under the proposed activity-based cos
0 0
Add a comment Improve this question Transcribed image text
Answer #1

First of all we need to calculate total manufacturing cost for 250 Stairways by using direct materials, direct labor and assigned overhead costs.

$$

Direct Materials

$103,800

Direct Labor

$113,100

Assigned Overhead

$79,460

Total Manufacturing Costs

$296,360

Number of Stairways

                     250

Manufacturing Cost per Stairway

(Total Manufacturing Cost $296,360 / 250 Stairways)

$1,185.44

Total manufacturing cost per stairway = $1185.44

Hope the above calculations, working and explanations are clear to you and help you in understanding the concept of question.... please rate my answer...in case any doubt, post a comment and I will try to resolve the doubt ASAP…thank you

Add a comment
Know the answer?
Add Answer to:
Steve Hannon, sales manager, has received an order for 250 stairways from Community Builders, Inc., a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Shaker Stairs Co.designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles,...

    Shaker Stairs Co.designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted overhead costs Amount $75,000 82,000 220,000 105,000 108,000 126,000 270,000...

  • Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components...

    Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted overhead costs Amount $75,000 82,000 220,000 100,000 120,000 126,000...

  • Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components...

    Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Amount Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities $75,000 82,000 210,000 100,000 96,000 126,000 270,000 Total budgeted overhead...

  • P17-3A--- Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway...

    P17-3A--- Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2017 are as follows. Overhead Cost Pools Amount Purchasing $ 75,000 Handling materials 82,000 Production (cutting, milling, finishing) 210,000 Setting up machines 105,000 Inspecting 90,000 Inventory control (raw materials and finished goods) 126,000 Utilities 180,000 Total...

  • Shaker Stairs Co.designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles,...

    Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows.Overhead Cost PoolsAmountPurchasing$75,000Handling materials82,000Production (cutting, milling, finishing)210,000Setting up machines100,000Inspecting96,000Inventory control (raw materials and finished goods)126,000Utilities450,000Total budgeted overhead costs$1,139,000For the last 4 years, Shaker Stairs Co. has been charging overhead to products on the basis...

  • Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components...

    Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Amount Purchasing $75,000 Handling materials 82,000 Production (cutting, milling, finishing) 220,000 Setting up machines 105,000 Inspecting 114,000 Inventory control (raw materials and finished goods) 126,000 Utilities 360,000 Total budgeted overhead...

  • ACCT212 SEM 191-ASSIGNM QUESTION Thakin Stairs Co. designs and builds factory-made premium wooden stairways for homes....

    ACCT212 SEM 191-ASSIGNM QUESTION Thakin Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2014 are as follows. Amount Overhead Cost Pools $ 69,000 Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities 82,000 210,000 95,000 90,000...

  • Assign overhead costs using traditional costing and A B C; compare results.

    Assign overhead costs using traditional costing and A B C; compare results.(LO 1 2 ), AN Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2022 are as follows.Overhead Cost PoolsAmountPurchasing$75,000Handling materials82,000Production (cutting, milling, finishing)210,000Setting up machines105,000Inspecting90,000Inventory control (raw materials and finished goods)126,000Utilities180,000Total budgeted overhead costs$868,000For...

  • Problem 4-3A a-b, c1-c3 (Video) (Part Level Submission) Shaker Stairs Co. designs and builds factory-made premium...

    Problem 4-3A a-b, c1-c3 (Video) (Part Level Submission) Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2020 are as follows. Overhead Cost Pools Amount Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted...

  • CALCULATOR PRINTER VERSION BACK NEXT Problem 17-3A (Part Level Submission) Shaker Stairs Co. designs and builds...

    CALCULATOR PRINTER VERSION BACK NEXT Problem 17-3A (Part Level Submission) Shaker Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, handrais) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2017 are as follows. Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT