Develop a logic network for the sequence of activities listed in the table. Calculate the ES, EF, LS and LF times for all activities.
What is the project duration?
What are the critical activities?
Activity | Duration | PIB |
5 | 2 | None |
10 | 3 | None |
15 | 3 | 5 |
20 | 4 | 5 |
25 | 1 | 10 |
30 | 2 | 15 |
35 | 2 | 25 |
40 | 5 | 20, 30, 35 |