For the following questions, circle the best response.
Use the following data for Questions 7 through 10.
Air Fresh Industries uses a standard overhead costing system for the production of its EnergyPro cooling systems. Based on a capacity of 120,000 direct labor hours, the standard costs per unit of EnergyPro are applied to production as follows:
Variable overhead portion | 2 hours @ $16 = $32 |
Fixed overhead portion | 2 hours @ $10 = $20 |
During August, 30,000 units of EnergyPro were scheduled for production, but only 27,000 units were actually produced. Actual direct labor cost incurred was $885,600 for 55,350 actual hours of work. Actual variable overhead cost incurred was $863,450, and actual fixed overhead cost was $622,000.
The variable overhead spending variance was
a. $540 U.
b. $21,600 F.
c. $22,140 F.
d. $24,000 F.
e. $96,540 F.
We need at least 10 more requests to produce the solution.
0 / 10 have requested this problem solution
The more requests, the faster the answer.