Problem

Theory of Constraints Bakker Industries sells three products (611, 613, and 615) that it m...

Theory of Constraints Bakker Industries sells three products (611, 613, and 615) that it manufactures in four departments. Both labor and machine time are applied to products in each of the four departments. The machine-processing and labor skills required in each department prohibit switching either machines or labor from one department to another. However, Bakker has a good supply of both full-time and part-time labor and does not expect hiring or retention of employees to be a problem. Because of the availability of part-time labor, Bakker considers labor a variable cost and includes it in the calculation of throughput margin.

Bakker’s management is planning its production schedule for the next several months. Some machines will be out of service for extensive overhauling. Available machine times by department for each of the next six months are as follows:

 

Department

 

1

2

3

4

Normal machine capacity in machine-hours

3,500

3,500

3,000

3,500

Capacity of machines being repaired, in machine-hours

500

400

300

200

Available capacity in machine-hours

3,000

3,100

2,700

3,300

Labor and machine specifications per unit of product follow:

 

 

Department

Product

Labor and Machine Time

1

2

3

4

611

Direct labor-hours

2

3

3

1

 

Machine-hours

2

1

2

2

613

Direct labor-hours

1

2

0

2

 

Machine-hours

1

1

0

2

615

Direct labor-hours

2

2

1

1

 

Machine-hours

2

2

1

1

The Sales Department’s forecast of product demand over the next six months is as follows:

Product

Monthly Sales

611

500 units

613

400 units

615

1,000 units

Bakker’s inventory levels will not increase or decrease during the next six months. The unit price and cost data valid for the next six months follow:

 

Product

 

611

613

615

Price

$196

$123

$167

Direct materials

7

13

1 7

Direct labor

 

 

 

    Department 1

12

6

12

    Department 2

21

14

14

    Department 3

24

16

    Department 4

9

18

9

Variable overhead

27

20

25

Fixed overhead

15

10

32

Variable selling

3

2

4

Required

1. Determine whether Bakker can meet the monthly sales demand for the three products. What department is a constraint, if any?


2. What monthly production schedule would be best for Bakker Industries? Assume that Bakker includes all variable manufacturing costs in calculating throughput.

Step-by-Step Solution

Request Professional Solution

Request Solution!

We need at least 10 more requests to produce the solution.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the solution will be notified once they are available.
Add your Solution
Textbook Solutions and Answers Search
Solutions For Problems in Chapter 13