Problem

Constraint Analysis, Flow Diagrams (Appendix) Silver Aviation assembles small aircraft for...

Constraint Analysis, Flow Diagrams (Appendix) Silver Aviation assembles small aircraft for com­mercial use. The majority of its business is with small freight airlines serving areas whose airports do not accommodate larger planes. The remainder of Silver’s customers are commuter airlines and individuals who use planes in their businesses, such as the owners of larger ranches. Silver recently expanded its market into Central and South America, and the company expects to double its sales over the next three years.

To schedule work and track all projects, Silver uses a flow diagram. The diagram for the assembly of a single cargo plane is shown in Exhibit 1. The diagram shows four alternative paths with the critical path being ABGEFJK. Bob Peterson, president of Coastal Airlines, recently placed an order with Silver Aviation for five cargo planes. During contract negotiations, Bob agreed to a delivery time of 13 weeks (five work days per week) for the first plane with the balance of the planes being delivered at the rate of one every four weeks. Because of problems with some of the aircraft that Coastal is currently using, Bob contacted Grace Vander, sales manager for Silver Aviation, to ask about improving the delivery date of the first cargo plane. Grace replied that she believed the schedule could be shortened by as much as 10 work days or two weeks, but the cost of assembly would increase as a result. Bob said he would be willing to consider the increased costs, and they agreed to meet the following day to review a revised schedule that Grace would prepare.

Because Silver Aviation previously assembled aircraft on an accelerated basis, the company has a list of costs for this purpose. Grace used the data shown in Exhibit 2 to develop a plan to cut 10 working days from the schedule at a minimum increase in cost to Coastal Airlines. Upon com­pleting her plan, she reported to Bob that Silver would be able to cut 10 working days from the schedule for an associated increase in cost of $6,600. Grace’s Exhibit 3 shows accelerated assembly schedule for the cargo plane starting from the regularly scheduled days and cost.

EXHIBIT 1 Flow Diagram for Plane Assembly

EXHIBIT 2 Crash Cost Listing

 

Expected Activity Times

Direct Cost

 

Activity

Regular

Accel.

Regular

Accel.

Added Crash Cost Per Reduced Day

AB Frame fuselage

20 days

16 days

$12,000

$16,800

$1,200

BC Wing placement

6

5

3,600

5,000

1,400

CD Engine mount

9

7

6,600

8,000

700

DE Landing gear

7

5

5,100

6,700

800

BE Cargo doors

3

3

1,400

1,400

BG Electrical wiring

15

13

9,000

11,000

1,000

GE Instrument panel

8

6

5,700

8,300

1,300

EF Electrical tests

11

10

6,800

7,600

800

GH Exterior shell

9

7

4,200

5,200

500

FJ Interior finish

8

7

3,600

4,000

400

HJ Exterior paint

6

5

3,600

4,000

400

JK Final testing

3

2

3,500

4,400

900

 

 

 

$65,100

$82,400

 

EXHIBIT 3 Accelerated Plane Assembly Schedule

Activity Accelerated

Additional Cost per Day

Total Direct Cost

 

 

$65,100

HJ by one day

$400

65,500

FJ by one day

400

65,900

GH by two days

500

66,900

CD by two days

700

68,300

EF by one day

800

69,100

DE by two days

800

70,700

BG by one day

1,000

71,700

Required

1. Is Grace’s plan satisfactory? Why or why not?


2. Revise the accelerated assembly schedule so that Coastal Airlines will take delivery of the first plane ahead of schedule at the least incremental cost to Coastal.


3. Calculate the incremental costs that Bob will have to pay for this revised accelerated delivery.

Step-by-Step Solution

Request Professional Solution

Request Solution!

We need at least 10 more requests to produce the solution.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the solution will be notified once they are available.
Add your Solution
Textbook Solutions and Answers Search
Solutions For Problems in Chapter 13