For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.60 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.20 hours of direct labor time per unit and only a small amount of machining. Manufacturing overhead costs are currently assigned to products on the basis of direct labor-hours.

Despite the growing popularity of the company’s new LEC 90, profits have been declining steadily. Management is beginning to believe that there may be a problem with the company’s costing system. Direct material and direct labor costs per unit are as follows:

LEC 40 LEC 90
Direct materials $ 20.00 $ 46.00
Direct labor (0.20 hours and 0.60 hours @ $15.00 per hour) $ 3.00 $ 9.00

Management estimates that the company will incur $920,000 in manufacturing overhead costs during the current year and 80,000 units of the LEC 40 and 40,000 units of the LEC 90 will be produced and sold.

1-a. Compute the predetermined overhead rate assuming that the company continues to apply manufacturing overhead cost on the basis of direct labor-hours.

1-b. Using this rate and other data from the problem, determine the unit product cost of each product.

2. Management is considering using activity-based costing to assign manufacturing overhead cost to products. The activity-based costing system would have the following four activity cost pools:

Activity Cost Pool Activity Measure Estimated Overhead Cost
Maintaining parts inventory Number of part types $ 258,000
Processing purchase orders Number of purchase orders 80,000
Quality control Number of tests run 32,000
Machine-related Machine-hours 550,000
$ 920,000
Expected Activity
Activity Measure LEC 40 LEC 90 Total
Number of part types 750 1,400 2,150
Number of purchase orders 1,600 400 2,000
Number of tests run 1,400 1,800 3,200
Machine-hours 4,000 6,000 10,000

Determine the activity rate for each of the four activity cost pools. (Round your answers to 2 decimal places.)

3. Using the activity rates you computed in part (2), do the following:

a. Determine the per unit amount of manufacturing overhead cost that would be assigned to each product using the activity-based costing system.

b. Compute the unit product cost of each product.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1a

PREDETERMIND OVERHEAD RATE
DIRECT LABOUR HOUR REQUIRE TO PRODUCE LEC 40      16,000.00 (=80000*0.2)
DIRECT LABOUR HOUR REQUIRE TO PRODUCE LEC 90      24,000.00 (=40000*0.6)
Total Direct Labour hours require      40,000.00
Manufacturing overhead cost 9,20,000.00
Overhead rate based on labour hours 23 (=920000/40000)

1b

Unit Product Cost
Particular's LEC 40 LEC 90
Direct Material 20 46
Direct Labour 3 9
Overhead (Overhead rate * Labour require per unit) 4.6 13.8
Total 27.6 68.8

2

Activity rate for each activity
Activity Cost pool Activity measure number of total activity Estimated overhead cost Activity rate
Maintainig part inventory Number of part types                                       2,150.00                             2,58,000.00 120
Processing purchase order Number of purchase orders                                       2,000.00                                 80,000.00 40
Quality Control Number of test runs                                       3,200.00                                 32,000.00 10
machine related Machine - hours                                     10,000.00                             5,50,000.00 55
Total                             9,20,000.00

3a

Manufacturing Overhead Cost
LEC 40 LEC 90
Particular's Activity rate Number of activty Total cost Number of activty Total cost
Number of part types            120.00                         750.00      90,000.00                     1,400.00 1,68,000.00
Number of purchase orders               40.00                     1,600.00      64,000.00                         400.00      16,000.00
Number of test runs               10.00                     1,400.00      14,000.00                     1,800.00      18,000.00
Machine - hours               55.00                     4,000.00 2,20,000.00                     6,000.00 3,30,000.00
Total overhead 3,88,000.00 5,32,000.00
unit produce      80,000.00      40,000.00
Per unit overhead cost 4.85 13.3

3b

Unit Product Cost
Particular's LEC 40 LEC 90
Direct Material 20 46
Direct Labour 3 9
Overhead base on activity 4.85 13.3
Total 27.85 68.3
Add a comment
Know the answer?
Add Answer to:
For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...

    For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.80 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.60 hours of direct labor...

  • For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...

    For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.60 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.20 hours of direct labor...

  • For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...

    For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.80 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.40 hours of direct labor...

  • For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...

    For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.80 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.40 hours of direct labor...

  • For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...

    For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.80 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.40 hours of direct labor...

  • For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...

    For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.60 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.20 hours of direct labor...

  • For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...

    For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.60 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.20 hours of direct labor...

  • For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...

    For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.80 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.60 hours of direct labor...

  • For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...

    For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.60 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.20 hours of direct labor...

  • For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...

    For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.80 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.60 hours of direct labor...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT