Develop a logic network for the sequence of activities listed in the table.
Activity | PIB |
5 | None |
10 | 5 |
15 | 5 |
20 | 10, 15 |
25 | 15 |
30 | 20 |
35 | 20, 25 |
40 | 25 |
45 | 30, 35, 40 |