Question

Problem 18.1A Determining the cost to be capitalized for acquisition of assets. LO 18-1 On January 6, 2019, Baxter Company pu

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

Baxter Company

1. Computation of the capitalized cost of the manufacturing plant –

Capitalized cost of manufacturing facility     $3,300,000

  1. Computation of the capitalized cost of the land –

Cost of land acquisition

$1,500,000

Add: cost of razing old building

$11,500

value of salvaged materials

($6,400)

permit to raze

$2,100

$7,200

Add: Attorney fee

$5,500

Insurance cost

$2,800

Cost of land

$1,515,500

  1. Capitalized cost of land improvements –

Cost of land improvements

cost of filling the site

41,400

cost of leveling the site

$23,000

sidewalks and curbs

$116,000

cost of paving parking area

$116,700

cost of land improvements

$297,100

Add a comment
Know the answer?
Add Answer to:
Problem 18.1A Determining the cost to be capitalized for acquisition of assets. LO 18-1 On January...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • e Cambridge Business Publishee Accounting for Long-Lived and Intangible Assets Chapter 9 PROBLEMS-SET A P9-1A. Acquisition...

    e Cambridge Business Publishee Accounting for Long-Lived and Intangible Assets Chapter 9 PROBLEMS-SET A P9-1A. Acquisition Cost of Long-Lived Assets The following items represent expenditures (or receipts) LO1 related to the construction of a new home office for Norma Company. Cost of land site, which included an old apartment building appraised at $75,000 Legal fees, including fee for title search. .. Payment of apartment building mortgage and related interest due at time of sale Payment for delinquent property taxes assumed...

  • Exercise 18.1 Determining the elements that make up the cost of an asse LO 18-1 The...

    Exercise 18.1 Determining the elements that make up the cost of an asse LO 18-1 The following costs were incurred by Imports Auto Parts in connection with the construction o retail store building: Cost of land, including $18,400 of legal costs Cost to demolish old building Costs of grading land for building site Costs related to building construction Legal costs relating to building permits Costs of paving parking lot $340,000 18,450 10,600 890,000 16,825 94,000 1 & 2. What are...

  • Determining asset cost and recording full-year depreciation Road Runner High-Speed Online, Inc. incurred the following costs...

    Determining asset cost and recording full-year depreciation Road Runner High-Speed Online, Inc. incurred the following costs in acquiring it's property and equipment: A. $250,000 - Purchase price of four acres of land, including an old building that will be used for a garage (75% to land and 25% to building). B. $8,100 - Dirt and leveling of land. C. $17,650 - Fence around the land. D. $600 - Attorney fee for title search on the land. E. $5,900 - Delinquent...

  • 485 Chapter 9 Long-Term Assets: Fixed and intangible Problems: Series A Оb, 1 PR 9-1A Allocating...

    485 Chapter 9 Long-Term Assets: Fixed and intangible Problems: Series A Оb, 1 PR 9-1A Allocating payments and receipts to fixed asset accounts The following payments and receipts are related to land, land improvements, and buildings acquired for use in a wholesale ceramic business. The receipts are identified by an asterisk. Land, $400,000 2,500 285,000 55,000 15,500 5,000 Fee paid to attorney for title search ... Cost of real estate acquired as a plant site: Land. a. b. Building (to...

  • s101(LO 1) (Acquisition Costs of Realty) The following expenditures and receipts are related o land, land...

    s101(LO 1) (Acquisition Costs of Realty) The following expenditures and receipts are related o land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses. . Money borrowed to pay building contractor (signed a note) h Payment for construction from note proceeds $(275,000) 275,000 c. Cost of land fill and clearing d. Delinquent real estate taxes on property assumed by purchaser e. Premium on 6-month insurance policy during construction fRefund of 1-month insurance...

  • Allocating Payments and Receipts to Fixed Asset Accounts The following payments and receipts are related to...

    Allocating Payments and Receipts to Fixed Asset Accounts The following payments and receipts are related to land, land improvements, and buildings acquired for use in a wholesale apparel business. The receipts are identified by an asterisk a. Fee paid to attorney for title search $3,600 b. 720,000 Cost of real estate acquired as a plant site: Land Building (to be demolished) 60,000 c. Finder's fee paid to real estate agency 23,400 d. Delinquent real estate taxes on property, assumed by...

  • $400,000 PR 9-1A Allocating payments and receipts to fixed asset accounts Obj. 1 The following payments...

    $400,000 PR 9-1A Allocating payments and receipts to fixed asset accounts Obj. 1 The following payments and receipts are related to land, land improvements, and buildings acquired for use in a wholesale ceramic business. The receipts are identified by an asterisk. A Fee paid to attorney for title search .. .......... B. Cost of real estate acquired as a plant site: Land........ Building (to be demolished)........... C. Delinquent real estate taxes on property, assumed by purchaser... D. Cost of razing...

  • Allocating Payments and Receipts to Fixed Asset Accounts The following payments and receipts are related to...

    Allocating Payments and Receipts to Fixed Asset Accounts The following payments and receipts are related to land, land improvements, and buildings acquired for use in a wholesale ceramic business. The receipts are identified by an asterisk. Fee paid to attorney for title search $3,700 Cost of real estate acquired as a plant site: Land 390,000 Building (to be demolished) 37,100 Delinquent real estate taxes on property, assumed by purchaser 21,900 Cost of tearing down and removing building acquired in (b)...

  • The following payments and receipts are related to land, land improvements, and buildings acquired for use...

    The following payments and receipts are related to land, land improvements, and buildings acquired for use in a wholesale ceramic business. The receipts are identified by an asterisk. a. Fee paid to attorney for title search $ 2,480 b. Cost of real estate acquired as a plant site: Land 273,700 Building (to be demolished) 51,500 c. Delinquent real estate taxes on property, assumed by purchaser 16,570 d. Cost of tearing down and removing building acquired in (b) 5,495 e.* Proceeds...

  • F10.1 (LO 1) (Acquisition Costs of Realty) The following expenditures and receipts are related to land,...

    F10.1 (LO 1) (Acquisition Costs of Realty) The following expenditures and receipts are related to land, land improvements, and buildings acquired for use in a business enterprise. The receipts are enclosed in parentheses. a. Money borrowed to pay building contractor (signed a note) $(275,000) b. Payment for construction from note proceeds 275,000 c. Cost of land fill and clearing 8,000 d. Delinquent real estate taxes on property assumed by purchaser 7,000 e. Premium on 6-month insurance policy during construction 6,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT