White Maple Company produces maple bookcases to customer order. It received an order from a customer to produce 15,000 bookcases. The following information is available for the production of the bookcases.
Process time | 16.0 days |
Inspection time | 0.5 days |
Move time | 5.5 days |
Wait time | 18.0 days |
Required
1. Compute the company’s manufacturing cycle time.
2. Compute the company’s manufacturing cycle efficiency. Interpret your answer.
Analysis Component
4.Assume that White Maple wishes to increase its manufacturing cycle efficiency to 0.75. What are some ways that it can accomplish this?