Direct labor variances — insurance company application The Foster Insurance Company develo...

Direct labor variances — insurance company application The Foster Insurance Company developed standard times for processing claims. When a claimwas received at the processing center, it was first reviewed and classified as simple or complex. The standard time for processing was:

Simple claim  

36 minutes

Complex claim  

1.25 hours

Employees were expected to be productive 7.5 hours per day. Compensation costs were $135 per day per employee. During July, which had 20 working days, the following number of claims were processed:

Simple claims  

3,000 processed

Complex claims

960 processed

Required:

a. Calculate the number of workers that should have been available to process July claims.


b. Assume that 23 workers were actually available throughout the month of July. Calculate a labor efficiency variance expressed as both a number of workers and a dollar amount for the month.

Step-by-Step Solution

Request Professional Solution

Request Solution!

We need at least 10 more requests to produce the solution.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the solution will be notified once they are available.
Add your Solution
Textbook Solutions and Answers Search