Question

1- Al –Tawaan Plastics entered into a contract to install a pipeline for a fixed price...

1-

Al –Tawaan Plastics entered into a contract to install a pipeline for a fixed price of OR2,200,000. Al –Tawaan uses the cost recovery method of revenue recognition.

2015 2016                2017

Cost incurred 250,000                       1,600,000        450,000

Estimated cost to complete      1,550,000 500,000 0

In 2015, Al –Tawaan would report (rounded to the nearest thousand) gross profit (loss) of:

Select one:

a. OR 73,000

b.  OR 0

c.  OR 56,000

d.  OR (100,000)

2-

Al –Tawaan Plastics entered into a contract to install a pipeline for a fixed price of OR2,200,000. Al –Tawaan uses the cost recovery method of revenue recognition.

2015 2016                2017

Cost incurred 250,000                       1,600,000        450,000

Estimated cost to complete 1,550,000 500,000 0

In 2016, Al –Tawaan would report (rounded to the nearest thousand) gross profit (loss) of:

Select one:

a. OR(223,000)

b.  OR(206,000)

c. OR(150,000)

d. OR0.

3-

Al –Tawaan Plastics entered into a contract to install a pipeline for a fixed price of OR2,200,000. Al –Tawaan uses the cost recovery method of revenue recognition.

2015                2016                2017

Cost incurred 250,000 1,600,000        450,000

Estimated cost to complete 1,550,000 500,000 0

In 2017, Al –Tawaan would report (rounded to the nearest thousand) gross profit (loss) of:

Select one:

a. OR 50,000

b.  OR 2,000

c. OR(100,000)

d. OR 123,000

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Under Cost Recovery method of revenue recognition , until coreesponding costs are fully recovered gross profit recognition will be deferred in case of a long term contract also. If loss , it should be recognized in that year.

In this question the collection amount is not given. Therefore answer is Gross profit should be recognized

1. 0 for year 2015

2. (150000) for Year 2016

3. 50000 for Year 2017

Calculation as follows:

Cost Recovery Method: Cost Incurred (Cumulative) Estimated cost to complete Total Cost to Complete Contract Fixed Price Gross

for your information and further understanding while in % of Completion method the answer would have been

% Of completion Method A B Cost Incurred (Cumulative) Estimated cost to complete Total Cost to Complete % of Completion Contr

Add a comment
Know the answer?
Add Answer to:
1- Al –Tawaan Plastics entered into a contract to install a pipeline for a fixed price...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • (25 MARKS) Highland Construction entered into a contract to to Johor Bahru. The agreed contract price...

    (25 MARKS) Highland Construction entered into a contract to to Johor Bahru. The agreed contract price was RM4 million, the position of the contract at the end of the years 2015, 2016, and 2017: into a contract to construct an express highway from Melaka RM4 million, the following table shows the 2015 RM'000 2017 RM'000 Variation to the contract price (increase) Cumulative costs incurred to date Estimated costs yet to be incurred Progress billings to date 2016 RM'000 400 1,800...

  • Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000....

    Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000. Cost information over the life of the contract is as follows: Year 2014 2015 2016 Cost Incurred During Year $2,000,000 3,500,000 1.100.000 Estimated Cost to Complete $5,000,000 1,250,000 0 Rangers uses cost-to-cost to estimate the percentage complete on the contract. Provide the amount of gross profit recognized each year using two alternative revenue recognition methods. Year Completed Contract Method Percentage of Completion Method 2014...

  • Ranger's Corp. entered into a contract to construct a factory building. The contract price is $10M....

    Ranger's Corp. entered into a contract to construct a factory building. The contract price is $10M. cost information over life of the contract is as follows 5.16 Rangers Corp. entered into a contract to construct a factory building. The contract price is $10,000,000. Cost information over the life of the contract is as follows: Year 2014 2015 2016 Cost Incurred During Year $2,000,000 3,500,000 1,100,000 Estimated Cost to Complete $5,000,000 1.250.000 Rangers uses cost-to-cost to estimate the percentage complete on...

  • In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2016, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2018. Information related to the contract is as follows: I NEED HELP RESOLVING THE EMPTY 8 BOXES BELOW (4&5). 4. Calculate the amount of revenue and gross profit to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your...

  • 1) A construction company entered into a fixed-price contract to build an office building for $20...

    1) A construction company entered into a fixed-price contract to build an office building for $20 million. Construction costs incurred during the first year were $6 million and estimated costs to complete at the end of the year were $9 million. The building was completed during the second year. Construction costs incurred during the second year were $10 million. How much revenue and gross profit or loss will the company recognize in the first and second year if it recognizes...

  • Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1,...

    Curtiss Construction Company, Inc., entered into a fixed price contract with Axelrod Associates on July 1, 2021, to construct a four-stor office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,420,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,540,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT