(25 MARKS) Highland Construction entered into a contract to to Johor Bahru. The agreed contract price was RM4 million, the po
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Extract of Statement of Profit and Loss:
Particulars                  2,015                  2,016                   2,017
Sales for the current year          1,219,355          1,420,645          1,760,000
Less:
Cost incured in the current year              945,000              855,000          1,300,000
Profit (Only from this contract)              274,355              565,645              460,000
Working Note: Calculation of Cost and Sales to be recognised during the year:
Particulars                  2,015                  2,016                   2,017
Cumulative Cost Incurred              945,000          1,800,000          3,100,000
Expected Future Cost to be Incurred          2,155,000          1,200,000                          -  
         3,100,000          3,000,000          3,100,000
Cost for the current year              945,000              855,000          1,300,000
Stage of Completion (Incurred/Total) 30.48% 60.00% 100.00%
Total value of Sale from this contract          4,000,000          4,400,000          4,400,000
Cumulative to be recognised as per stage of completion          1,219,355          2,640,000          4,400,000
Sales for the current year          1,219,355          1,420,645          1,760,000
Exract of Balance Sheet:
Assets                  2,015                  2,016                   2,017
Gross amount due from customers for contract work
Sales recognised till date          1,219,355          2,640,000          4,400,000
Less: Progress Billing to date              800,000          1,900,000          3,000,000
             419,355              740,000          1,400,000

Final Check:

One way to cross check the answer is that the total of Profit = 1,300,000 is equal to Revenue (4,400,000) minus Cost (3,100,000)

Add a comment
Know the answer?
Add Answer to:
(25 MARKS) Highland Construction entered into a contract to to Johor Bahru. The agreed contract price...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • QUESTION 1 (25 MARKS) Contract No.12476 commenced during year 2017 and has a fixed contract price...

    QUESTION 1 (25 MARKS) Contract No.12476 commenced during year 2017 and has a fixed contract price of RM900,000. During the year 2017, costs incurred for materials, wages and sub-contractors charges amounted to RM420,000. A plant costing RM78,000 was purchased during year 2017 specifically for contract No.12476. At the end of year 2017: i. The plant was valued at RM62,000. ii. Unused materials on site were valued at RM80,000. in. It is estimated that further costs recognise RM290,000 would be incurred...

  • QUESTION 1 (25 MARKS) Contract No. 12476 commenced during year 2017 and has a fixed contract...

    QUESTION 1 (25 MARKS) Contract No. 12476 commenced during year 2017 and has a fixed contract price of RM900.000. During the year 2017, costs incurred for materials, wages and sub-contractors charges amounted to RM420,000. A plant costing RM78,000 was purchased during year 2017 specifically for contract No.12476. At the end of year 2017: i. The plant was valued at RM62,000. ii. Unused materials on site were valued at RM80,000. iii. It is estimated that further costs recognise RM290,000 would be...

  • b) Dollah Construction Berhad agreed to construct a building where the contract price was RM50 million...

    b) Dollah Construction Berhad agreed to construct a building where the contract price was RM50 million and the estimated total costs were RM46 million. By the end of the first year, 40% of the work was completed. Required: i) Determine the gross profit recognised in the first year. (6 marks) (CLO2:PLO2:C2) ii) If the contract yields a loss of RM5 million, how would the company recognise the total loss? (2 marks) (CLO2:PLO2:C3) iii) What is contract revenue and how Dollah...

  • On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $220 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 2021 2022 2023 $ 40 $80 $50...

  • Bob Ltd signs a contract on 1 April 2018 to build an office building. The construction...

    Bob Ltd signs a contract on 1 April 2018 to build an office building. The construction is scheduled to commence 1 July 2018 and the estimated date of completion is 30 June 2021. The cost of the building is estimated to be $155m and the total contract price is fixed at $180m. The following data relates to the construction period: For the year ended 30 June 2019 2020 2021 $’000 $’000 $’000 Costs to date 46,500 108,500 155,000 Estimated Costs...

  • In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract...

    In 2015 The Big Boss Construction Company, started a 3 year project at a fixed contract price of $22,000,000. The estimated construction costs were $15,500,000. The project was completed on time during the 2917 year. The following information is available for the three year period of the construction project. 2015 2016 2017 Costs Incurred to Date $6,188,000 $12,360,000 $15,875,000 Estimated Costs to Complete 9,282,000 3,090,000 -- Billings to Date 6,400,000 18,890,000 22,000,000 Collections to Date 5,100,000 17,110,000 21,630,000 Required 1....

  • (25 MARKS) QUESTION 3 Sime Garby Berhad is a publicly listed company. The following is the...

    (25 MARKS) QUESTION 3 Sime Garby Berhad is a publicly listed company. The following is the Statement of Profit and Loss and the Statements of Financial Position for the company for the year 2017: Statement of Profit or Loss for the year ended 31 December 2017 2017 2016 RM000 BM'000 25.500 17.250 Revenue Cost of sales (14,800) (10.350) Gross profit 10,700 6.900 Distribution costs (2,700) (1.850) Administrative expenses (2,100) (1.450) Finance costs (650) (100) Profit before tax 5,250 3,500 Income...

  • 1- Al –Tawaan Plastics entered into a contract to install a pipeline for a fixed price...

    1- Al –Tawaan Plastics entered into a contract to install a pipeline for a fixed price of OR2,200,000. Al –Tawaan uses the cost recovery method of revenue recognition. 2015 2016                2017 Cost incurred 250,000                       1,600,000        450,000 Estimated cost to complete      1,550,000 500,000 0 In 2015, Al –Tawaan would report (rounded to the nearest thousand) gross profit (loss) of: Select one: a. OR 73,000 b.  OR 0 c.  OR 56,000 d.  OR (100,000) 2- Al –Tawaan Plastics entered into a contract to install...

  • On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...

    On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $360 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year Estimated costs to complete as of December 31 S 30 140 $40...

  • Fender period. Construction Company receives a contract to construct a building over a 3 year Information...

    Fender period. Construction Company receives a contract to construct a building over a 3 year Information relating to the performance of the contract is summarized as follows: 2015 2016 2017 S 16,000,000 Cumulative construction costs incurred to date Estimated costs to complete Billings during the year Cash collected during the year 6,000,000 8,000,000 6,000,000 3,000,000 8,000,000 7,000,000 4,000,000 5,000,000 Required: 1. How much is Fender Construction charging to build this athletic stadium? In other words, what is the contract price...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT