QUESTION 7 The Armstrong Corporation developed a flexible budget for its production process. Armstrong budgeted to use 16,000

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Materials Quantity Variance

= (AQ-SQ) *SP

= (20,000 - 16,000)*17

= 4000 * 17

= 68,000 Unfavorable

Option B is the answer

Add a comment
Know the answer?
Add Answer to:
QUESTION 7 The Armstrong Corporation developed a flexible budget for its production process. Armstrong budgeted to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 16- A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and w...

    16- A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22,000 hours at a total labor cost of $269,500. What is the direct labor rate variance? Multiple Choice $27,500 unfavorable. $22,000 favorable. $16,000 unfavorable. $16,000 favorable. $6,000 unfavorable. 20- Summerlin Company budgeted 4,000 pounds of material costing $5.00 per pound to produce 2,000 units. The company actually used 4,500 pounds that cost $5.10...

  • Summerlin Company budgeted 4,100 pounds of material costing $6.00 per pound to produce 2,000 units. The...

    Summerlin Company budgeted 4,100 pounds of material costing $6.00 per pound to produce 2,000 units. The company actually used 4,600 pounds that cost $6.10 per pound to produce 2,000 units. What is the direct materials quantity variance? Multiple Choice 0 $3,050 unfavorable. 0 $460 unfavorable. 0 $3,460 unfavorable. 0 $3,000 unfavorable. 0 $410 unfavorable. Summerlin Company budgeted 4,100 pounds of material costing $6.00 per pound to produce 2,000 units. The company actually used 4,600 pounds that cost $6.10 per pound...

  • NU Elticiency Variances Simon Company had the following information ng information available: Budgeted Costs The budget...

    NU Elticiency Variances Simon Company had the following information ng information available: Budgeted Costs The budget was to manufacture and sell 5,- ufacture and sell 5,200 units Direct Materials: 4 pounds per unit @ $2.00 per po Direct Labor: 1.5 hours per units @ $15 per nou $2.00 per pound and had the following costs: Direct Materials: 19.500 pounds that cost $41,480 Direct Labor: 8,000 hours that cost $118,900 Required 1. Calculate the amount actually spent on direct materials 2....

  • please provide an explanation. thank you Budgeted Costs The budget was to manufacture and sell 6,200...

    please provide an explanation. thank you Budgeted Costs The budget was to manufacture and sell 6,200 units Direct Materials: 4 pounds per unit @ $2.00 per pound Direct Labor: 1.5 hours per units @ $15 per hour The company sold 5,000 units and had the following costs: Direct Materials: 19,500 pounds that cost $41480 Direct Labor 8.000 hours that cost $118.900 9. Actual Cost of Direct Labor 10. Flexible Budget for Direct Labor 11. Flexible Budget Variance for Direct Labor...

  • Wagner Company developed the following standard costs for its product for 2011: Direct Materials - 4...

    Wagner Company developed the following standard costs for its product for 2011: Direct Materials - 4 pounds at $4.50 per pound Direct Labor - 2 hours at $10.50 per hour Based on their flexible budget, budgeted Manufacturing Overhead costs are $80,000 of fixed costs plus variable costs of $4 per direct labor hour. Normal capacity is set at 20,000 units of product OR 40,000 DIRECT LABOR HOURS. (20,000 units x 2 labor hours per unit) Actual costs for 2011 were...

  • answer starting at 5 down DUSLS The budget was to manufacture and sell 5,200 units Direct...

    answer starting at 5 down DUSLS The budget was to manufacture and sell 5,200 units Direct Materials: 4 pounds per unit @ $2.00 per pound Direct Labor: 1.5 hours per units @ $15 per hour ne company sold 5,000 units and had the following costs: Direct Materials: 19,500 pounds that cost $41,480 Direct Labor: 8,000 hours that cost $118,900 Required 1. Calculate the amount actually spent on direct materials 2. Calculate the flexible budget for direct materials 3. Calculate the...

  • 1.A company produces widgets with budgeted standard direct materials of 2 pounds per widget at $5...

    1.A company produces widgets with budgeted standard direct materials of 2 pounds per widget at $5 per pound. Standard direct labor was budgeted at 0.5 hour per widget at $15 per hour. The actual usage in the current year was 25,000 pounds (an actual cost of $4.75 per pound) and 3,000 hours (an actual rate of $17 per pound )to produce 10,000 widgets. What was the direct labor usage variance? A. $30,000 favorable. B. $25,000 favorable. C. $25,000 unfavorable. D....

  • 1. What raw materials cost would be included in the company’s flexible budget for March? 2....

    1. What raw materials cost would be included in the company’s flexible budget for March? 2. What is the materials quantity variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input the amount as a positive value.) 3. What is the materials price variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no...

  • 3- Claremont Company sells refurbished copiers. During the month, the company sold 180 copiers at an...

    3- Claremont Company sells refurbished copiers. During the month, the company sold 180 copiers at an average price of $3,000 each. The budget for the month was to sell 175 copiers at an average price of $3,200. The expected total sales for 180 copiers were: Multiple Choice $540,000. $576,000. $525,000. $560,000. $550,000. 9- A job was budgeted to require 3 hours of labor per unit at $11.00 per hour. The job consisted of 8,000 units and was completed in 22,000...

  • The standard materials cost to produce 1 unit of Product R is 6 pounds of material at a standard price of $50...

    The standard materials cost to produce 1 unit of Product R is 6 pounds of material at a standard price of $50 per pound. In manufacturing 8,000 units, 47,000 pounds of material were used at a cost of $51 per pound. What is the direct materials quantity variance? Multiple Choice $47,000 unfevorable $47000 favorable $50,000 unfavcracle Multiple Choice $47,000 unfavorable. $47,000 favorable. $50,000 unfavorable $50,000 favorable. Prex 1 of 20 Next Fletcher Company collected the following data regarding production of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT