Question

Questions 17-18 DIRECTIONS: Answer Questions 17 through 18 based on the information below. A contract has been awarded to the
0 0
Add a comment Improve this question Transcribed image text
Answer #1

17) % of completion for 2016 is = (Actual cost to date/(Actual cost to date Estimated cost to complet))*100 % of completion f

Add a comment
Know the answer?
Add Answer to:
Questions 17-18 DIRECTIONS: Answer Questions 17 through 18 based on the information below. A contract has...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Required information The following information applies to the questions displayed below.) Beavis Construction Company was the...

    Required information The following information applies to the questions displayed below.) Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,830,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2017 2018 441,000 $1,130,000 1,029.000 D 415,000 1,415,000 315,000 2,515,000 Assume that Beavis recognizes revenue on...

  • The contract price for a 3-year construction contract is $100 The actual cost and estimated costs...

    The contract price for a 3-year construction contract is $100 The actual cost and estimated costs for each vear are given below: Items 2016 2017 2018 Actual cost incurred each year $10 Estimated cost to complete $40 Under Percentage of Completion method (You first prepare the table I showed you in the class to make your calculations easier) S20 $30 1. Compute Actual cost incurred to date 2. Compute total estimated cost for each year 3. Compute estimated gross profit...

  • Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the...

    Required information [The following information applies to the questions displayed below.] Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,750,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below: 2017 2018 Costs incurred during the year $ 469,000 $ 1,050,000 Estimated costs to complete 871,000 0 Billings during the year 480,000 1,270,000 Cash collections during the year 380,000 1,425,000 Assume that Beavis recognizes...

  • Required information SB Problem The following information applies to the questions displayed below.) Beavis Constru...

    Required information SB Problem The following information applies to the questions displayed below.) Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2017 and completed in 2018. Cost and other data are presented below. Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2017 2018 $ 450,000 $1,108, eee 1,050,000 400,000 1,400,000 300,000 1,500,000 Problem 5-284 Assume...

  • Problem 18-11 Your answer is partially correct. Try again. On July 1, 2017, Coronado Construction Company...

    Problem 18-11 Your answer is partially correct. Try again. On July 1, 2017, Coronado Construction Company Inc. contracted to build an office building for Gumbel Corp. for a total contract price of $1,880,000. On July 1, Coronado estimated that it would take between 2 and 3 years to complete the building. On December 31, 2019, the building was deemed substantially completed. Following are accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Gumbel for 2017,...

  • Fender period. Construction Company receives a contract to construct a building over a 3 year Information...

    Fender period. Construction Company receives a contract to construct a building over a 3 year Information relating to the performance of the contract is summarized as follows: 2015 2016 2017 S 16,000,000 Cumulative construction costs incurred to date Estimated costs to complete Billings during the year Cash collected during the year 6,000,000 8,000,000 6,000,000 3,000,000 8,000,000 7,000,000 4,000,000 5,000,000 Required: 1. How much is Fender Construction charging to build this athletic stadium? In other words, what is the contract price...

  • Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking...

    Shanahan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It is estimated that the complex will take 3 years to construct. Additional information follows. Estimated cost of complex Contract price AA 600,000 900,000 The following data pertain to the construction period. 2019 610,000 $ 6100 A 2017 270,000 330,000 270,000 240,000 2018 450,000 150,000 550,000 500,000 Costs to date Estimated costs to complete Progress billings to date Cash collected to date $...

  • Problem 18-9 Sheridan Construction Company has entered into a contract beginning January 1, 2017, to build...

    Problem 18-9 Sheridan Construction Company has entered into a contract beginning January 1, 2017, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $897,000. The following data pertain to the construction period. Costs to date Estimated costs to complete Progress billings to date Cash collected to date 2017 $263,120 334,880 273,000 2018 $460,460 137,540 556,000 506,000 2019...

  • Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction...

    Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the...

  • ! Required information [The following information applies to the questions displayed below.] In 2021, the Westgate...

    ! Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,490,000 5,810,000 2,030,000 1,815,000 2022 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT