Problem

The estimate for a three-story dormitory included 30 plumbing fixtures on each of the floo...

The estimate for a three-story dormitory included 30 plumbing fixtures on each of the floors. In developing the bid, the estimator used a production rate of 0.625 man-hours to install a fixture. The project superintendent is organizing the plumbing crews to include two plumbers per crew. What is the duration (in days) of the activity to install all the fixtures in the domitory. Assume an eight-hour workday.